IDACORP, Inc. earnings recap

Q3 FY2026, reported October 29, 2026 · Beat 6 of last 6 quarters

IDACORP, Inc. reported Q3 FY2026 revenue of $603M, a miss of 0.1% against consensus, and EPS of $2.73, a beat of 8.8%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full IDACORP, Inc. company page →See the earnings preview →IDACORP, Inc. is in the Utilities & Energy layer →
What this means for the buildout

This quarter is the first clean read on contracted data center load converting into utility revenue: Meta's Boise data center is operating and Micron's fabs are progressing, showing how AI-driven load shows up in a regulated utility's industrial line before the large associated capital is even fully spent. The 8.9% preliminary load CAGR and a 2032 RFP shortlist carrying more megawatts than the committed forecast imply a multi-year build cycle across gas generation, transmission and grid hardening, with CWIP already above $2.1 billion. Guidance raised on strong operations plus prefunded equity through 2027 suggests the funding ladder for that build is largely in place, though a June 2027 rate case looks increasingly likely as broad-customer projects enter service.

Results vs consensus
EstimateActualvs est
Revenue$603M$603M-0.1%miss
EPS$2.51$2.73+8.8%beat
What was said

IDACORP reported third quarter diluted EPS of $2.73 versus $2.26 a year ago and nine-month EPS of $5.76 versus $5.13, with the quarter aided by roughly $44 million of higher retail revenue from base rates and customer growth. Large contract customers contributed almost $12 million of operating income in the quarter, driving a 27% increase in industrial revenues as Meta's data center south of Boise began operations in September and Micron's Fab 1 and Fab 2 expansions progressed. Customer count rose 2.2% year over year, including 2.4% residential growth, and O&M expense came in higher as expected on Jim Bridger and Valmy deferred-cost amortization and wildfire mitigation, largely recovered through rates. Construction work in progress exceeded $2.1 billion at quarter end, reflecting heavy infrastructure spending, and the company executed $268 million of forward sale agreements in the quarter under its 2026 ATM program. During the quarter the company also received FERC approval for the Oregon sale and shortlisted 11 projects from its 2032 RFP.

Key metrics
Q3 diluted EPS
$2.73
vs $2.26 in Q3 2025; nine-month EPS $5.76 vs $5.13, with only $6.3M of additional ADITC amortization vs $39M a year ago
FY2026 EPS guidance
$6.40–$6.50
Raised $0.10 at the bottom and $0.05 at the top; management framed it as a 19th consecutive year of EPS growth
Industrial revenue growth
+27% YoY
Driven by large contract customers constructing and coming online; weather-normalized industrial and special contract sales volumes up 58%
Preliminary 2027 IRP load CAGR
8.9%
Retail sales over the next five years; roughly 19,000 GWh in 2027 growing to about 29,000 GWh by 2032, signed or committed customers only
Large contract customer operating income
+$12M
Third quarter contribution on the new reconciliation line, roughly $20M year to date as the ramp builds
Management outlook

Management raised full-year 2026 diluted EPS guidance to $6.40–$6.50 (up $0.10 at the bottom and $0.05 at the top) and cut expected additional ADITC amortization to less than $10 million from less than $15 million, versus roughly $40 million in 2025. Full-year O&M is now guided to $535–$545 million, CapEx remains $1.3–$1.5 billion but is trending to the high end, and hydropower generation is expected at 5.5–6.0 million MWh. A refreshed CapEx forecast lands on the Q4 call and will incorporate company-owned projects selected from the 2032 RFP, which management said are not in the current plan and would be funded with roughly 50/50 debt and equity. Equity is already prefunded — about $873 million of unsettled forwards are available, covering current-plan equity needs through 2027 and likely into part of 2028 — and the company targets a 50% debt-to-equity structure. The 2032 RFP shortlist of 11 projects drew more than 100 bids, with contracts targeted by year-end and CPCN filings to follow; management is also running numbers on a potential June 2027 rate case, citing CWIP converting to plant in service in 2027 for broad-customer projects. The Oregon distribution sale is still expected to close in spring 2027, and Micron Fab 2 ESA negotiations are described as going well with a hope of meeting prior year-end timing.

From the call

“A particular note for this quarter are industrial revenues, which increased by an incredible 27% since last year's third quarter.”

on Industrial revenue growth

“META officially began operations at its data center south of Boise in September and is now ramping up.”

on Large load ramp

“We are 2 years into more than doubling our rate base over a 5 year window.”

on Rate base growth

What analysts asked

Assuming the RFP shortlist is larger than the committed load forecast, what has to happen before you contract beyond committed need, and how big is the pipeline sitting outside the 29,000 GWh forecast?

Lisa Grow said a signed ESA or significant financial commitment is enough to add a customer to the load forecast — full commission approval is not required. Adam Richins sized the pipeline at about 4 gigawatts, excluding Micron Fab 1 and Meta 1, split roughly into 1 GW promising (financial commitment, moving toward construction), 1 GW in active study, and about 2 GW preliminary, plus roughly 3 GW of new inquiries since that figure was last cited, putting about 5 GW in the preliminary bucket.

How many megawatts do you expect to procure from the RFP, what is the timing and profile of capital spend on the self-build projects, and what is the status of the Micron Fab 2 ESA?

Adam Richins pointed to the 430 MW advanced simple cycle unit (Peregrine) as the top-ranked 2031 project, with turbines reserved and an EPC contract awarded, while the 432 MW combined cycle 2032 project remains under evaluation pending the load forecast. CapEx is spread across 2028 through 2032 plus transmission, with some spend now occurring years ahead of in-service. Brian Buckham said incremental CapEx above the current plan would be funded roughly 50/50 debt and equity, with possible exceptions for customer prepayments or bill-transfer structures, and noted neither plant is in the existing CapEx forecast. Lisa Grow said Micron Fab 2 negotiations are going well and the company is hopeful of meeting its prior year-end timeline.

With a large CapEx plan and additional contracts signed, where are the main supply chain bottlenecks and how are you preparing to execute, including on potential incremental CapEx?

Lisa Grow said turbine reservation or supply agreements are in place and she feels strong about the plants, while breakers, transformers and conductor remain the chronic challenge the company works to get ahead of. Adam Richins added that the EPC contractor market has been tough, but the company has awarded and selected contractors for every plant but one, and has been pleasantly surprised by the number and variety of bidders interested in its diverse load.

Potential supply chain impact
METAMeta's data center south of Boise began operations in September and is ramping, and it is included in the preliminary 2027 IRP load forecast; further Meta expansions could add incremental load and RFP-driven capital needs for Idaho Power.
MUMicron Fab 1 and Fab 2 are in the 8.9% preliminary load CAGR and Fab 2 ESA negotiations are ongoing with a prior year-end target; a signed ESA could add load, and any Fab 3 decision is explicitly outside the current forecast — a potential upside signal for future CapEx.