Alliant Energy Corporation earnings recap

Q3 FY2026, reported October 29, 2026 · Beat 6 of last 7 quarters

Alliant Energy Corporation reported Q3 FY2026 revenue of $1.28B, a beat of 1.9% against consensus, and EPS of $1.52, a beat of 16.0%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Alliant Energy Corporation company page →See the earnings preview →Alliant Energy Corporation is in the Utilities & Energy layer →
What this means for the buildout

Alliant's refreshed plan shows a regulated utility converting a data center pipeline into hard infrastructure: a 19% larger four-year CapEx plan, added gas combustion turbines and storage, and a stated $2 billion-$3 billion of CapEx per incremental gigawatt of contracted load. The roughly 1 GW of additional contracted load expected within six months, if converted, could imply meaningful further generation and grid orders layered onto the 2027-2030 window. The $5.1 billion DOE guaranteed loan and expanded tax credit monetization also point to cheaper, longer-dated funding for generation and transmission build in the Midwest.

Results vs consensus
EstimateActualvs est
Revenue$1.26B$1.28B+1.9%beat
EPS$1.31$1.52+16.0%beat
What was said

Alliant reported third quarter 2026 GAAP earnings of $1.52 per share, with year-over-year growth driven by higher revenue requirements and AFUDC on capital investments at IPL and WPL, timing of income tax expense that reverses in the fourth quarter, higher equity earnings from corporate venture fund investments, a $0.05 per share electric margin benefit from above-normal summer temperatures versus $0.03 last year, and higher temperature-normalized retail electric sales led by commercial and industrial strength in Wisconsin and early data center load in Iowa. Those were partly offset by higher other O&M from business and generation fleet growth, plus higher financing and depreciation costs on a growing rate base. On the load side, Google is taking transmission service in Cedar Rapids on a ramp consistent with the accelerated schedule filed with the Iowa Commission, QTS Cedar Rapids expects to complete commissioning of its first two buildings later this quarter, and Meta is on distribution service in Wisconsin with transmission service expected in Q1 2027; the company also said Mesabi Metallics expects to locate plants in Lee County, Iowa, with only its non-curtailable initial capacity reflected in the refreshed plan. Regulatorily, Iowa's retail electric base rate stability plan was extended one year through the end of 2030, a Wisconsin large load tariff was filed, an ICR application was filed for a second Google project in Cedar Rapids, and a QTS Clinton individual customer rate application is expected in the first half of 2027.

Key metrics
2026 ongoing EPS guidance
$3.41 – $3.46
Narrowed to the top half of the original range on strong 9-month results and improved Q4 visibility
2027 ongoing EPS guidance
$3.63 – $3.73
Represents 8% growth over the $3.41 midpoint of the original 2026 guidance; 2027 dividend target of $2.25/share, up 5%
Capital investment plan 2027-2030
$15.9B
19% above last year's 4-year plan; drives 13% CAGR in rate base plus CWIP, up from 12% previously
Contracted demand growth
>60% by 2031
Supported by 5 data centers, 3 of which are actively under construction
Large load pipeline
3.4 GW across 3 sites
Expects ~1 additional GW of contracted large load within 6 months, at roughly $2B-$3B of CapEx per GW
Management outlook

Management narrowed 2026 ongoing EPS guidance to the top half of the original range, $3.41-$3.46, and initiated 2027 guidance of $3.63-$3.73, which it framed as 8% growth off the $3.41 midpoint of the original 2026 guide. It raised its long-term annual earnings growth target to 6% to 8% plus and extended an 8% plus expectation from 2027 through 2030, alongside a projected total shareholder return of greater than 11% per year over that period. The refreshed 2027-2030 capital plan of $15.9 billion is 19% larger than the prior plan and adds 1.2 GW of natural gas combustion turbines and 200 MW of energy storage; the gap between the 13% investment CAGR and 8% plus earnings growth reflects about 375 basis points of equity issuance dilution and roughly 50 basis points from refinancing maturing nonutility and parent debt. Financing is anchored by approximately 40% equity funding of incremental CapEx (the low end of the prior 40%-50% range), with about $1.1 billion of the $2.7 billion of common equity already secured through forward equity agreements, roughly $2 billion of tax credits expected over the plan, and a $5.1 billion Department of Energy guaranteed loan program that management estimates could produce up to $1.2 billion of cumulative customer savings. Lisa Barton said the company expects roughly 1 additional GW of contracted large load within six months; Robert Durian said each GW would likely bring $2B-$3B of additional CapEx, with updates targeted for the EEI and AGA conferences while stressing a deliberately higher bar for what gets included. Management also flagged a one-year extension of Iowa retail electric base rate stability through the end of 2030, a Wisconsin large load tariff filing, and planned filings for QTS Clinton and a Wisconsin base rate review covering forward test years 2028-2029.

From the call

“Our objective is not to present the biggest number, but to provide investors with the greatest confidence in the executability of our growth.”

on Disclosure discipline

“We expect this work to produce approximately 1 additional gigawatt of contracted large load within the next 6 months, creating meaningful upside to our current capital plan.”

on Large load pipeline

“think of our capital expenditure plan updates will largely be for every gigawatt of additional load, you're probably going to see somewhere in the neighborhood of $2 billion to $3 billion of additional CapEx.”

on CapEx per gigawatt

What analysts asked

Is 2027 the new base to grow 8% plus off of, and taking dilution into account, how should we frame the 'plus' — can you be above 9% in this plan?

Robert Durian said you can build off either the $3.41 midpoint of original 2026 guidance or the $3.68 midpoint of 2027 guidance and get to the same place. He described the 'plus' as representing earnings growth of at least 8% each year over 2027-2030, with some periods higher than that minimum, typically in years with higher capital expenditures.

For the next gigawatt of contracted load, what is the capital intensity to serve it given MISO accreditation changes, and does it require capacity in parallel or depend on curtailability?

Durian said capacity is lined up with load ramps so generation is ready alongside construction-cycle cash flows, and framed roughly $2 billion to $3 billion of additional CapEx per gigawatt of additional load — largely because the plan focuses only on the capacity resources needed to serve those customers, with broader energy resource opportunities treated as further-out upside.

How much of the CapEx for the next gigawatt lands inside the current planning period versus after, and is 40% a good rule of thumb for equity content on incremental CapEx?

Durian said the next gigawatt ramps more in the 2029-2030 timeframe, with associated gas generation possibly in 2030-2031, so the CapEx splits between the 2027-2030 plan and beyond. On equity, he said future incremental CapEx should be funded with a relatively lower level of new common equity than the prior 40%-50% guidance, helped by data center cash flows ramping in the latter part of the plan.

Potential supply chain impact
METAMeta is taking distribution service at its Wisconsin data center with transmission service expected in Q1 2027; continued progress there could support incremental WPL rate base and generation needs, though timing of the transmission step-up remains a factor to watch.