X-Energy, Inc. Class A Common Stock earnings recap
Q3 FY2026, reported November 12, 2026 · Beat 0 of last 3 quarters
X-Energy, Inc. Class A Common Stock reported Q3 FY2026 revenue of $66M, a beat of 7.9% against consensus, and EPS of $-0.14, a miss of 31.0%.
The Buildout is a website built by one person using AI agents, and could have factual errors.
X-Energy's quarter is a licensing and commercial-conversion story rather than a revenue story: an NRC construction permit for an industrial process-heat project, a second Amazon-backed utility deal, and a fuel facility moving to equipment installation are the gating items that would turn a 144-reactor pipeline into steel, concrete and fuel orders. Management's insistence that the NRC is no longer the pacing item, and that graphite, forgings, tubing and HALEU capacity are, points to where the real buildout bottlenecks sit for the advanced nuclear chain. The roughly $1.8 billion balance sheet with no debt gives the company room to keep pre-funding long-lead supply capacity on behalf of customers that have not yet taken final investment decisions.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $61M | $66M | +7.9% | beat |
| EPS | -$0.11 | -$0.14 | -31.0% | miss |
Total revenues and grant income were $66.3 million, up 118% year over year, split between $51.5 million of services revenue — mostly Xe-100 design work under the Advanced Reactor Demonstration Program — and $14.8 million of grant income tied to the Dow demonstration reactor. Total operating expenses were $169.9 million, up 139%, comprising $93.6 million of direct costs and $76 million of SG&A, of which $22 million was noncash equity-based compensation; SG&A also carries expensed TX-2 design and site preparation costs. The NRC issued a construction permit to Long Mott Energy, a Dow subsidiary, for the Seadrift, Texas project more than a month ahead of schedule — described as the first NRC construction permit for a high-temperature gas-cooled reactor in nearly 60 years and the first ever pebble-bed gas reactor approval. In October the company announced a joint development agreement with AEP for a 12-unit, roughly 960 MW Xe-100 project in Sullivan County, Indiana supported by Amazon, its second announced deployment opportunity with Amazon after Energy Northwest. Vertical construction of TX-1 at Oak Ridge was completed on schedule, the Xe-100 was accepted into the U.K. Generic Design Assessment, and phased renovations continued at the XTAC facility in Frederick, Maryland. The company ended September with $1.8 billion in cash and investments and no debt, with $51.2 million of net cash used in operating activities and $71.8 million of capital expenditures, of which DOE reimbursed $27.8 million in cash during the quarter.
Management did not issue financial guidance, but laid out a dense forward calendar. Dow is expected to weigh a preliminary investment decision during 2027, with full-scale construction to follow a final investment decision; the Xe-100 design will be completed before construction begins, but not before that preliminary decision, and Clay Sell said Dow runs a formal gated process requiring sufficient engineering, met cost targets and validated O&M assumptions. The AEP/Amazon joint development agreement for a 12-unit, roughly 960 MW project on a former coal site in Sullivan County, Indiana covers early scope — site characterization, feasibility work and preparation for a future construction permit application — with commercial terms between Amazon and AEP still being outlined. Energy Northwest remains a future licensing project, the Xe-100 is now in the U.K. Generic Design Assessment alongside a Centrica partnership exploring up to 6 GW, and TRISO-X moves into interior build-out and equipment installation at TX-1 while TX-2 and TX-L advance in design. Sell said the NRC has unofficially signaled a goal of 6 to 12 months for subsequent applications versus the 17 months it took to docket-and-issue for Dow, and repeatedly argued regulatory approval is not on the critical path — supply chain is, which is why the company is pre-buying long-lead material. Management said it will roll out 2027 milestones "in the near future" and expects to name a successor to retiring TRISO-X President Joel Duling in the coming months.
“Regulatory approval is not on the critical path for any of our projects.”
on Licensing risk
“And so we've chosen to make some early investments to secure capacity and to buy early material with the full expectation that when our customers reach their investment decisions, they will take over those obligations on a go-forward basis.”
on Supply chain pre-investment
“We'll get the engineering and design work done before we start construction.”
on Cost and schedule discipline
What needs to happen to get Dow to a preliminary FID, and will preliminary FID be the 2027 milestone for the Dow project or are there other items on that list?
Sell said Dow runs a proprietary, formalized gated decision process requiring that an appropriate amount of engineering be done, cost targets be met and O&M assumptions be validated, with decisions taken through Dow's procurement process to its board. He said X-Energy has a good view that this happens over the course of 2027 and that Dow will provide further guidance as appropriate; the timing is Dow's process, fed by inputs from both sides.
On procuring long-lead materials to get ready to build, what are the key challenges and what should investors watch?
Sell said the strategy is to reach scale quickly, which requires early investments so that graphite, steel forgings, enriched material and steam generator tubes are available in the needed capacity at the needed time. He pointed to secured capacity with Doosan Enerbility for large steel components, graphite capacity reservations and material from Toyo Tanso and SGL, and early steam generator tube material from Alleima, with the expectation customers take over those obligations once they reach their investment decisions.
The Dow construction permit came ahead of schedule — is that replicable for future projects, could it be even faster, and what is the aspiration for the next application?
Sell said yes and yes: the nuclear island and nuclear steam supply system, where all safety-related systems sit, is the same package for the first and subsequent plants, so the engineering and safety analysis is replicable for Energy Northwest, AEP and beyond. The Dow permit took 17 months from docketing to issuance; he said the NRC's stated objective is to get to roughly 6 to 12 months, and that regulatory approval is not on the critical path — supply chain is, which is why the company is investing early there.