Fervo Energy Company earnings recap

Q3 FY2026, reported November 9, 2026 · Beat 0 of last 2 quarters

Fervo Energy Company reported Q3 FY2026 revenue of $116K, a miss of 12.3% against consensus, and EPS of $-0.07, a beat of 18.7%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Fervo Energy Company company page →See the earnings preview →Fervo Energy Company is in the Utilities & Energy layer →
What this means for the buildout

Fervo has crossed from pilot-stage concept to a revenue-generating 24/7 firm power asset, and the 396 MW Google take-or-pay — with a separate ~600 MW behind-the-meter option under SB132 — is a template for how hyperscaler load can be served without either side waiting on the other. The lowered second-half 2026 CapEx on an unchanged $2.2B project budget suggests construction productivity gains are real, though the shift of dollars to the right also means the cash-out curve now leans harder into 2027–2028. The near-doubling of Cape's assessed heat-in-place to 8.4 GW indicates drilling-driven resource expansion, the same dynamic that extended shale inventory, which could matter for how much firm capacity sits behind future data center contracts.

Results vs consensus
EstimateActualvs est
Revenue$132K$116K-12.3%miss
EPS-$0.09-$0.07+18.7%beat

These figures come from the same table as our earnings calendar. The write-up below may quote the company's own adjusted or reported figures, which can differ.

What was said

Fervo declared commercial operation of its first 33 MW GeoBlock at Cape Station on September 30, ahead of the contractual deadline, after 23 months of construction, and said brine is arriving at design flow rates and temperatures with power being sold under the PPA. GeoBlock 2 has reached grid sync and is exporting test energy, GeoBlock 3 is in cold commissioning, and both remain on track for commercial operation by January 1, 2027. The company signed a 15-year, 396 MW take-or-pay PPA with Google (Cape Google 400) with parent guarantees from Fervo and Alphabet, structured as grid-connected capacity, plus an approximately 600 MW behind-the-meter expansion option under Utah's SB132. Drilling for GeoBlocks 4 through 11 is about 18% complete with four H&P Flex 3 rigs running, and first 50 MW turbines have passed factory acceptance testing. Q3 financials were pre-revenue at the project level: G&A of $39.4M (including ~$14M stock comp), operating loss of $43.7M, net income of $11.7M aided by $15.4M interest income, an $11.8M swap gain and a $29.9M tax benefit, with $1.9B of unrestricted cash and $301.6M of debt.

Key metrics
Contracted backlog
1,054 MW / $11.9B
Up 396 MW (~60%) QoQ with the Google PPA; backlog was 658 MW / $7.2B at the time of the May IPO
GeoBlock 1 commercial operation
33 MW
COD declared Sept 30, 2026, ahead of contractual deadline; grid sync Sept 24; built in 23 months
Cape Google 400 PPA
396 MW
15-year take-or-pay in four 99 MW tranches targeted mid-2028, plus a ~600 MW behind-the-meter expansion option
H2 2026 CapEx
$700M–$750M
Cut from prior $850M–$900M expectation; Q3 CapEx was $256.7M, Q4 guided to ~$450M–$500M
Cape Station heat-in-place
8.4 GW
DeGolyer & MacNaughton update nearly doubles the prior 4.3 GW estimate — roughly 18x the MW under construction
Management outlook

Management kept its forward revenue commentary unchanged rather than issuing new numbers: Q4 2026 revenue is expected "in line with" the Q2 call, and 2027 expectations are also unchanged (an analyst on the call framed the maintained 2027 range as $60M–$80M without correction). The operating cadence was reaffirmed — GeoBlocks 2 and 3 in commercial operation by January 1, 2027, putting roughly 100 MW in service, with all eight Cape Google 400 units (400 MW) online by the end of 2028. CapEx guidance for the second half of 2026 was effectively lowered to $700M–$750M from $850M–$900M, not because the $2.2B Cape Google 400 budget changed but because construction sequencing pulls spend closer to the 2028 revenue dates; project finance for that project is expected to be ready around mid-2027 at roughly 70% loan-to-value. On cost, management reiterated $5,500/kW installed CapEx for GeoBlocks 4 through 11 against a long-term $3,000/kW target, with the 3.0 well design (7,500-ft laterals, 8 5/8-inch casing, ~430°F reservoir) deemed sufficient to get there without moving to larger casing. Longer-term markers moved up: the 2030 capacity target was raised from 1 GW to 1.1 GW, estimated resource potential from ~40 GW to over 58 GW, and early development from 48.6 GW to 54.7 GW. Management also stressed that its growth plan does not depend on pending federal legislation such as BAAJA, though passage would be additive on permitting and transmission.

From the call

“GeoBlock 1 has given us the playbook. It has taught us about commissioning sequence, equipment and controls, contract coordination and regulatory approvals. We've run that playbook once, and now we run it repeatedly, improving each time we do.”

on Repeatable GeoBlock delivery model

“It lowers project on project risk. We build Cape station on our schedule. Google can develop a potential data center on their schedule and neither party is waiting on the other.”

on Google PPA structure

“the overall construction budget is not changing. What is changing is the time with which we deliver that same amount of CapEx. And so by pushing dollars to the right closer to when we generate revenue, just by taking advantage of time value of money, we're already improving returns.”

on CapEx timing and returns

What analysts asked

Where are you on the CapEx path from $7,000/kW down to $5,500/kW at Cape Google 400 — how much is subsurface versus surface, how is drilling progress tracking, and does the larger DeGolyer & MacNaughton heat-in-place estimate change the per-well math on Cape?

Latimer said subsurface and surface can't really be disentangled in geothermal, but the ~30°F higher target temperature is the overarching lever — more energy per unit of brine flow means fewer wells and a more efficient plant, which is how the design went from 33 MW net to 50 MW net per GeoBlock. Drilling days versus depth and completion metrics are tracking expectations, supporting the $5,500/kW target. He said the heat-in-place study reflects credit for deeper drilling rather than a design change; the Cape Google 400 well plan is unchanged.

How should investors think about water loss and thermal decline — how much can you extrapolate Project Red's behavior to Cape Station, and what gives you confidence in long-term performance?

Latimer said water stewardship drove design choices — dry cooling only, no evaporative cooling, and targeting deeper brackish zones rather than freshwater — and early Cape data shows minimal freshwater use, no material OpEx impact, and permitted volumes that support years of expansion. On thermal decline, he said the observed decline at Red after a stable period was expected, that the data is now proprietary to Fervo, and that no one else has three years of operating history to test mitigation techniques. Cape is a different, returns-oriented resource with longer laterals, better spacing, larger casing and higher temperatures, and early Cape flow and temperature data are within modeled expectations.

On the ~600 MW option with Google, when does Google have to decide, given 550 MW ready-to-build and over 8 GW of capacity potential at Cape?

Latimer said capacity is not the constraint — there are multiples of the 600 MW available at Cape. The timing depends on working through the various requirements to build a data center, and he expects Google to continue making progress on that into 2027.

Potential supply chain impact
DVNThe partnership is framed around geoscience, horizontal drilling and completions expertise; Fervo's scaling from two to four rigs and its 18%-complete GeoBlocks 4–11 drilling program could indicate continued reliance on partners with shale-style subsurface capabilities, though no direct financial contribution is disclosed.