NET Power Inc. earnings recap

Q3 FY2026, reported November 12, 2026 · Beat 1 of last 7 quarters

NET Power Inc. reported Q3 FY2026 EPS of $-0.07, a miss against consensus.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full NET Power Inc. company page →See the earnings preview →NET Power Inc. is in the Power Generation layer →
What this means for the buildout

NET Power is positioning directly against the data center grid bottleneck, arguing that islanded, co-located gas generation sidesteps interconnection queues and shifting cost-allocation debates over who pays for large new loads. Its decision to standardize a product combining reciprocating engines, gas turbines and battery storage — rather than engineer one-off plants — is a bet that replication speed, not technology novelty, is what AI campus developers will pay for. The main swing factor for the buildout is commercial: the equipment is ordered and the deposits are paid, but full notice to proceed and construction are explicitly gated on committed financing and a signed definitive agreement.

Results vs consensus
EstimateActualvs est
EPS-$0.04-$0.07n/mmiss
What was said

NET Power reported a third quarter with no revenue, no debt and approximately $183 million of cash, equivalents and investments. Property, plant and equipment rose to about $141 million from roughly $33 million at year-end, almost entirely construction-in-progress, comprising about $118 million for 10 Wärtsilä reciprocating engines and the related EPC contract plus about $23 million of deposits on two gas turbine generator packages; the 10-Q notes recovery of those costs depends on whether the initial project proceeds, recovery under the cost reimbursement agreement, and resale or redeployment of the equipment. Operationally, management repositioned the company as a "powered land developer" selling standardized islanded power solutions that combine reciprocating engines, gas turbines and battery storage, sized with redundancy to meet data center reliability requirements. The initial project is being developed for a prospective customer — a leading developer of frontier AI models — at a Texas site that has not yet been secured and that is separate from Project Permian, with the parties negotiating toward a definitive energy services agreement that neither is obligated to sign. Management also noted a nearly $180 million cost reimbursement mechanism tied to approved expense items, and said it is evaluating every powered land opportunity in Texas and other markets to prioritize speed to power.

Key metrics
Cash, cash equivalents & investments
$183M
No debt; company ended the quarter with approximately $183M of cash, cash equivalents and investments
G&A run rate
~$30M-$35M/year
Approximately $30 million-$35 million a year; costs will continue to be managed with discipline
Property, plant & equipment
$141M
Up from roughly $33M at year-end; nearly all construction-in-progress, including ~$118M for 10 Wärtsilä reciprocating engines and the related EPC contract
Gas turbine deposits
~$23M
Deposits on two gas turbine generator packages, held alongside the reciprocating engine commitments
Customer cost reimbursement cap
~$180M
Non-refundable reimbursement of approved expense items owed by the prospective customer if certain events occur, subject to conditions, unless NET Power elects to keep the related equipment
Management outlook

Management gave no revenue or margin guidance — the company remains pre-revenue — and instead framed the path forward around converting a prospective customer into a definitive energy services agreement. The initial project is now being developed for a prospective customer described as a leading developer of frontier artificial intelligence models, at a Texas site NET Power has not yet secured and which is separate from Project Permian; Project Permian is intended to continue in parallel as a second project. CFO Lee Shuman said the liquidity forecast assumes the company will not issue full notice to proceed under its EPC agreement, or make additional significant equipment or construction commitments, without committed financing or other capital, and that existing cash and available-for-sale securities should cover obligations for at least the next 12 months. Management said projects will require project-level financing, partner capital, additional equity, or some combination, none of which has been committed, making secure commercial arrangements the stated top priority. G&A is running at approximately $30 million-$35 million a year and management said costs will continue to be managed with discipline. The tone was deliberate rather than promotional: Danny Rice said the company will stay flexible on where it builds so it can stay uncompromising on how fast it can happen, and repeatedly flagged permitting and execution — not demand — as the binding constraints.

From the call

“What we cannot control is the timing of regulatory processes, and customers need power as soon as possible. We are prioritizing speed to power.”

on Speed to power vs. regulatory timing

“We are developing our initial project for a prospective customer who is a leading developer of frontier artificial intelligence models at a site in Texas that we have not yet secured, and that is separate from Project Permian.”

on Initial project and customer

“Our liquidity forecast assumes that we will not issue full notice to proceed under our EPC agreement or make additional significant equipment or construction commitments without committed financing or other capital.”

on Capital discipline and financing condition