Bitdeer Technologies Group earnings recap

Q3 FY2026, reported November 10, 2026 · Beat 1 of last 7 quarters

Bitdeer Technologies Group reported Q3 FY2026 revenue of $321M, a beat of 24.2% against consensus, and EPS of -$0.46, a miss of 31.3%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Bitdeer Technologies Group company page →See the earnings preview →Bitdeer Technologies Group is in the Operators layer →
What this means for the buildout

Bitdeer is increasingly a power-conversion story rather than a pure miner: 332 IT MW of secured AI Cloud capacity against a 350 MW target for Q1 2028 and ~$7.6 billion of claimed contracted revenue put it in the ranks of powered-land owners selling long-duration capacity. The financing detail matters for the broader buildout — prepayments above 50% of GPU deployments, ~$1.3 billion of anticipated letters of credit backstopping Tydal rent, and a shift from corporate equity to asset-level project debt describe the funding template that marginal AI capacity may increasingly require. Its ability to mine on already-energized sites while permitting and interconnection work proceeds is a reminder that existing grid interconnects, not new power, are the scarce input.

Results vs consensus
EstimateActualvs est
Revenue$258M$321M+24.2%beat
EPS-$0.35-$0.46-31.3%miss

These figures come from the same table as our earnings calendar. The write-up below may quote the company's own adjusted or reported figures, which can differ.

What was said

Revenue was $320.7 million with gross profit of $10.8 million (3.4% margin), a $19.4 million sequential improvement, and adjusted EBITDA of $69.6 million. Net loss was $125.5 million, or $0.46 per share, including $125.8 million of depreciation and amortization and a $54.6 million noncash fair value loss on Bitcoin-denominated borrowings. Bitcoin production reached 3,855 BTC, up 43% sequentially with a record 1,355 BTC in September, at a power cost of roughly $36,000 per Bitcoin and fleet efficiency of 15.4 J/TH versus 20.1 a year ago; self-mining hash rate ended at ~82.3 EH/s and co-mining at 28.7 EH/s. AI Cloud revenue was $20.4 million (more than 11x YoY) at ~15% gross margin with 4,328 GPUs at ~95% utilization and ~$86 million of ARR, and the company signed multiyear GPU cloud agreements with enterprise technology customers for GB300 deliveries starting in November. Capital expenditures were $478 million, including ~$288 million for data center construction and land and ~$110 million for SEALMINER production, leaving $163.7 million of cash, $1.95 billion of total debt and ~$342 million of deferred revenue.

Key metrics
Total Revenue
$320.7M
Up ~89% YoY and ~40% QoQ; self-mining added ~$49M and co-mining ~$35M of the sequential increase, AI Cloud ~$6M
Adjusted EBITDA
$69.6M
21.7% margin; up ~173% YoY and ~124% QoQ from $31.1M in Q2 FY2026
AI Cloud Backlog
~$2.9B
A102 (9.5 MW) sold out at >$800M over five years; A201 (21.7 MW) >70% contracted at >$1.7B over five years
Total AI Platform Contracted Revenue
~$7.6B
~$4.7B Tydal base-term lease plus ~$2.9B AI Cloud backlog; ~$8B Tydal value if renewal option exercised
Secured AI Cloud Data Center Capacity
~332 IT MW
~95% of the 350 IT MW target for Q1 2028 after adding A202 (65.1 MW), A901 (67 MW) and A103 (60 MW)
Management outlook

Management cut 2026 crypto mining infrastructure capital expenditure to at or below $200 million, the low end of the prior $200 million to $280 million range, redirecting capital toward contracted AI and HPC projects while financings close. Remaining Tydal spend was described as roughly $250 million to $350 million across Phase 1 and Phase 2 and extending into 2027, with formal 2027 capital and AI Cloud revenue guidance deferred to the Q4 release. Delivery milestones were reaffirmed: Tydal Phase 1 at year-end with customer installations beginning in January, Phase 2 deliveries at the end of Q1 2027, A102 revenue in Q1 2027 and A201 in Q2 2027. Financing is the explicit gating item — Tydal project financing has started, A102 GPU financing is in final stages and A201 work is underway, with rent for Tydal's first eight years expected to be backed by roughly $1.3 billion of letters of credit for years 1-6 and a ~$475 million cash reserve for years 7-8. The tone was deliberately defensive on capital structure: management framed volatility and tighter AI credit as an environment its model was built for, emphasizing customer prepayments (deferred revenue of ~$342 million) covering 50% or more of GPU deployments, and prioritizing non-dilutive project-level debt over equity.

From the call

“Our AI platform now represents approximately $7.6 billion of expected contracted revenue. That includes approximately $4.7 billion from the base term of our Tydal lease and approximately $2.9 billion of AI cloud backlog.”

on Contracted revenue visibility

“The past several months have brought increased volatility. Bitcoin prices moved sharply. Credit is tightened across AI infrastructure, and investors are asking harder questions about how these projects get financed and delivered.”

on Financing environment

“I think that the neolabs, AI-related startups are very underserved on the market, while frontiers, I think, are a little bit overserved.”

on AI Cloud customer mix

What analysts asked

How are AI Cloud prepayments evolving, what percentage of CapEx can they cover today, and how are you thinking about customer mix — shifting toward AI labs at higher rates versus hyperscalers?

Jihan Wu said prepayments should be well above 50% in the near foreseeable future, and that pressure on customers to prepay is rising because capital markets are closing on neoclouds, meaning no competitor can fund new CapEx without strong client support. He said Bitdeer will focus on neolabs and AI startups, which are underserved, while frontiers are somewhat overserved and hyperscaler terms are not very profitable.

Can you update us on Tydal Phase 1 project financing as you approach year-end delivery, and on the key milestones and execution priorities for Phase 2?

Michael Potter said the project financing process is advancing and that Volta's announced GPU financing removed the last major item needed to activate the letter of credit, leaving construction completion and GPU bring-up. He cited the advanced construction, already-available grid power from the prior mining operation, and the LC backstop as differentiators, while acknowledging the AI financing market is tough; he said the company believes it is on track for both the December 31 Phase 1 and Phase 2 milestones, and pointed to Volta's external due diligence as a partial comfort.

Given the mix of Bitcoin sales and AI Cloud prepayments, does this suggest there shouldn't be equity financing in Q4 2026 or into Q1 2027?

Potter said the company will not tie its hands absolutely, but noted the ATM was wound down at the tail end of Q2 and it has not been accessing equity recently. He said the plan is to link contracted cash flows to project financing and GPU-as-a-Service funded by large customer prepayments plus shorter-term financing rather than stretching debt over five years, and that equity is being limited to earlier-stage investments.

Potential supply chain impact
AEPBitdeer holds 570 MW under contract with AEP at Clarington, Ohio; management said there is no update there, it is pursuing relief against litigation, and it is currently planning Bitcoin mining at the site — which may keep that load on AEP's grid rather than converting to AI load in the near term.
CRWVBitdeer's CEO argued credit markets are closing on neoclouds that cannot secure customer prepayments, a dynamic that could pressure GPU-cloud competitors reliant on uncommitted CapEx while potentially favoring Bitdeer's prepayment-funded model.
APLDWith A102 sold out, A201 more than 70% contracted and ~332 IT MW secured, Bitdeer's Malaysia-centric leasing push could sharpen competition for AI/HPC tenants among listed data center hosts.
CORZManagement argued already-energized sites carry an edge amid permitting uncertainty following the midterms; that logic may extend to peers with existing powered shells, though it is not company-specific evidence.
IRENBitdeer's commentary that neolab and AI-startup demand is underserved relative to hyperscalers may signal where smaller-scale GPU capacity pricing lands for other miners-turned-AI-hosts.
CLSKBitdeer cited 15.4 J/TH fleet efficiency and ~$36,000 power cost per Bitcoin as a cost advantage; continued fleet upgrades across large miners could raise the competitive efficiency bar for pure-play peers.