Ameren Corporation earnings recap
Q3 FY2026, reported November 5, 2026 · Beat 5 of last 6 quarters
Ameren Corporation reported Q3 FY2026 revenue of $2.88B, a beat of 2.1% against consensus, and EPS of $2.42, a beat of 5.7%.
The Buildout is a website built by one person using AI agents, and could have factual errors.
Ameren's plan is now explicitly anchored to data-center load: 2.8 GW of signed hyperscaler ESAs, a further 5.6 GW of firmed large-load interest, and roughly 7.7 GW of generation additions tied to a $38.1 billion five-year capital plan. The pace of that build — and the 12.9% Missouri sales CAGR it supports — depends on customer construction timelines, making it a useful read on the cadence of AI-driven load growth in the MISO Midwest. The $90 billion-plus decade pipeline, including competitive MISO LRTP transmission awards, could support demand across gas turbines, solar, storage, transmission equipment and EPC labor.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $2.82B | $2.88B | +2.1% | beat |
| EPS | $2.29 | $2.42 | +5.7% | beat |
Ameren reported third quarter 2026 GAAP earnings of $2.42 per share versus $2.35 GAAP and $2.17 adjusted in the third quarter of 2025, driven by higher sales and favorable weather, higher earnings on investments in innovative energy technologies and higher earnings on infrastructure investments. The quarter was the warmest in St. Louis in more than 50 years, with September the hottest on record; excluding weather, weather-normalized Missouri electric retail sales for the trailing twelve months ended September rose approximately 0.5%, led by the commercial customer class, while higher O&M at Ameren Missouri partially offset results. The company invested more than $4 billion in energy infrastructure through September, and grid automation investments avoided more than 63 million customer outage minutes year to date across Missouri and Illinois. Operationally, Ameren filed its 2026 Missouri Integrated Resource Plan in September, received Missouri PSC approval in October for nearly 1 GW of solar and storage resources after a five-month review, and was selected for the competitive EASL transmission project in Iowa — its first competitive transmission award outside its service territory. On the regulatory front, the Missouri electric rate review is proceeding on schedule, the Ameren Illinois 2025 reconciliation request of $28 million aligns with ICC staff and administrative law judge recommendations, and an ALJ recommended approval of the $2.7 billion Illinois multiyear grid plan with proposed downward capital adjustments of approximately $200 million.
Management raised 2026 EPS guidance to $5.35–$5.55 from $5.25–$5.45 and initiated 2027 guidance of $5.70–$5.90, with the $5.80 midpoint representing 8.4% growth off the original 2026 guidance midpoint of $5.35. They rolled forward a $38.1 billion 2027–2031 capital plan — an increase of more than 20% versus last year's plan — expected to drive 13.3% compound annual rate base growth from 2026 through 2031 and 8%–10% compound annual EPS growth from 2027 through 2031, with growth expected near the upper end of that range in 2028 and 2029 as large-load sales ramp. Missouri sales are assumed to compound at 12.9% per year from 2027 through 2031 on 2.9 GW of assumed new load by 2031, anchored by the 2.8 GW of signed electric service agreements; the preferred resource plan contemplates roughly 7.7 GW of new generation additions, about an 80% increase in installed capacity, and approximately $2.75 billion of tax credits from 2027 through 2031. Management characterized the plan as conservative — only signed ESAs and the capital needed to serve them are embedded, with the 5.6 GW of firmed large-load interest framed as upside to both sales and capex in the outer years of the plan. Financing assumes roughly $5 billion of equity issuance from 2027 through 2031, of which about $1.7 billion has already been sold forward under the ATM program, plus approximately $5.2 billion of new long-term debt in 2027. The Missouri rate review proceeds on schedule with intervenor direct testimony in early December, a PSC order expected by May 2027 and new rates effective by June 2027, and management reiterated a 45%–55% dividend payout ratio target.
“we raised our 2026 earnings per share guidance range to $5.35 to $5.55 from our original range of $5.25 to $5.45.”
on Guidance raise
“we are developing a balanced and diverse portfolio that includes adding approximately 7.7 gigawatts of new generation capacity from 2027 through 2031, which would increase Ameren Missouri's installed capacity by approximately 80%.”
on Generation buildout
“Over time, if we're able to sign additional ESAs, I look at it as really strengthening the EPS growth rate in the outer years of this 5-year plan and lengthening the period of this strong growth.”
on Upside from additional ESAs
The gap between EPS CAGR and rate base CAGR has widened versus the last update — what's driving it, is it structural, and could it narrow over time?
The delta is primarily financing: the $38.1 billion capital plan will be funded in a balanced way consistent with history, including roughly $5 billion of equity issuance over five years, of which about $1.7 billion is already priced through forward hedging. That equity dilution is the primary driver of the difference between rate base growth and expected EPS growth.
2027 guidance implies just over 8% growth — can you share the cadence of growth through the new planning period relative to the 8% to 10% range?
The $5.80 midpoint is 8.4% growth off the original 2026 guidance of $5.35, delivering on the prior commitment to hit the upper end of the old 6%–8% range. Both sales growth and rate base growth step up in 2028 and 2029 as hyperscaler load ramps and capital is deployed, supporting growth near the upper end of the 8%–10% CAGR; the plan only incorporates signed ESAs and the capital to serve 2.9 GW of sales, leaving upside from the additional 5.6 GW of firmed large-load interest and the IRP upside case.
With the incremental opportunity beyond the ~3 GW already signed, how do you manage construction risk given sector-wide E&C constraints — can you handle the totality of what's in hand?
Management pointed to secured long-lead materials — turbines and generators for the 2027 simple-cycle unit are already on their pads, Big Hollow has an EPC contract with the same builder, and West Alton has a construction agreement with Alberici and McCarthy plus Sargent & Lundy as engineer of record — along with standardized designs across the renewables and battery program and added project oversight. Lyons added that Missouri had no gubernatorial election, Illinois reelected Governor Pritzker, commissions are not elected and legislative majorities were unchanged, so relative energy policy stability is expected; long-lead commitments have already been made for resources outside the current capital plan.