NWPX Infrastructure, Inc. earnings recap

Q3 FY2026, reported October 28, 2026 · Beat 6 of last 7 quarters

NWPX Infrastructure, Inc. reported Q3 FY2026 revenue of $179M, a beat of 6.9% against consensus, and EPS of $1.86, a beat of 12.7%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full NWPX Infrastructure, Inc. company page →See the earnings preview →NWPX Infrastructure, Inc. is in the Cooling layer →
What this means for the buildout

The data center read here is second-order but real: a water-infrastructure manufacturer is now booking >$11M of data center precast orders on $33.5M quoted, with individual projects scaling from a few hundred thousand dollars to $3M-$5M, which may indicate data center siting is pulling in conventional civil and stormwater/wastewater product demand alongside the electrical and thermal build. At the same time, the record $435M WTS backlog and ~$144M of Q3 bookings are tied to municipal drinking water and wastewater programs rather than compute, so the durable signal is that public water infrastructure spend is running in parallel with — and increasingly intersecting — the data center construction cycle.

Results vs consensus
EstimateActualvs est
Revenue$168M$179M+6.9%beat
EPS$1.65$1.86+12.7%beat
What was said

NWPX reported record consolidated net sales of $179.4M (+18.7%), record gross profit of $38.2M (+18.8%) at a 21.3% margin, and net income of $18.2M, or $1.86 per diluted share, up 35%. WTS set records for revenue ($131.9M, +27%) and gross profit ($27.3M, +23.4%) at a 20.7% segment margin, down 60 bps YoY on production mix though up ~180 bps year-to-date; the NDA project contributed roughly $31M of revenue in the quarter. Precast revenue was $47.5M (+0.6%) on 4% lower volume and 3% higher pricing, with gross margin up 160 bps to 22.9%; order book was $67M including $10M from Serpentix, with the legacy book at $57M versus $61M at June 30 and $55M a year ago, and some customer shipments were delayed. The company closed the $49.7M Serpentix acquisition in September (about $1M of Q3 revenue, one partial month), generated $20.4M of free cash flow ($56M year-to-date) and $27.4M of operating cash flow, and repurchased $1.2M of shares. Steel represented roughly 28% of COGS in the quarter, and management said steel lead times remain extended but have begun to moderate.

Key metrics
Consolidated net sales
$179.4M
Record; up 18.7% YoY from $151.1M, driven by Water Transmission Systems strength
WTS backlog (incl. confirmed orders)
$435M
Record; up from $423M at June 30 and $301M a year ago, and grew even while working through the NDA project
WTS segment revenue
$131.9M
Quarterly record, +27% YoY from $103.9M; tons produced +7%, selling price per ton +19% on mix
Diluted EPS
$1.86
Net income $18.2M, +35% YoY; highest quarterly EPS in company history excluding the 2018 one-time bargain purchase gain
Data center orders booked YTD
>$11M
Against $33.5M quoted through Q3 in Precast; roughly $7M shipped so far this year
Management outlook

Management expects Q4 consolidated performance to be stronger than both Q4 2025 and Q1 2026, despite typical holiday and weather seasonality, and said the strength of orders already in hand validates the quarter. In WTS they expect backlog to remain elevated through year-end, full-year base bidding (excluding the NDA project) to exceed 2025 levels, and additional NDA contribution in Q4 with some of the roughly $16M remaining possibly bleeding into early 2027; they noted the business would have set a record in 2026 even without that project, with nine-month WTS revenue up about 10% (and 12% on another stated basis) ex-NDA. Precast is guided to be steady versus Q3, with 2026 still expected to be a record revenue year, supported by a $67M order book (including $10M from Serpentix) and continued data center fill-in. CFO Aaron Wilkins tightened expense and cash guidance: SG&A $55M-$56M, D&A $22M-$23M, tax rate 23%-24%, capex $21M-$23M, and free cash flow raised to $62M-$72M from the prior $56M-$65M. The tone was confident to the point of superlative, with the CEO saying he has never seen this much momentum in WTS heading into a fourth quarter, and management listing margin over volume, M&A, cost efficiencies and shareholder returns as near-term priorities.

From the call

“I think I can safely say that I have never seen this much momentum on the Water Transmission Systems business heading through the fourth quarter and into next year.”

on WTS demand momentum

“Right now, just in the state of Texas, there's 49 data centers that are under construction, and there's another 114 that are planned, and 72 of those are in the pre-construction phase.”

on Data center pipeline

“We currently have a cash conversion cycle for that business that is around 99 days. To put in perspective, a year ago, for which I thought we were pretty strong on the pre-bills and really kind of driving those contract liabilities through, we were at 150 days.”

on Working capital and cash conversion

What analysts asked

On Precast, you quoted $33.5M of data center projects and booked over $11M year-to-date — how much has shipped versus what's in the order book, what does the quoting pipeline look like into 2027, and how does the margin profile compare with traditional Precast work?

Margins on data center work are generally higher than normal Precast orders, which Scott attributed to the speed customers expect; roughly $7M has shipped this year, with several relatively large projects still being converted to orders, and quoting, booking and shipping should all move higher from here. He framed data centers as filling gaps left by soft residential and commercial — Geneva was historically ~85% residential but is ~40% residential this year, with the rest filled by non-residential and data center orders.

On data centers, when you think about going into next year, how much larger could these project sizes be than the historical commercial or institutional work?

Scott said data center bids have historically been $300,000-$400,000 projects, but projects currently in front of the company that it is trying to convert are as large as $3M-$5M. He referenced 49 data centers under construction in Texas, 114 planned and 72 in pre-construction, noting some political slowdown, and said 2027 could be even larger than this year on the data center side, adding to total Precast revenue potential.

On the NDA opportunity — if the total was roughly $50M and $39M of revenue landed in the last two quarters, does the remaining ~$11M all ship in Q4, or does some bleed into 2027 and does the total opportunity scale down?

Scott said total project value was about $56M, with roughly $40M done through Q2 and Q3; some of the remaining $16M should be recognized in Q4, but how much depends on how fast the contractor can take it, and some may bleed into early 2027. He said there are rumors of additional NDA-type projects but nothing the company has seen, and that ex-NDA the business is up 10%-12% through nine months, with Q3 conversions of about $144M into backlog and Q4 shaping up as the second-largest bidding quarter of the year.

Potential supply chain impact
NUESteel was roughly 28% of Q3 COGS, management said lead times remain extended but are moderating, and steel in backlog is being priced around $1,300/ton entering Q4; a record $435M WTS backlog could support continued mill pull, though moderating lead times may ease the pricing tailwind embedded in project bids.
STLDNWPX credits longstanding domestic mill relationships for reliable steel access; with Q4 described as the second-largest bidding quarter of the year and most 2027 production already in backlog, incremental plate/coil needs may follow, though the mix and timing of awards remain uncertain.