Black Hills Corporation earnings recap

Q3 FY2026, reported November 4, 2026 · Beat 4 of last 6 quarters

Black Hills Corporation reported Q3 FY2026 revenue of $466M, a miss of 3.5% against consensus, and EPS of $0.57, a beat of 21.9%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Black Hills Corporation company page →See the earnings preview →Black Hills Corporation is in the Utilities & Energy layer →
What this means for the buildout

This quarter is a concrete example of a regulated utility converting hyperscale data center demand into contracted, utility-like infrastructure — 564 megawatts of new gas generation, 2.1 gigawatts of third-party PPAs and roughly $700 million of transmission through 2029 — which could pull forward demand for gas turbines, long-lead electrical equipment, and transmission line and substation hardware. The private microgrid plus Large Power Contract Service structure may become a template other utilities copy to serve AI load without shifting risk onto retail customers, widening the addressable pipeline of rate-based generation and transmission. Management's estimate of at least 2.5 gigawatts of earlier-stage Wyoming opportunities, partly tied to Microsoft's land purchase, suggests the load forecast in this territory is still moving up rather than settling.

Results vs consensus
EstimateActualvs est
Revenue$483M$466M-3.5%miss
EPS$0.47$0.57+21.9%beat
What was said

Black Hills reported Q3 2026 GAAP EPS of $0.54 and adjusted EPS of $0.57, up from $0.45 a year earlier, with $0.28 per share of higher margins from new rates, rider recovery and weather favorability more than offsetting higher O&M, financing and depreciation. Year-to-date adjusted EPS was $2.89 versus $2.68, and management said it remains on track for full-year adjusted EPS guidance of $4.25 to $4.45. Regulators approved new annual revenues of $17.9 million in Arkansas at a 9.8% ROE, $27.4 million in South Dakota at a 7.58% WACC subject to a four-year base rate moratorium, and $4 million in Wyoming at a 9.6% ROE and 53% equity structure, with new rates effective in October and December; the Colorado Electric review continues, seeking recovery of $184 million of investment since 2024. The 99-megawatt Lange II gas project is in final construction and scheduled for service in the fourth quarter. Commercially, the company executed definitive agreements with Google for a planned southern Wyoming data center combining 564 megawatts of company-owned gas generation at Cheyenne Prairie, 26 megawatts of industrial-tariff and market service, and management of 2.1 gigawatts of third-party resources through a private microgrid, with service beginning late 2027 and full ramp targeted for late 2030. Liquidity stood at $685 million available on the revolver after roughly $70 million of year-to-date ATM equity issuance, and the NorthWestern Energy merger awaits the Montana decision due by November 12.

Key metrics
Adjusted EPS
$0.57
vs $0.45 in Q3 2025; GAAP EPS was $0.54 after $0.03 of merger-related transaction costs
FY2026 adjusted EPS guidance
$4.25–$4.45
Reaffirmed; ~6% growth at the midpoint over 2025, with confidence in the upper half of the 4%–6% long-term growth range
Contracted Google project net income (2030)
~$150M
Combined generation returns plus microgrid management fees; ~$2.4B of unlevered free cash flow through 2048 after netting the $1.8B generation investment
Large load pipeline
600 MW in plan / 600 MW in negotiation / ≥2.5 GW exploratory
In-plan load driven by Microsoft and Meta; the planned Google data center is upside to be added to the 2027–2031 plan in February
New Wyoming generation and transmission investment announced
~$2.5B
Includes $1.8B of generation through a nonregulated affiliate and a $606M Aeolus transmission CPCN filed this week
Management outlook

Management reaffirmed 2026 adjusted EPS guidance of $4.25 to $4.45 — roughly 6% growth at the midpoint — and reiterated confidence in delivering in the upper half of its 4% to 6% long-term growth rate. The Google agreements convert a multi-year negotiation into contracted cash flows: a cash return on the $1.8 billion of company-owned generation begins during construction from mid-2027, those assets are placed in service in phases during 2028 and 2029, and microgrid management fees on approximately 2.1 gigawatts of third-party resources start in late 2027 and ramp on a contractual schedule to 2030, together producing about $150 million of net income in 2030 and an estimated $2.4 billion of unlevered free cash flow through 2048 after netting out the generation spend. Financing costs on the project are treated as a pass-through, and management said the investments will be funded with strong cash flows plus a mix of debt and equity while holding investment-grade credit metrics. Beyond Google, the company is negotiating to serve an additional 600 megawatts and sees at least 2.5 gigawatts of earlier-stage Wyoming opportunities, and it plans to fold the Google project into an updated 2027–2031 financial plan and capital forecast in February. On the merger, the only remaining approval is a written decision from the Montana Commission, now due by November 12 after a 30-day extension.

From the call

“After more than a year of active and constructive negotiations, we are thrilled to have successfully executed definitive agreements to serve Google's planned data center in Wyoming, which is outlined in some detail on Slide 4.”

on Google agreements executed

“Taken together, these earnings streams will ramp up and deliver approximately $150 million of net income in 2030.”

on Google project economics

“So I don't think there's a limit right now because we have the opportunity to use that flexible service that we have through the LPCS tariff.”

on Capacity for more large load

What analysts asked

Are the terms, rate and economics of the Google deal a fair unit-basis proxy investors should use for prospective data center deals?

Management steered away from a per-unit read, saying the focus is on contractual protections and the recovery mechanism; the material elements are not predicated on load but on the fact that many economic components are contracted.

Can you separate the $150 million of 2030 Google-related net income between generation returns and the microgrid management fee?

Those factors are confidential; the management fee is based on contractually negotiated pricing and a ramp schedule, while generation earns a cash return during construction and then a utility-like risk-adjusted return once placed in service.

How does the Google earnings contribution ramp in 2027, 2028 and 2029 before the $150 million in 2030, and is 2030 a flat line through 2048?

The management fee begins in late 2027 and ramps to 2030 on a negotiated schedule; the generation return starts mid-2027 with assets placed in service in 2028 and 2029, fully in service for 2030, when depreciation begins over 20 years through 2048. Management flagged the $2.4 billion of unlevered free cash flow as a key point, noting it is after netting out the $1.8 billion of generation spend.

Potential supply chain impact
METAMeta's Cheyenne AI data center is now expected to begin taking service in early 2027, a shift from 'later this year' on the prior call; the ramp could add near-term load-driven margin and modest incremental capital within the 600 MW already in plan.
MSFTMicrosoft's purchase of more than 3,200 acres in the Cheyenne area for future expansion sits outside the current plan; if it converts to contracted load it could expand generation and transmission needs well beyond the 600 MW planned today.
NWEThe Montana Commission's written decision, now due by November 12, is the seventh and last approval for the pending NorthWestern Energy merger; a closing could combine two utilities facing similar large-load interconnection demand, with Colstrip's role among the open questions.