Black Hills Corporation (BKH) | The Buildout — AI Infrastructure

Mkt cap · 52-wk · YTD · delayed
Updated Aug 12, 2026Q1 FY2026 reviewed
Black Hills Corporation delivers regulated electric service and transmission that power hyperscale data centers in Wyoming.
Peak load +16% YoY
Wyoming Electric set an all-time peak of 439 MW in July 2026.
Advances up to $377M
1.8 GW Cheyenne reservation extended through August 31.
600 MW by 2030
Only 600 MW of the more than 3 GW pipeline is in the plan.
1.8 GW unsigned
Reservation is a bridge; customer advances are refundable.
The Buildout Takeaway
The Wyoming data-center story is now showing up in actual system peaks, and customer cash is tied to long-lead generation equipment. The test is whether the 1.8 GW Cheyenne project moves from refundable reservation to definitive agreements in Q3.
15 analysts·8 Buy7 Hold0 Sell
Coverage is thin — only 1 price estimate, so no target is shown

FY2026 adjusted EPS $4.25–$4.45 · midpoint implies about 6% growth over 2025 adjusted EPS of $4.10 · excludes merger-related costs
Important: The Buildout is a data analytics platform. Content is generated by algorithms and AI agents using public filings, earnings transcripts, and market data. This is not personalized investment advice.
Our View

The Verdict

Black Hills Corporation is a regulated electric and gas utility that owns generation, transmission, and distribution serving customers across eight states. It is building a large-load electric service model under its Wyoming LPCS tariff that delivers power to hyperscale data centers near Cheyenne. The AI buildout reaches the company through electricity, not compute: data-center customers take regulated electric service, market energy procurement, and, as load grows, contracted or company-owned generation and transmission.

Market Cap
Revenue (TTM)$2.3B
Revenue Growth+3.6%
EBITDA Margin (TTM)35.9%
Net Debt$4.6B
Earnings Beats2 of 7
P/E (TTM)
EV/EBITDA (TTM)

What We Like

  • Wyoming Electric set an all-time peak load of 439 MW in July 2026, up 16% year over year, the 20th consecutive year of rising peak loads.
  • The data-center opportunity pipeline is more than 3 GW; 600 MW is in the base plan by 2030, with more than 2.5 GW under active negotiation.
  • The 1.8 GW Cheyenne project has $201 million of refundable customer advances received, with the agreement now providing for up to $377 million.
  • Management expects large-load demand to contribute more than 10% of growing consolidated EPS beginning in 2028.
  • The NorthWestern Energy merger is at 6 of 7 approvals, with only Montana remaining and close expected in H2 2026.

What We’re Watching

  • Definitive agreements for the 1.8 GW project are targeted for Q3 2026, after the June 30 milestone passed and the reservation was extended through August 31.
  • The reservation advances are refundable and the largest contract remains unsigned.
  • Weather was still a swing factor: Q1 was -$0.13 per share versus normal and Q2 -$0.03 per share versus normal.
  • Montana merger decision is expected mid-October to mid-November 2026; a delay could push the H2 2026 close.
Bottom Line

The large-load thesis is strengthening but unfinished: peak load is accelerating, customer-funded equipment reservations expanded, and the pipeline is several times larger than what is in the plan. The open question is whether the 1.8 GW Cheyenne project reaches definitive agreements by the end of Q3 2026.

Next upDefinitive agreements for the 1.8 GW Cheyenne project are targeted for Q3 2026; that tests whether the largest pipeline item converts from refundable reservation to contracted load. The Montana merger decision is expected mid-October to mid-November 2026.
Last Quarter — Q1 FY2026

Earnings

Q2 2026 adjusted EPS was $0.54, up from $0.38 in Q2 2025; GAAP EPS was $0.50 and included $0.04 of merger-related costs. New rates and rider recovery added $0.21 per share, while higher financing and depreciation combined for a $0.12 drag. Q2 revenue and gross margin are not disclosed in the source material; the standout was Wyoming Electric's new all-time peak load of 439 MW, up 16% year over year.

MetricQ1 FY2026Q4 FY2025Q1 FY2025YoY
Revenue$781M$636M$805M−3.0%
Gross margin27.9%41.2%36.2%-830bps
EBITDA$275M$245M$274M+0.2%
EPS$1.73$1.39$1.87−7.4%
Customer advances on 1.8 GW reservationup to $377M$201Mn/a
We are looking at finishing these agreements by the end of the quarter. We are on track to do that. If we do not do it by the end of the quarter, ask the shareholders certainly not panic in any way.— Management, 2026-08-06

Management tone: Management stayed disciplined and direct on counterparty and timing questions, but framed definitive-agreement deadlines as working milestones rather than contractual dates. They declined to quantify the 1.8 GW project's capex, megawatts, or negotiated return until negotiations are complete.

Management Guidance

FY2026 adjusted EPS guidance was held at $4.25–$4.45, excluding merger-related costs. The midpoint implies about 6% growth over 2025 adjusted EPS of $4.10. Long-term growth was reaffirmed in the upper half of 4%–6%, with large load expected to contribute more than 10% of consolidated EPS beginning in 2028 and 600 MW in the plan by 2030.

Business Trajectory

Trajectory

Consolidated Q1 2026 revenue was $780.7 million, down from $805.2 million a year earlier, driven mostly by gas revenue. Electric Utilities revenue rose to $241.6 million from $236.7 million, and electric industrial GWh rose to 707.4 from 609.8, attributed to Wyoming Electric LPCS and BCIS tariff customers. Trailing signals are mixed: revenue is decelerating and gross margin compressing, while operating margin is expanding and EBITDA margin is roughly stable. Rate and rider recovery plus O&M discipline are the near-term offsets; the main untested driver is further conversion of Wyoming large-load demand.

Revenue & Margin Trajectory
RevenueGross margin$0$500$325M$334M$464M$548M$342M$336M$436M$575M$356M$322M$501M$598M$334M$326M$478M$537M$327M$347M$486M$633M$373M$381M$562M$824M$474M$463M$791M$921M$411M$407M$592M$726M$403M$402M$597M$805M$439M$430M$636M$781M40%28%Q2'16Q3Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26
RevenueGross margin$0$500$325M$334M$464M$548M$342M$336M$436M$575M$356M$322M$501M$598M$334M$326M$478M$537M$327M$347M$486M$633M$373M$381M$562M$824M$474M$463M$791M$921M$411M$407M$592M$726M$403M$402M$597M$805M$439M$430M$636M$781M40%28%Q2'16Q3Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26
Gross margin as reported.
Share Price — 12 Months
$25$50$75$052-wk high $77Aug '25NovFeb '26MayAug '26
52-week range $58–$77.
Share Price — 12 Months
$25$50$75$052-wk high $77Aug '25NovFeb '26MayAug '26
52-week range $58–$77.
The Numbers

The Model

The model projects FY+1 revenue of $2,371M and EBITDA of $891M, a 37.6% margin. FY+2 revenue is projected at $2,558M with EBITDA of $975M, a 38.1% margin. Near-term projections are anchored by renewed rate and rider recovery and the 600 MW of data-center load already in the plan; FY+2 reflects continued regulated investment and early large-load conversion.

Revenue & EBITDA Projections
REVENUE$2.3B$2.4B$2.6BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$820M$891M$975M38.1%FY25FY+1 (E)FY+2 (E)
REVENUE$2.3B$2.4B$2.6BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$820M$891M$975M38.1%FY25FY+1 (E)FY+2 (E)
Solid bars are reported actuals; outlined bars are model projections — not company guidance.
MetricFY2025Next FY (E)Following FY (E)
Revenue$2.3B$2.4B$2.6B
YoY Growth+2.6%+7.9%
EBITDA$820M$891M$975M
EBITDA Margin35.5%37.6%38.1%

Projections are the median of 5 independent model runs. The model’s revenue sits 13.1% below analyst consensus.

FY2026 adjusted EPS guidance was held at $4.25–$4.45, excluding merger-related costs. The midpoint implies about 6% growth over 2025 adjusted EPS of $4.10. Long-term growth was reaffirmed in the upper half of 4%–6%, with large load expected to contribute more than 10% of consolidated EPS beginning in 2028 and 600 MW in the plan by 2030.

What Could Go Right — and Wrong

What good looks like
  • The 1.8 GW Cheyenne project signs definitive agreements in Q3 2026 and moves into CPCN and construction.
  • The more than 2.5 GW negotiated pipeline, including the 75 MW opportunity, converts to signed contracts.
  • Microsoft's 3,200-acre Cheyenne land position becomes additional contracted load beyond the 600 MW in the plan.
  • Meta's Cheyenne AI data center ramps later in 2026 as guided.
  • LCT-CAM is approved effective January 2027, giving direct transmission cost recovery.
What could go wrong
  • The 1.8 GW negotiation stalls or terminates after the August 31 reservation extension; advances are refundable.
  • Adverse rate-case outcomes in South Dakota Electric or Colorado Electric reset the constructive regulatory path.
  • Montana denies or delays the merger, pushing close beyond H2 2026.
  • Supply-chain inflation on turbines, transformers, and generation units raises project costs.
  • Weather volatility continues and rate and rider recovery is not enough to offset the drag.
What’s Next

Looking Ahead

The next twelve months pivot on definitive agreements for the 1.8 GW project, targeted for Q3 2026, and the Montana merger decision expected mid-October to mid-November 2026. Lange II's 99 MW in-service is scheduled for Q4 2026. LCT-CAM effectiveness is expected January 2027, and Meta's load ramp later in 2026 will test whether the second named hyperscale customer is moving from construction to operations.

Catalysts
  • Aug 20, 2026Arkansas Gas rate hearing — Final order and new rates expected in H2 2026.
  • Q3 20261.8 GW definitive agreements — Tests conversion of the largest pipeline item into contracted load.
  • Q3 202675 MW data center opportunity — Signed agreement or definitive service arrangement.
  • Mid-Oct to mid-Nov 2026Montana merger decision — Final approval gate; close expected second half 2026.
  • Q4 2026Lange II in-service — 99 MW generation project reaches commercial operation.
  • Jan 2027LCT-CAM effective — Transmission cost recovery from large-load customers begins.
Numbers

Financials

Annual Summary

MetricFY2024FY2025TTMYoY
Revenue$2.1B$2.3B$2.3B+8.6%
Gross Margin39.5%38.6%35.6%93bps
EBITDA$773M$820M$6.7B+6.0%
EBITDA Margin36.3%35.5%35.9%85bps
Net Income$273M$292M$288M+6.7%
Free Cash Flow−$25M−$146M−$1.2B
Net Cash

Key Ratios (Trailing)

Valuation
  • P/E TTM
  • EV/EBITDA TTM
  • EV/Revenue TTM
  • Price/FCF TTM
Profitability
  • Gross Margin (TTM)35.6%
  • EBITDA Margin (TTM)35.9%
  • Net Margin (TTM)12.6%
  • ROIC4.9%
  • FCF Conversion-38.1%
  • SBC / Revenue0.4%
Reference

The Company

Black Hills Corporation is a regulated electric and gas utility headquartered in Rapid City, South Dakota. It serves approximately 227,000 electric customers in Colorado, Montana, South Dakota, and Wyoming and approximately 1,138,000 gas customers across Arkansas, Colorado, Iowa, Kansas, Nebraska, and Wyoming. Its relevance to the AI buildout runs mainly through regulated electric service to large-load data centers in Wyoming under the Large Power Contract Service tariff.

The company operates as an electric generator, transmitter, distributor, and gas distributor. It runs 3 to 4 rate reviews per year across its footprint and owns a generation portfolio spanning coal, gas, and wind, with a Colorado battery storage project expected in service late 2027. It is pursuing a stock-for-stock merger with NorthWestern Energy that would create a combined company serving roughly 1.4 million customers across 8 states.

Business Segments

Electric Utilities
approximately 227,000 electric customers
Generation, transmission, and distribution in Colorado, Montana, South Dakota, and Wyoming; Q1 2026 revenue $241.6M.
Growth driver: Wyoming large-load demand and rate and rider recovery.
Gas Utilities
approximately 1,138,000 gas customers
Regulated natural gas distribution in Arkansas, Colorado, Iowa, Kansas, Nebraska, and Wyoming; Q1 2026 revenue $543.1M.
Growth driver: Recurring rate reviews across a six-state footprint.

Competitive Landscape

The competitive dynamic is defined mainly by regulated franchise territory rather than direct commodity competition. Within its service territory, BKH is the incumbent electric utility, but the record flags inferred competitive overlap from AEP in the same Cheyenne corridor based on neighbor evidence, not BKH disclosure. Hyperscale customers have alternatives if BKH execution slips.

  • AEP
    Inferred geographic competitor in the Cheyenne corridor based on neighbor evidence; AEP disclosed a fuel-cell generation facility near Cheyenne. Not confirmed by BKH as a direct competitor.
AEP overlap is inferred from AEP and analyst references, not confirmed by BKH disclosure.

Supply Chain

Black Hills sits at the physical delivery point for Wyoming data-center load, supplying electricity, transmission, and contracted generation rather than chips or buildings. Customer advances help fund long-lead generation equipment.

Supplier
Wärtsilä
Engines for the Lange II generation project; technology corroborated, exact package machine-derived.
Supplier
174 Power Global / Turkey Creek Solar
Machine-derived lead for the 200 MW Colorado solar PPA; not confirmed in filings.
Regulated grid and generation provider
BKH
Owns generation, transmission, and distribution, serving load through the LPCS tariff, market energy, and contracted or company-owned resources.
Existing customer served through market energy procurement for more than a decade.
Meta
New AI data center in Cheyenne expected to begin ramping later in 2026.
Undisclosed 1.8 GW hyperscale customer
Prospective customer with refundable advances of $201 million received, now up to $377 million.
75 MW data center customer
Separate prospective customer, part of the more than 2.5 GW pipeline.

Analysis updated Aug 12, 2026, reviewing Q1 FY2026. Prices delayed. Built with The Buildout’s published methodology. Not investment advice. No positions held. © The Buildout 2026.

More on BKH: Earnings recap