Akamai Technologies, Inc. earnings recap

Q3 FY2026, reported November 5, 2026 · Beat 7 of last 7 quarters

Akamai Technologies, Inc. reported Q3 FY2026 revenue of $1.12B, a beat of 0.4% against consensus, and EPS of $1.77, a beat of 6.0%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Akamai Technologies, Inc. company page →See the earnings preview →Akamai Technologies, Inc. is in the Operators layer →
What this means for the buildout

Akamai is positioning itself as a CPU-heavy, distributed inference and agent-execution layer rather than a GPU training buildout, with over 90% of deployed servers being CPUs, ~$22 million of expected revenue per megawatt on this year's large deals, and a stated ~75% adjusted EBITDA / ~30% operating margin at full ramp. The $1.7B Q4 memory and component prepurchase, alongside fully contracted colo and power, is a concrete datapoint that memory and space — not demand — remain the gating items in the AI infrastructure supply chain, and that contract structures with pricing adjustment mechanisms are being used to shift component-cost risk. The $30 million slip from Q4 into 2027 shows how thin the margin for execution is between signing a multi-billion-dollar AI contract and recognizing revenue against it.

Results vs consensus
EstimateActualvs est
Revenue$1.12B$1.12B+0.4%beat
EPS$1.67$1.77+6.0%beat
What was said

Total revenue was $1.122B, up 6% year over year as reported and 7% in constant currency, with CIS at $109M, Security at $622M and Delivery and other cloud applications at $391M, down 3%. International revenue was $563M, about 50% of the total, up 7% as reported and 9% in constant currency. Non-GAAP net income was $262 million, or $1.77 per diluted share, down 5% year over year, with non-GAAP operating margin of 25% in line with expectations, and CapEx of $464 million, or 41% of revenue, slightly below guidance on equipment delivery timing. Two of the first three large CIS contracts, representing $2.8B of total contract value, are now generating revenue, with the third in final testing and expected to begin contributing later in Q4; supply chain and third-party data center delays pushed roughly $30 million of revenue out of Q4 into 2027. The company did not repurchase stock in the quarter, has bought back about 5 million shares for ~$616 million year to date, and ended September 30 with approximately $4.2B of cash, cash equivalents and marketable securities; it also flagged the late-October launch of Akamai Inference and Akamai Agent Sandbox (described on the call as "just last week"), after the Q3 close.

Key metrics
Cloud Infrastructure Services revenue
$109M
Up 34% YoY as reported, 35% in constant currency.
Security revenue
$622M
Up 9% YoY as reported, 10% in constant currency; led by API Security, WAF and Guardicore Segmentation
Multiyear CIS commitments signed YTD
>$14B
Includes a new $11.6B, 7-year Anthropic commitment for CPU workloads plus two other large AI deals and numerous enterprise wins
2027 CIS revenue outlook
$1.1B–$1.3B
Implies more than doubling; total company revenue growth guided to 17%–22% in constant currency in 2027
Q4 FY2026 CapEx guidance
$2.445B–$2.645B
Up from $464M (41% of revenue) in Q3; includes ~$1.7B of prepurchased memory and critical components for the Anthropic contract
Management outlook

Management reset the near-term trajectory lower on timing while sharply raising the multiyear outlook. Roughly $30 million of CIS revenue shifts from Q4 FY2026 into 2027 after supply chain and third-party data center delays on two deals, which the company says are resolved and carry no penalty or lost contract value; Q4 revenue is guided to $1.145B–$1.170B (up 5%–7%), non-GAAP operating margin ~24%, adjusted EBITDA margin ~38% and EPS of $1.50–$1.70, with full-year FY2026 revenue of $4.44B–$4.465B, CIS growth of 40%–42% in constant currency, and EPS of $6.47–$6.68. For 2027, CIS revenue is expected to more than double to $1.1B–$1.3B, driving total company growth of 17%–22% in constant currency, with CFO Ed McGowan sizing the ramp at 25%–30% of CIS revenue in the first half and 70%–75% in the second half, and 2028 total revenue surpassing $7 billion without assuming any revenue from the $9 billion Anthropic option. On profitability, McGowan said margins should bottom in the first half of 2027 — perhaps a point lower, with 1–2 points of noncash colocation straight-lining pressure — before EBITDA margin expands significantly through 2028, against a fully ramped economics target of ~$2.2B of annual revenue at ~75% adjusted EBITDA and ~30% non-GAAP operating margin. The company said it has secured and contracted all colo and power for the $11.6B contract, ~70% of required hardware and components, and permitting through 2028, and that it expects to fund the expansion and the 2027 convertible maturity primarily from existing cash (~$4.2B at quarter end) and operating cash flow, supplemented by measured incremental financing if needed; it also said it will stop announcing every large CIS transaction unless SEC rules require it.

From the call

“Most notably, we signed an $11.6 billion commitment over 7 years with Anthropic to support their CPU workloads with our distributed infrastructure and software. This brings the total of multiyear commits for CIS signed this year to more than $14 billion.”

on Anthropic contract

“In fact, we now anticipate that our CIS revenue will more than double in 2027 to $1.1 billion to $1.3 billion and that Akamai's overall revenue growth rate will dramatically accelerate as a result, with total 2027 revenue growing 17% to 22% in constant currency over 2026 levels.”

on 2027 outlook

“we are pleased to confirm that we have secured and contracted for all the necessary space and power or colo required to deliver the full contract value with these sites expected to be available to us throughout the revenue ramp period previously outlined. In addition, we've secured approximately 70% of all the necessary hardware, memory, and other components needed to deliver on this contract, including $1.7 billion of memory and other critical items in Q4 2026.”

on Capacity and supply secured

What analysts asked

You lowered 2026 revenue due to supply chain issues — can you detail the near-term bottlenecks, how confident you are in the 2027 CIS number, and how it ramps through the year?

Tom Leighton characterized the issues as minor data center items likened to a construction punch list, a couple of months of delay with no revenue lost, just pushed into next year, and said he is very confident in the 2027 estimates given the range accounts for substantial potential delays. Ed McGowan said to model 25%–30% of 2027 CIS revenue in the first half and 70%–75% in the back half, and pointed to revenue already being recognized, all colo signed for the largest transaction, and approvals already in hand.

Given you won't announce every incremental CIS win, can you comment on the demand pipeline, and how should we think about pipeline conversion versus a capital raise? Also, what is the magnitude of the pricing premium versus the $22 million per megawatt on earlier deals?

Leighton described a very strong pipeline with hundreds of customers including substantial accounts, with power and data center space already contracted to accommodate it, and said any capital raise would be modest and done with shareholder interests in mind. McGowan said recent deals are coming in at higher pricing, that the $11.6B-style deals represent the largest volume and longest term and therefore the lowest unit pricing — a floor — and that margins are insulated because component cost increases can be passed into pricing on new deals.

Will margin lag in the fourth quarter before revenue steps up next year, and what direction should we expect?

McGowan said colocation costs come in ahead of revenue on large build-outs and that long-term colo commitments carry escalators requiring straight-line treatment, creating a noncash charge equal to roughly 1–2 points of margin pressure next year. He expects margins to bottom in the first half of 2027, maybe a point lower than current levels and operating in the mid-20s, with additional near-term costs for network build and support, freight, and contractors, before EBITDA margin leverage expands significantly through 2028.

Potential supply chain impact
NVDAManagement said well over 90% of deployed servers are CPUs and that CPUs need far less power than GPU-based neocloud builds; an increasingly CPU-weighted CIS mix could imply relatively less GPU pull per dollar of Akamai cloud revenue than GPU-centric peers, though Akamai still supports a variety of GPUs.
MSFTLeighton noted that even hyperscalers use Akamai cloud for latency-sensitive applications; continued emphasis on edge proximity as a differentiator may shape how Akamai positions itself alongside partner-hyperscalers rather than purely against them.
DOCNAkamai said apples-to-apples pricing in recent CIS deals is higher than earlier deals and that market pricing rises with component costs; that could be a modest signal of firmer unit pricing in CPU-oriented cloud compute, though Akamai's multiyear committed contracts are not directly comparable to on-demand pricing.
FFIVAkamai's security revenue grew 9% as reported and 10% in constant currency on WAF and API Security demand, with AI cited as a tailwind; sustained growth in application security could indicate a stable-to-firming demand backdrop for competing WAF and API protection vendors.