OGE Energy Corp. (OGE) | The Buildout — AI Infrastructure

——Mkt cap — · 52-wk —–— · YTD — · delayed
Updated Sep 22, 2026Q2 FY2026 reviewed
OGE Energy is a regulated electric utility selling power and grid access to data centers.
FY26 EPS reaffirmed
$2.38-$2.48 guided, midpoint $2.43.
Google contract filed
Filed May 1, 2026 to power three Oklahoma data centers.
Peak over 6,800 MW
New all-time high, about 180 MW above the 2024 record.
200 MW ramp slipped
Two large customers pushed ramp further into the year.
The Buildout Takeaway
The demand side of the story is tangible: data-center load is why OGE is adding generation and transmission, and the regulatory framework is being built to protect existing ratepayers while it does. The open question is whether that load connects to the regulated grid or bypasses it through behind-the-meter self-supply, and whether the pipeline beyond Google converts.
21 analysts·9 Buy12 Hold0 Sell
Coverage is thin — only 4 price estimates, so no target is shown

FY2026 EPS $2.38-$2.48, midpoint $2.43 • long-term EPS growth 5%-7%, top half of range through 2030 • FFO/debt target about 17%.
Important: The Buildout is a data analytics platform. Content is generated by algorithms and AI agents using public filings, earnings transcripts, and market data. This is not personalized investment advice.
Our View

The Verdict

OGE Energy is a holding company whose only reportable segment is OG&E, a regulated electric utility that generates, transmits, distributes and sells electricity in Oklahoma and western Arkansas. It is not an AI technology company. The buildout reaches it as demand: data centers need large amounts of power, and OGE sells that power and grid access under regulated contracts and tariffs. The flagship example is Google's data centers in Muskogee and Stillwater, Oklahoma. The model's case rests on that load growth funding new generation and transmission that enters rate base, with a regulatory framework designed to shield existing customers from the cost.

Market Cap—
Revenue (TTM)$3.2B
Revenue Growth+0.6%
EBITDA Margin (TTM)41.4%
Net Debt$5.8B
Earnings Beats3 of 7
P/E (TTM)—
EV/EBITDA (TTM)—

What We Like

  • Google's special contract was filed May 1, 2026 to serve multiple Oklahoma data centers, with a procedural schedule set and resolution expected before the end of 2026.
  • The Oklahoma large-load tariff, filed June 17, 2026, sets terms for loads greater than 75 MW: 100% upfront grid-connection funding, a 15-year minimum, collateral, and a consumer-protection charge, plus a proposed $25-$30 million annual affordability credit per typical 1 GW data center.
  • Management cites 6 or 7 active large-load negotiations, a funnel wider than the Google deal, on a system described as just under 7 GW.
  • Capacity additions are accelerating: 550 MW added in 2026 (Horseshoe Lake and Tinker) and 300 MW planned in 2027 (Frontier Storage), against a historical pace of roughly 300-400 MW per year.
  • FY2026 EPS guidance was reaffirmed at $2.38-$2.48, and Moody's revised both OGE and OG&E outlooks to stable from negative while lowering the parent downgrade threshold to 17%.

What We’re Watching

  • Two current large customers pushed roughly 200 MW of ramp further into 2026, citing issues on their side; management says the commitments remain but the timing is not in OGE's control.
  • The 4%-6% short-term load-growth guide stated on the Q1 2026 call was not restated on the Q2 2026 call.
  • Management did not directly answer whether the large-load tariff holds if a large customer self-supplies, and behind-the-meter development is active in the territory.
  • The SPP transmission notice to construct is outside company control and now expected in Q4 2026, with Seminole-Shreveport cost, routing and the AEP split still open; the Arkansas rate review went silent after Q1.
Bottom Line

The thesis is intact and, on the disclosed evidence, strengthening at the margin: the anchor contract moved from anonymous to named to filed, the tariff framework landed ahead of schedule, the credit outlook moved to stable, and the system set a record peak. The counterweights are timing rather than demand — a 200 MW ramp slip, an unrestated load-growth guide, and unresolved transmission terms. The open question is how much load beyond Google's IRP-included gig converts from the 6-7 negotiations, and whether it connects to the regulated grid.

Next upThe next signposts are the Oklahoma rate-case filing this quarter, expected adoption of the Frontier storage order in short order, the SPP transmission notice in Q4 2026, and an OCC order on the Google contract before the end of 2026. Each tests whether the capital pipeline is clearing on schedule.
Last Quarter — Q2 FY2026

Earnings

Q2 2026 consolidated earnings were $0.56 per diluted share versus $0.53 a year earlier, on revenue of $711.9M at a 69.4% gross margin with EBITDA of $329.8M, or 46.3% of revenue. OG&E contributed $0.58 versus $0.53, helped by warm second-quarter weather and lower depreciation and interest expense on assets placed in service, partly offset by higher O&M expense. The holding company widened its loss to about $0.02 per share on higher interest expense and a prior-year benefit tied to legacy midstream operations.

MetricQ2 FY2026Q1 FY2026Q2 FY2025YoY
Revenue$712M$753M$742M−4.0%
Gross margin69.4%37.1%47.7%+2170bps
EBITDA$330M$250M$327M+0.8%
EPS$0.58$0.24$0.53+8.7%
System peak load>6,800 MWn/an/aNew all-time record
Our proposed customer affordability charge would benefit residential customers to the tune of $25 million to $30 million annually for a typical 1 gigawatt data center.— CEO, 2026-07-29

Management tone: Management's tone held steady across the Q1 and Q2 2026 calls and firmed as the Google filing, large-load tariff and Frontier order landed. Management described the roughly 200 MW ramp shift as a timing issue rather than a change to the growth thesis and framed the pipeline as a long conveyor belt of opportunities. The 5%-7% long-term EPS target was omitted from the Q2 prepared script but reaffirmed in Q&A. On self-supply, management reframed rather than directly answered the question.

Management Guidance

FY2026 EPS guidance was reaffirmed at $2.38-$2.48, midpoint $2.43, assuming normal weather for the rest of the year. Long-term EPS growth is targeted at 5%-7% through 2030, with the top half of the range expected in 2027 and 2028 and supported by expected strong load growth. Management reaffirmed an FFO/debt target of about 17% and said all planned 2026 financing is complete. The 4%-6% short-term load-growth guide stated in Q1 was not restated on the Q2 call.

Business Trajectory

Trajectory

Revenue has tracked a seasonal band lately: $1,045M in Q3 FY2025, $726M in Q4 FY2025, $753M in Q1 FY2026 and $712M in Q2 FY2026. The code-computed read is decelerating revenue, with gross margin expanding about 660 basis points, operating margin compressing about 580 basis points and EBITDA margin roughly flat. Near-term results are weather-driven — Q1 FY2026 residential revenue fell $26.9M year over year, and Q2's warm weather offset part of that headwind. The structural driver is rate base: management added 550 MW in 2026 and plans 300 MW in 2027 against a historical 300-400 MW per year, and says that pace must increase.

Revenue & Margin Trajectory
RevenueGross margin$0$1.0B$744M$531M$456M$586M$717M$502M$493M$567M$699M$512M$490M$514M$755M$472M$431M$504M$702M$485M$1.6B$577M$864M$581M$589M$804M$1.3B$712M$557M$605M$945M$567M$597M$663M$965M$760M$748M$742M$1.0B$726M$753M$712M48%69%Q3'16Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26Q2
RevenueGross margin$0$1.0B$744M$531M$456M$586M$717M$502M$493M$567M$699M$512M$490M$514M$755M$472M$431M$504M$702M$485M$1.6B$577M$864M$581M$589M$804M$1.3B$712M$557M$605M$945M$567M$597M$663M$965M$760M$748M$742M$1.0B$726M$753M$712M48%69%Q3'16Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26Q2
Gross margin as reported.
Share Price — 12 Months
$20$40$052-wk high $49Sep '25DecMar '26JunSep '26
52-week range $42–$49.
Share Price — 12 Months
$20$40$052-wk high $49Sep '25DecMar '26JunSep '26
52-week range $42–$49.
The Numbers

The Model

The model projects FY+1 revenue of $3,240M and EBITDA of $1,354M, a 41.8% margin, and FY+2 revenue of $3,380M and EBITDA of $1,433M, a 42.4% margin. The near-term figure is anchored by the existing regulated rate base and modest load growth. FY+2 reflects the data-center pipeline — generation additions and transmission projects moving into rate base. No per-share figures are published here.

Revenue & EBITDA Projections
REVENUE$3.3B$3.2B$3.4BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$1.4B$1.4B$1.4B42.4%FY25FY+1 (E)FY+2 (E)
REVENUE$3.3B$3.2B$3.4BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$1.4B$1.4B$1.4B42.4%FY25FY+1 (E)FY+2 (E)
Solid bars are reported actuals; outlined bars are model projections — not company guidance.
MetricFY2025Next FY (E)Following FY (E)
Revenue$3.3B$3.2B$3.4B
YoY Growth—−0.6%+4.3%
EBITDA$1.4B$1.4B$1.4B
EBITDA Margin41.7%41.8%42.4%

Projections are the median of 5 independent model runs. The model’s revenue sits 2.5% below analyst consensus.

FY2026 EPS guidance was reaffirmed at $2.38-$2.48, midpoint $2.43, assuming normal weather for the rest of the year. Long-term EPS growth is targeted at 5%-7% through 2030, with the top half of the range expected in 2027 and 2028 and supported by expected strong load growth. Management reaffirmed an FFO/debt target of about 17% and said all planned 2026 financing is complete. The 4%-6% short-term load-growth guide stated in Q1 was not restated on the Q2 call.

What Could Go Right — and Wrong

What good looks like
  • The 6-7 active large-load negotiations convert into filed contracts, adding demand beyond the IRP.
  • The large-load tariff is approved as filed and additional large loads connect to the regulated grid rather than self-supplying.
  • The SPP notice to construct for the Seminole-Shreveport 765 kV line arrives in Q4 2026 with a workable cost and split, adding a large transmission project.
  • The roughly 200 MW ramp shift comes online as management expects, confirming it was a timing issue.
  • The capacity build accelerates beyond 300-400 MW per year and enters rate base under an own-and-operate model.
What could go wrong
  • Large-load ramp slips again; commitments are in place but the timing is outside the company's control.
  • Behind-the-meter self-supply wins in Oklahoma, weakening the regulated growth model.
  • The SPP notice is delayed or the cost, routing and AEP split come out unfavorably, pushing the capital plan out.
  • The capital plan outruns the financing plan, with the June 15, 2026 debt agreement watch-tagged negative against a 2026 financing-complete claim.
  • Environmental compliance costs estimated at $2.4 billion to $2.8 billion bite without timely recovery.
What’s Next

Looking Ahead

Over the next 12 months the story turns on regulatory outcomes rather than demand. The Google special contract should move toward an OCC order by the end of 2026, the Oklahoma rate review is to be filed this quarter, and the SPP notice to construct for the Seminole-Shreveport 765 kV line is expected in Q4 2026. Frontier storage adoption is expected in short order, and Horseshoe Lake units 13 and 14 are due online in Q4 2026. The pieces of a larger capital plan are arriving one filing at a time, which management says will continue.

Catalysts
  • Q3 2026Oklahoma rate case filed — Distribution-only review; new rates anticipated in 2027.
  • In short orderFrontier storage order — OCC adoption of the 300 MW battery preapproval expected.
  • Q4 2026SPP transmission notice — Tests route, cost and AEP split for the 765 kV line.
  • Q4 2026Horseshoe Lake units online — 450 MW of combustion-turbine capacity enters service.
  • By end-2026Google contract resolution — OCC order would de-risk the anchor data-center contract.
  • Balance of 2026RFP pre-approval filings — Multiple filings expected as generation negotiations close.
Numbers

Financials

Annual Summary

MetricFY2024FY2025TTMYoY
Revenue$3.0B$3.3B$3.2B+9.2%
Gross Margin46.2%48.2%53.6%+200bps
EBITDA$1.3B$1.4B$1.3B+5.8%
EBITDA Margin43.0%41.7%41.4%134bps
Net Income$442M$471M$471M+6.6%
Free Cash Flow−$278M$835M$1.2B—
Net Cash————

Key Ratios (Trailing)

Valuation
  • P/E TTM—
  • EV/EBITDA TTM—
  • EV/Revenue TTM—
  • Price/FCF TTM—
Profitability
  • Gross Margin (TTM)53.6%
  • EBITDA Margin (TTM)41.4%
  • Net Margin (TTM)14.6%
  • ROIC5.7%
  • FCF Conversion90.2%
  • SBC / Revenue0.2%
Reference

The Company

OGE Energy is a holding company whose only reportable segment is the regulated electric utility run through wholly owned subsidiary OG&E. The 10-K describes OG&E as the largest electric company in Oklahoma, generating, transmitting, distributing and selling electricity in Oklahoma and western Arkansas. OGE sold its former midstream business in 2022, making this a pure-play regulated utility. The business matters to the AI buildout as a power supplier: data centers draw large, high-load-factor electricity, and OGE sells that power and grid access under regulated contracts and tariffs.

On operations, OG&E owns and co-owns a generation fleet spanning gas, coal, wind and small solar. Named plants include Seminole 1-3 (1,521 MW of gas steam), Muskogee 4-6 (1,510 MW), Sooner 1-2 (1,038 MW of coal), the partially owned Redbud (619 MW, 51%) and McClain (375 MW, 77%) combined-cycle units, and three Oklahoma wind farms. The 10-K says OG&E holds coal supply agreements for 100 percent of its expected coal requirements through 2027 for the Sooner, Muskogee and River Valley facilities, and lists named wind power purchase agreements with CPV Keenan, Edison Mission Energy and NextEra Energy. Management intends to own and operate new generation rather than rely on power purchase agreements.

Business Segments

Electric Company (OG&E)
Only reportable segment
Regulated generation, transmission, distribution and retail electricity sales in Oklahoma and western Arkansas.
Growth driver: Data-center large-load growth and rate-base additions
Large-load / data center service
Loads greater than 75 MW under the new tariff
Data centers served under special contracts and a new large-load tariff framework.
Growth driver: Google and 6 or 7 active load negotiations

Competitive Landscape

OGE is the regulated monopoly provider in its service territory, but the 10-K says it faces competition in various degrees from government-owned electric systems, municipally-owned electric systems, rural electric cooperatives and, in certain respects, from other private utilities, power marketers and cogenerators. For the AI-related load, the material names a different competitive threat: large customers that self-supply behind the meter. Core Scientific's Muskogee path is described as including behind-the-meter solutions, and Oracle is pursuing on-site generation. Management did not directly answer whether the large-load tariff holds if a customer self-supplies; it pivoted to the merits of the regulated model.

  • Transmission partner on the Seminole-Shreveport 765 kV line; also listed as a competitor in the inferred supply-chain wiring around data center load in the SPP region.
  • NextEra Energy
    Supplies wind and solar capacity under contracts; also listed as a competitor in the inferred supply-chain wiring.
  • Listed as a competitor in the inferred supply-chain wiring; not discussed in the filings.
  • Listed as a competitor in the inferred supply-chain wiring; not discussed in the filings.
  • Xcel
    Listed as a competitor in the inferred supply-chain wiring; not discussed in the filings.
The 10-K competition quote names categories, not companies (government-owned, municipal and cooperative systems, private utilities, power marketers, cogenerators). Named competitors come from the inferred supply-chain wiring.

Supply Chain

OGE sits at the power layer of the AI stack, converting fuel and renewable supply into regulated electricity and grid capacity for large data-center loads. Google is the only hyperscaler with a documented contract; the wider roster is inferred.

Supplier
NextEra Energy
Wind PPA (Blackwell, OK) and 600 MW nameplate solar for Google agreements
Supplier
CPV Keenan
Wind PPA, Woodward County, OK
Supplier
Edison Mission Energy
Wind PPA, Dewey County, OK
Supplier
Coal suppliers (unnamed)
Coal for Sooner, Muskogee and River Valley; 100% of expected requirements through 2027
Supplier
AEP
Joint transmission partner on the Seminole-Shreveport 765 kV line
→
Low electric rates
OGE
Owns and operates regulated generation, transmission and distribution across Oklahoma and western Arkansas.
→
Google (Alphabet)
3 data centers
Muskogee and Stillwater, OK; special contract filed May 1, 2026
Residential, commercial and industrial
915,232 customers
Customer count at March 31, 2026, up from 908,851 a year earlier

Analysis updated Sep 22, 2026, reviewing Q2 FY2026. Prices delayed. Built with The Buildout’s published methodology. Not investment advice. No positions held. © The Buildout 2026.

More on OGE: Earnings recap