Hallador Energy Company earnings recap
Q3 FY2026, reported November 9, 2026 · Beat 4 of last 6 quarters
Hallador Energy Company reported Q3 FY2026 revenue of $130M, a beat of 10.1% against consensus.
The Buildout is a website built by one person using AI agents, and could have factual errors.
Hallador is monetizing the scarcity of accredited dispatchable capacity rather than the data center credit trade directly — its October sale was to an investment-grade utility at over $80/MWh with fuel risk carried by the customer, and roughly 95% of Merom's accredited capacity is now contracted through 2035. The Turtle Creek decision to proceed on turbines and interconnection ahead of signed offtake is an explicit bet that grid access and equipment, not buyers, are the binding constraints through 2028. Management's comments that MISO's traditional queue is backlogged for years, turbines are sold out through 2030 and beyond, and projects displaced from other states are routing to Indiana support a multi-year tightness read for behind-the-meter-adjacent dispatchable supply in MISO.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $118M | $130M | +10.1% | beat |
| EPS | $0.08 | -$0.10 | — | Not comparable |
EPS: The gap is too large to be a like-for-like comparison (the estimate and the result may be on different bases), so we do not call it a beat or a miss.
Merom generated more than 1.4 million megawatt hours in the quarter, up 77% sequentially, with one unit in scheduled outage for part of the period and some post-outage teething issues that resolved; availability was 74% for the quarter and 80% in August and September. Total operating revenue was $130.3 million versus $146.6 million a year ago, with electric sales of $92.8 million versus $93.2 million (accredited capacity revenue up 21% to $18.7 million, offsetting a $3.6 million decline in delivered energy revenue) and third-party coal sales of $36.1 million versus $51.3 million on roughly 400,000 fewer tons sold. Net loss was $4.5 million, including a $5.7 million loss on extinguishment of debt from the credit facility refinancing, adjusted EBITDA was $17.3 million versus $24.9 million a year ago, and cash flow used in operations was $21.8 million. Capital expenditures were $57.1 million versus $19.4 million a year ago, reflecting Turtle Creek development and Merom reliability work, while Sunrise produced about 0.9 million tons at an average cost per ton sold of $52.17 versus $42.74. In October the company signed its third large Merom sale of the year — roughly $700 million over six years starting in 2029 at over $80/MWh — and in September closed a $600 million senior secured construction bridge term loan that lifted total bank debt to $550 million.
Management is targeting a final investment decision on Turtle Creek before year-end, subject to Board approval, as it finalizes the engineering and construction agreement and equipment bids, with commercial operation still targeted for the second half of 2028; the MISO expedited interconnection study is complete but the interconnection agreement is not yet executed, and long-term contracts for the plant's output are targeted for early 2027, potentially structured as tolling arrangements where customers bear gas cost. Financing is framed around the $600M construction bridge plus a $75M super priority revolver in late-stage negotiations (roughly $55M of additional availability), with the remaining capital from debt, project financing, equity or a sale of part of Turtle Creek under a stated objective of little or no shareholder dilution. CFO Todd Telesz warned that reported earnings will carry the full interest expense of a plant that is not yet earning, that "the reported losses will likely widen before the plant runs," and that cash interest is 3.5% on the drawn balance (about $19.3M a year), encouraging investors to model cash. On the contracted book, blended capacity and energy pricing rises from $46/MWh for the rest of 2026 to $59 in 2027, $73 in 2030 and $75 for 2031 through 2035, with capacity prices moving from $262 per megawatt day in 2027 to $478 in 2029. Management also pointed to higher coal pricing and higher volumes next year, saying it is encouraged about 2027 earnings potential, while targeting roughly 5.2 million MWh of annual Merom generation and platform capex that is relatively flat next year.
“The AI race is really about which companies can get enough power, and we are in that race as the supplier to the utilities.”
on AI power demand
“I want to be very clear about one point. We sold to an investment-grade utility, not a data center. Data centers may be driving nearly all the growth in utility load, but our counterparty is an investment-grade utility that serves its whole territory, and it pays us whether any particular data center gets built or not.”
on Counterparty credit risk
“As Brent mentioned, until Turtle Creek reaches commercial operations, reported earnings will carry the full interest expense of a plant that is not yet earning. Most of it is accrued rather than paid. The reported losses will likely widen before the plant runs.”
on Earnings bridge to commercial operation
With a larger pool of Turtle Creek offtake counterparties, is an investment-grade utility the ideal counterparty, or does it come down to taking the best economics?
Brent Bilsland said it is always about the best deal, balancing the price a customer will pay against that customer's credit risk, and noted that the majority of Hallador's contracts are with investment-grade utilities that have been very reliable. He added that because Turtle Creek is gas, it simply has a wider universe of potential customers.
Walk back through the ways to value Merom/Turtle Creek and identify which of the value buckets is most conservative and what assumptions underlie them.
Brent Bilsland clarified the discussion was about Turtle Creek, framing a path from roughly an $800 million project to about $1.6 billion of value over 24 months across four steps: equipment acquisition, permits and entitlements, contracts, and construction, with each step potentially contributing about $200 million above cost. He said the company is nearly complete with two of the steps, cited the June TransAlta transaction as a recent public mark for contracted gas generation while cautioning that it is a different asset and that markets change, and said selling part or all of the asset is on the table if the equity does not reflect full value.
If the engineering and construction contract and the interconnection agreement slip into 2027, does that put the second-half 2028 commercial operation timeline at risk?
Brent Bilsland replied that the second half of 2028 remains a high-conviction target.