ProPetro Holding Corp. earnings recap

Q3 FY2026, reported October 28, 2026 · Beat 5 of last 7 quarters

ProPetro Holding Corp. reported Q3 FY2026 revenue of $355M, a beat of 10.9% against consensus, and EPS of $0.09, a beat.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full ProPetro Holding Corp. company page →See the earnings preview →ProPetro Holding Corp. is in the Power Systems layer →
What this means for the buildout

ProPetro's quarter gives the behind-the-meter power thesis a data point that is no longer purely forward-looking: roughly $8 million of PROPWR adjusted EBITDA, ~510 MW under contract, and a hyperscaler site already operating with reciprocating gas engines. The 2.6 GW of secured equipment, including over 1 GW of 10-MW Caterpillar units, suggests equipment access rather than demand may be the pacing item for new behind-the-meter capacity into 2028, while the company's own warning that 2027 earnings skew to the second half and that reservation fees lag deployment is a reminder that revenue recognition can trail contracted megawatts. The simultaneous sell-out of the frac fleet and H1 2027 repricing window also implies the cash-generating completions core may be entering an upcycle just as the power buildout consumes capital.

Results vs consensus
EstimateActualvs est
Revenue$320M$355M+10.9%beat
EPS-$0.01$0.09n/mbeat
What was said

ProPetro reported third quarter revenue of $355 million (up 16% sequentially), net income of $13 million or $0.09 per diluted share, and adjusted EBITDA of $60 million, 17% of revenue and up 33% sequentially, driven by higher completions utilization and incremental PROPWR deployments and partly offset by rebuild costs. PROPWR generated approximately $8 million of adjusted EBITDA, and contracted capacity reached roughly 510 MW with the ~230 MW Targa award; the first data center deployment, built largely on 2.6-MW units, is live in the Midwest. Completions reactivated a 13th fleet earlier than planned and is now essentially sold out of available frac capacity; the ramp required rehiring field personnel, restocking inventory and spare parts, and added pressure on maintenance shops, which weighed on margins. Capital expenditures incurred were $171 million ($43 million completions, $128 million PROPWR) versus $123 million paid, operating cash flow was $46 million after roughly $15 million of working capital consumption, and the company ended the quarter with $729 million of cash and $934 million of total liquidity.

Key metrics
Total revenue
$355M
Up 16% sequentially from $306M in Q2 2026, with both completions and PROPWR contributing higher revenue
Adjusted EBITDA
$60M
17% of revenue, up 33% sequentially; includes approximately $16M of lease expense tied to the electric frac fleets
Net income
$13M
$0.09 per diluted share, versus a net loss of $8M ($0.07 per share) in the prior quarter
PROPWR adjusted EBITDA
~$8M
Meaningful sequential step-up; project-level results and margins continue to meet internal expectations
Contracted power capacity
~510 MW
Includes the recently announced ~230 MW Targa agreement; backed by ~2.6 GW of secured generation equipment, over 1 GW of it 10-MW Caterpillar units
Management outlook

Management laid out a stair-step path for PROPWR: roughly 250-275 MW deployed by the end of 2026, stepping up to more than 500 MW by early 2028, with additional data center awards incremental to that 500 MW and potentially deploying as early as late 2027. Because larger projects require personnel, site preparation and mobilization to build ahead of revenue, 2027 earnings are expected to be weighted toward the second half. Full-year 2026 capital expenditures incurred are guided to $525M-$575M, with the PROPWR portion narrowed to $400M-$430M on better year-end visibility into equipment delivery timing, while the $1.4M-$1.5M per megawatt cost and four-to-six-year payback targets are unchanged; 2027 PROPWR capex is expected to rise from 2026 levels as Caterpillar framework deliveries and milestone payments ramp. In completions, they expect to hold roughly 13 active fleets in Q4 but flagged meaningful holiday seasonality and continued margin pressure from rebuild costs, with the shift from rebuilding to optimizing costs targeted for 2027 as activity stabilizes. More than two-thirds of active horsepower is contracted, with most renewals in the first half of 2027, and management said early pricing momentum is already showing up in those conversations. They also cautioned that cash reservation fees on certain PROPWR contracts will not be recognized in revenue or adjusted EBITDA until assets are deployed and generating power, so reported results may trail contracted capacity in a given period.

From the call

“Importantly, we are currently deployed and operating on a hyperscaler project and execution is exceptionally well. We are one of the very few behind-the-meter power providers live on a data center site today, and we believe this operating track record validates our strategy and has helped accelerate our broader growth.”

on Live data center deployment

“Our fleet is essentially sold out. Demand is very high, and we are turning away opportunities today because we do not have the capacity to serve them.”

on Completions capacity sold out

“In short, demand is poised to grow and supply is not. This bodes well for our long-term setup for our services.”

on Permian frac supply and demand

What analysts asked

Where are you in conversations with data center customers on contracts, and how should we think about the timing of signing relative to ordering balance of plant and deployment starting late 2027 or early 2028?

Travis Simmering said a data center contract would be incremental to the 500 MW, which reflects the 510 MW already contracted and guided for deployment in early 2028. He said conversations remain positive and headed toward execution despite broader turmoil in the data center market, that balance of plant equipment is already being ordered with line of sight to project-specific needs, and that deployments could come late 2027 but at scale in 2028.

What are the different drivers lengthening the negotiation process on large power projects — community pushback, moratoriums, or commercial terms — and does the existing 60-MW data center project help de-risk contracting?

Travis Simmering said it is not pushback but real contract risk exposure on both sides, including liability damages over long durations on large installations, plus getting project scope right between the parties; the initial 60-MW contract gives a useful starting point, but larger and longer deals carry far more scrutiny. Sam Sledge added that the team runs several opportunities in parallel that can affect one another, and that a few weeks or a month longer to secure the right deal with the right risk-sharing is a tradeoff the company accepts.

How many distinct projects make up the several hundred megawatts in advanced negotiations, and do data center operators want behind-the-meter providers to supply balance of plant or just lease the generation?

Sam Sledge said it is definitely more than one opportunity, with two really active in that several-hundred-megawatt range, and that the company has narrowed focus to the most realistic, executable deals given available timelines. On balance of plant, he said it is a necessity — transformers, upfront gas conditioning and distribution, and emissions control — with battery system responsibility decided project by project; ProPetro is providing a full turnkey service rather than dry leasing, with a model built on operating and maintaining assets 24/7.

Potential supply chain impact
CATOver 1 GW of ProPetro's secured 2.6 GW is Caterpillar 10-MW reciprocating engines under the strategic framework agreement, with deliveries of the 10-MW units starting in the back half of 2028 — engine availability and delivery cadence could remain the gating factor for behind-the-meter data center capacity and may be a read on demand for Cat's stationary gas gensets.
XOMExxon Mobil accounted for 24.9% of FY2025 revenue; management's expectation of additional public and independent rig additions late this year into 2027 and a sold-out frac fleet could support higher completion service demand, though the benefit depends on whether those rigs convert to completed wells.
OXYOccidental accounted for 13.7% of FY2025 revenue; with most of ProPetro's contracted horsepower repricing in the first half of 2027, sustained Permian activity from large independents may influence how much of that pricing uplift is realized.