NiSource Inc earnings recap
Q3 FY2026, reported October 28, 2026 · Beat 6 of last 7 quarters
NiSource Inc reported Q3 FY2026 revenue of $1.37B, a beat of 0.6% against consensus, and EPS of $0.27, a beat of 17.9%.
The Buildout is a website built by one person using AI agents, and could have factual errors.
NiSource is converting a regulated utility footprint into a large-load power supplier: 5 GW of signed data center capacity with a third hyperscaler added, a $40 billion seven-year capital plan, and a Genco structure designed to fund generation and transmission for Amazon, Alphabet and Microsoft. The economics matter for the buildout because the model routes savings back to retail customers (~$1.75 billion, ~$140 per year at full ramp) while keeping Genco assets outside the electric rate base, which could give regulators a template for approving more data center load. The 2 GW in active negotiations plus 2 GW in development, and management's indication that the pipeline exceeds 9 GW, suggests follow-on generation, battery and transmission work into the 2030s.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $1.34B | $1.37B | +0.6% | beat |
| EPS | $0.23 | $0.27 | +17.9% | beat |
NiSource reported third quarter consolidated adjusted EPS of $0.27 versus $0.19 a year earlier, bringing year-to-date adjusted EPS to $1.49, driven by disciplined cost management and higher usage and customer counts at NIPSCO, Columbia Gas of Ohio, Virginia and Kentucky, partially offset by higher O&M from storm response. The quarter included an August 11 derecho across northern Indiana with wind speeds up to 110 mph, one of the most severe weather events in NIPSCO's history; more than 1,700 external personnel joined internal teams within 24 hours and broad restoration was completed by August 25 without injury, with an internal after-action review expected by late November and the company is hiring a third-party expert to conduct an independent review over the next several months. Regulatorily, Columbia Gas of Ohio filed its first three-year forward-looking rate case under the SB 103 framework, Kentucky and Virginia cases remain on schedule with new Virginia rates effective October 12 subject to refund and decisions expected in the first half of 2027, and NIPSCO received a fourth federal order requiring continued operation of the Schahfer coal units. The company signed a 20-year Microsoft electric service agreement starting in 2028, its third Genco customer and fifth agreement in just over a year, raising expected savings to existing NIPSCO electric customers to approximately $1.75 billion, and issued $750 million of junior subordinated notes in August. Alphabet transmission infrastructure was completed ahead of schedule with billing beginning this summer, and construction continues on the Amazon site, described as the largest infrastructure project in company history, including a 345 kV delivery substation and associated transmission expected in service next year.
NiSource narrowed 2026 consolidated adjusted EPS guidance to the upper half of its previously stated $2.02 to $2.07 range and initiated 2027 guidance of $2.22 to $2.30, which implies double-digit growth at each midpoint and includes $0.05 to $0.09 of Genco contribution. The company extended its plan to 2033, targeting a 10-11% consolidated adjusted EPS CAGR with the base plan delivering 6-8% annual growth and Genco layering on top — $0.32 to $0.40 of EPS contribution in 2030 rising to $0.52 to $0.68 by 2033, the first year of full customer ramp. Management said the larger plan reduces average annual residential bill increases by more than 100 basis points to less than 4% from 2027 through 2031, and that over 90% of investments convert to initial recovery within 12 months. Financing assumes $400 million to $600 million of annual maintenance equity in the near term, stepping down to minimal levels starting in 2032, with FFO to debt held at 14-16%. On demand, management cited 5 GW of signed capacity, 2 GW in active strategic negotiations and 2 GW in developing opportunities within a 9 GW pipeline, said the pipeline is larger than 9 GW, and expects to share an upsizing study sometime in 2027. The Microsoft special contract is expected to be filed with the IURC by year end with an order sought in the first half of 2027, and management flagged potential storm hardening and resiliency capital that has not yet been quantified.
“With our recently announced Microsoft agreement, Genco now serves 3 of the largest technology companies in the world, and brings our signed agreements to an expected $1.75 billion in savings to existing NIPSCO electric customers.”
on Genco customer base and customer savings
“Today, we initiated our 2027 adjusted EPS guidance at $2.22 to $2.30 per share which implies a double digit year over year growth next year at each midpoint, including $0.05 to $0.09 of contribution from our Genco business segment.”
on 2027 guidance
“The moves we made with the CCGTs do that for Amazon. They help to ensure higher confidence of execution and modifying those in a way. But it is not a delay in schedule. it is actually an optimization.”
on Amazon CCGT sequencing
Does the Microsoft agreement largely capture the opportunity with them, or should we view it as a first phase of something larger?
Michael Luhrs said the company cannot comment on customer sites or their size, but that it is actively engaged with all three major customers and with customers in the queue. Lloyd Yates added that there is a lot of demand in that queue and expressed confidence in the company's ability to execute on the pipeline.
How is the strategic review of Genco progressing, does it need to be completed before executing on the remaining 4 gigawatts, and could it come sooner?
Lloyd Yates said the review does not need to happen before executing on the next 4 GW, noting 2 GW is currently in strategic negotiations with 2 GW behind that. He said the company is studying how to upsize and expects to roll that out sometime in 2027, and is optimistic.
With the Amazon CCGT shifting to 2030, what drove that, how will Amazon be served in the meantime, and who bears the incremental cost?
Michael Luhrs said there are two CCGTs and only one changed, with batteries coming online ahead of it and a pool portfolio used to optimize how customers are served while de-risking construction; he characterized the moves as an optimization rather than a delay, with some elements accelerated. Shawn Anderson added that capital requirements were unchanged in the disclosures and that pricing signals are still set off the customer ramp rate.