MDU Resources Group, Inc. (MDU) | The Buildout — AI Infrastructure

——Mkt cap — · 52-wk —–— · YTD — · delayed
Updated Sep 22, 2026Q2 FY2026 reviewed
MDU Resources Group sells regulated electric power and pipeline capacity into the North Dakota data-center buildout.
Data center load >1GW
Up from 580 MW signed a quarter earlier; ~240 MW online
Bakken East ~1.2 Bcf/d
All open-season customers executed; design is 1.4 Bcf/d
Net income +55.5%
Q2 2026 net earnings $21.3M vs $13.7M a year earlier
7(c) filing slips
Bakken East FERC filing moved from Q3 to Q4 2026
The Buildout Takeaway
The commercial book is moving faster than the financial statements. Contracted data-center megawatts and Bakken East precedent agreements both stepped up sharply between the Q1 and Q2 2026 calls, but neither sits in guidance: one waits on a state commission approval, the other on a Board investment decision and an undisclosed financing structure.
18 analysts·8 Buy8 Hold2 Sell
Coverage is thin — only 1 price estimate, so no target is shown

2026 EPS $0.93–$1.00 · Long-term EPS growth 6%–8% · Capital program ~$3.1B for 2026–2030, with Bakken East incremental
Important: The Buildout is a data analytics platform. Content is generated by algorithms and AI agents using public filings, earnings transcripts, and market data. This is not personalized investment advice.
Our View

The Verdict

MDU Resources Group is a regulated energy delivery company. It generates, transmits and distributes electricity, sells natural gas at retail, and owns a FERC-regulated interstate pipeline. Its place in the AI buildout is load: data-center developers in North Dakota buy firm electric capacity from its utility, and part of the demand behind its proposed Bakken East pipeline is power generation that may serve data centers. MDU does not sell compute, cooling or any AI value-chain product. It sells the power and the pipeline capacity those campuses need. The current data-center model is capital-light: the customer pays for the connection, and a share of the benefit flows back to retail customers as a bill credit.

Market Cap—
Revenue (TTM)$1.8B
Revenue Growth−1.1%
EBITDA Margin (TTM)31.6%
Net Debt$2.5B
Earnings Beats4 of 7
P/E (TTM)—
EV/EBITDA (TTM)—

What We Like

  • Data-center load under signed electric service agreements stepped up from 580 MW to over 1,000 MW in one quarter, with approximately 240 MW online versus 180 MW a quarter earlier.
  • Management says Bakken East now has executed agreements with all customers that submitted binding open-season interest, totaling nearly 1.2 Bcf/d against a 1.4 Bcf/d design, with a negotiated option toward nearly all of the original interest.
  • Projected Bakken East capital of $2.7 billion to $3.2 billion is explicitly incremental to the $3.1 billion 2026–2030 capital plan, which splits roughly $1.1 billion electric, $1.4 billion natural gas distribution and $643 million pipeline.
  • The State of North Dakota is a contracted Bakken East counterparty; a prior call quantified the commitment at $50 million annually for ten years, and the Q2 2026 call confirmed the state is part of the executed precedent agreements without repeating the figure.
  • The data-center model shares margin with retail customers — approximately $70 per year per average retail customer today, potentially over $200 per year when all volumes are online — while data-center customers pay the costs of connecting to the system.

What We’re Watching

  • The Bakken East FERC Section 7(c) filing moved from Q3 2026 to Q4 2026, attributed to longer precedent-agreement negotiations; a final investment decision is intended ahead of the filing but has no stated date.
  • The 430 MW Polaris Forge 3 agreement with Applied Digital is pending North Dakota Public Service Commission approval and is excluded from 2026 EPS guidance and the 6%–8% long-term EPS growth objective.
  • Pipeline segment earnings fell year over year in both reported quarters — $15.3 million versus a $17.2 million record in Q1 2026, and $14.4 million versus $15.4 million in Q2 2026 — with a $31 million FERC rate case effective December 1, 2026 subject to refund.
  • Bakken East's financing structure is undecided; management says all options are on the table and that a majority stake matters, with a strategic partner possible and financial partners also showing potential appetite, but no structure has been disclosed.
Bottom Line

The thesis is strengthening on the commercial side and stable on the financial side. Contracted data-center load and Bakken East precedent agreements both advanced materially between the two calls, and management reaffirmed guidance at both. Against that, the key regulatory filing slipped a quarter, a large slice of the data-center book is unapproved, and the pipeline segment has posted two quarters of year-over-year earnings declines. The open question is which clock sets the forecast: the fast commercial one or the regulated one.

Next upThe next dated items are the North Dakota electric interim rate order, requested to begin September 1, 2026, and the Bakken East Section 7(c) filing now expected in Q4 2026, with a final investment decision intended ahead of it. Management pointed to its normal late-November 2026 capital update as the point where a revised Bakken East capital range could appear.
Last Quarter — Q2 FY2026

Earnings Beat

MDU reported Q2 2026 results on August 6, 2026: revenue of $375.2 million and EBITDA of $157.3 million, a 41.9% EBITDA margin. Net earnings were $21.3 million, up 55.5% from $13.7 million a year earlier. Data-center load under signed electric service agreements rose from 580 MW to over 1,000 MW quarter over quarter, with approximately 240 MW online versus 180 MW, and the quarter included a new 430 MW agreement with Applied Digital for its Polaris Forge 3 campus. Year-to-date 2026 net earnings were $102.1 million, or $0.49 per share, versus $95.7 million, or $0.47 per share, in the first six months of 2025.

MetricQ2 FY2026Q1 FY2026Q2 FY2025YoY
Revenue$375M$606M$351M+6.8%
Gross margin100.0%25.0%30.6%+6940bps
EBITDA$157M$170M$82M+91.4%
EPS$0.10$0.39$0.07+49.6%
Data center load under signed ESAs>1,000 MW580 MWn/a—
Data center load online~240 MW180 MWn/a—
Additional volumes expected over the next few years as additional buildings are constructed.— Nicole Kivisto, President and CEO, 2026-08-06

Management tone: Management's tone shifted toward greater confidence on financing and delivered a concrete commercial step. On the Q1 2026 call the Bakken East financing answer was that all options were on the table and that a majority stake mattered; on the Q2 2026 call management said it feels very confident in the ability to finance a project like this and pointed to appetite for these types of assets. The data-center discussion moved from pursuing additional customers to a named 430 MW electric service agreement. Against that, the Section 7(c) filing slipped a quarter, and management declined to date the investment decision beyond saying it would come before the filing. The transcript-intelligence file notes that the phrase about being comfortable with the schedule preceded the prior slip and reappeared in the Q2 Q&A.

Management Guidance

Management reaffirmed 2026 EPS guidance of $0.93–$1.00 and its long-term EPS growth objective of 6%–8%, and kept the 2026–2030 capital program at approximately $3.1 billion: approximately $1.1 billion electric, $1.4 billion natural gas distribution and $643 million pipeline. Bakken East remains incremental to that plan. The 430 MW Polaris Forge 3 agreement is excluded from guidance and from the long-term growth rate until North Dakota Public Service Commission approval. The targeted annual customer growth rate is 1%–2%. The 60%–70% dividend payout ratio target was stated on the Q1 2026 call and was not repeated on the Q2 2026 call.

Business Trajectory

Trajectory

MDU's reported revenue line moves with pass-through natural gas costs, which run through revenue and expense together, so the top line is not a clean read on momentum. Revenue was $606.0 million in Q1 2026 versus $674.8 million a year earlier, and $375.2 million in Q2 2026; the Q1 decline was largely lower purchased natural gas sold, recovered in customer rates. EBITDA margins are expanding: Q1 2026 came in at 28.0% and Q2 2026 at 41.9%, against 24.3% and 23.4% a year earlier. The segments point three ways — the electric utility is up on rate recovery and early data-center load, natural gas distribution operating income rose on lower gas costs and new rates while higher interest expense pulled at the bottom line, and the pipeline is down on higher depreciation from newly placed assets and lower other income. Trailing-twelve-month revenue is $1,830.3 million and EBITDA $578.0 million, a 31.6% margin, against negative free cash flow as capital spending runs ahead of cash generation.

Revenue & Margin Trajectory
RevenueGross margin$0$1.0B$1.2B$1.0B$938M$1.1B$1.3B$1.2B$976M$1.1B$1.3B$1.2B$1.1B$1.3B$1.6B$1.4B$1.2B$1.4B$1.6B$1.4B$1.2B$1.4B$1.6B$1.4B$1.4B$1.0B$1.0B$1.9B$1.4B$1.1B$1.0B$1.1B$588M$344M$290M$536M$675M$351M$315M$534M$606M$375M20%100%Q3'16Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26Q2
RevenueGross margin$0$1.0B$1.2B$1.0B$938M$1.1B$1.3B$1.2B$976M$1.1B$1.3B$1.2B$1.1B$1.3B$1.6B$1.4B$1.2B$1.4B$1.6B$1.4B$1.2B$1.4B$1.6B$1.4B$1.4B$1.0B$1.0B$1.9B$1.4B$1.1B$1.0B$1.1B$588M$344M$290M$536M$675M$351M$315M$534M$606M$375M20%100%Q3'16Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26Q2
Gross margin as reported.
Share Price — 12 Months
$10$20$052-wk high $23Sep '25DecMar '26JunSep '26
52-week range $17–$23.
Share Price — 12 Months
$10$20$052-wk high $23Sep '25DecMar '26JunSep '26
52-week range $17–$23.
The Numbers

The Model

The model projects FY+1 revenue of $1,855.7 million and EBITDA of $546 million, a 29.4% margin, and FY+2 revenue of $2,057 million and EBITDA of $613 million, a 29.8% margin. For a regulated utility the forward earnings trajectory is a function of rate-base growth minus financing cost, and the rate-case calendar is where that resolves — which anchors the near term, alongside the data-center load already online. FY+2 carries the next step of the data-center ramp. The FY+2 revenue spread across the five model runs is 12%, from $1,980 million to $2,224 million. Bakken East's in-service dates of late 2029 and late 2030 sit outside both projection years.

Revenue & EBITDA Projections
REVENUE$1.9B$1.9B$2.1BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$497M$546M$613M29.8%FY25FY+1 (E)FY+2 (E)
REVENUE$1.9B$1.9B$2.1BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$497M$546M$613M29.8%FY25FY+1 (E)FY+2 (E)
Solid bars are reported actuals; outlined bars are model projections — not company guidance.
MetricFY2025Next FY (E)Following FY (E)
Revenue$1.9B$1.9B$2.1B
YoY Growth—−1.0%+10.8%
EBITDA$497M$546M$613M
EBITDA Margin26.5%29.4%29.8%

Projections are the median of 5 independent model runs. The model’s revenue sits 5.8% below analyst consensus.

Management reaffirmed 2026 EPS guidance of $0.93–$1.00 and its long-term EPS growth objective of 6%–8%, and kept the 2026–2030 capital program at approximately $3.1 billion: approximately $1.1 billion electric, $1.4 billion natural gas distribution and $643 million pipeline. Bakken East remains incremental to that plan. The 430 MW Polaris Forge 3 agreement is excluded from guidance and from the long-term growth rate until North Dakota Public Service Commission approval. The targeted annual customer growth rate is 1%–2%. The 60%–70% dividend payout ratio target was stated on the Q1 2026 call and was not repeated on the Q2 2026 call.

What Could Go Right — and Wrong

What good looks like
  • North Dakota regulators approve the 430 MW Polaris Forge 3 agreement, and the load enters guidance and the long-term growth rate.
  • The negotiated Bakken East option is exercised, taking contracted volumes from nearly 1.2 Bcf/d toward the 1.4 Bcf/d design.
  • Bakken East reaches a final investment decision with MDU retaining a majority stake, and the project enters the capital plan.
  • Filed rate cases land at or near ask — North Dakota's approximately $34.5 million, Washington's $25.1 million and $18.1 million, and Oregon's approximately $12.2 million settlement.
  • Additional data-center electric service agreements are executed on top of the current signed book.
What could go wrong
  • A second slip in the Bakken East Section 7(c) filing pushes the investment decision, capital-plan inclusion and eventual revenue further to the right.
  • The North Dakota Public Service Commission delays or declines the Polaris Forge 3 agreement, keeping 430 MW out of the numbers.
  • Steel prices, contractor labor or compression orders push Bakken East above the $2.7–$3.2 billion range.
  • The Bakken East financing structure is resolved on terms that are dilutive or reduce MDU's stake below a majority.
  • Behind-the-meter generation routes around the utility — Applied Digital owns approximately 10% of Base Electron, a roughly 1.2 GW gas generation developer in the Dakotas.
What’s Next

Looking Ahead

Over the next twelve months the nearest dated item is the North Dakota electric rate case, where approximately $26.3 million of interim relief was requested to begin September 1, 2026 within an approximately $34.5 million annual ask. The Bakken East Section 7(c) filing is now expected in the fourth quarter of 2026, with a final investment decision intended ahead of it, and management pointed to its normal late-November 2026 capital update as the point where a revised Bakken East range could appear. FERC pipeline rates take effect December 1, 2026 subject to refund; Montana's $10 million settlement and Oregon's approximately $12.2 million settlement are pending; and a Minnesota gas rate case is anticipated later in 2026. The North Dakota Public Service Commission decision on the 430 MW Polaris Forge 3 agreement has no stated date, and Bakken East first in-service is not until late 2029.

Catalysts
  • Sept 1, 2026ND electric interim rates — Approximately $26.3M interim within a ~$34.5M annual ask
  • Q4 2026Bakken East 7(c) filing — FID intended ahead of it; filing slipped from Q3 2026
  • Late November 2026Capital plan update — Possible revised Bakken East range; plan at ~$3.1B
  • Dec 1, 2026FERC pipeline rates effective — $31M annual ask, ~30% depreciation-driven; subject to refund
  • Later in 2026Minnesota gas rate case — Filing anticipated; no figure or date disclosed
  • UndatedPolaris Forge 3 decision — ND PSC approval would bring 430 MW into guidance
Numbers

Financials

Annual Summary

MetricFY2024FY2025TTMYoY
Revenue$1.8B$1.9B$1.8B+6.7%
Gross Margin33.0%30.6%42.4%238bps
EBITDA$466M$497M$578M+6.7%
EBITDA Margin26.5%26.5%31.6%+1bps
Net Income$281M$190M$197M-32.2%
Free Cash Flow−$20M−$319M−$351M—
Net Cash————

Key Ratios (Trailing)

Valuation
  • P/E TTM—
  • EV/EBITDA TTM—
  • EV/Revenue TTM—
  • Price/FCF TTM—
Profitability
  • Gross Margin (TTM)42.4%
  • EBITDA Margin (TTM)31.6%
  • Net Margin (TTM)10.8%
  • ROIC4.5%
  • FCF Conversion-60.7%
  • SBC / Revenue0.3%
Reference

The Company

MDU Resources Group describes itself as a pure-play regulated energy delivery business. It generates, transmits and distributes electricity and provides natural gas distribution, transportation and storage services, regulated by state public service commissions and/or the FERC. It became this deliberately: the company separated its former construction-services segment, Everus, into an independent public company on October 31, 2024, with transition services completed as of March 31, 2026. The electric utility serves retail customers in 185 communities and adjacent rural areas. Natural gas distribution serves 343 communities across eight states. The pipeline business, WBI Energy Transmission, runs over 3,800 miles of FERC-regulated natural gas transmission and storage lines and made up approximately 94% of segment revenue in 2025.

The utility operates through wholly-owned subsidiaries: Montana-Dakota for electric and gas, Cascade and Intermountain for gas, and WBI Energy for the pipeline and a non-regulated cathodic-protection business. MDU holds ownership stakes in generation rather than owning it outright — 25% of the 427-MW Coyote Station, 22.7% of the 475-MW Big Stone Station, 25% of the 100-MW Wygen III, 49.0% of the 250-MW Badger Wind Farm, plus the 88-MW Heskett Unit 4 peaking turbine. Earnings come through rate cases rather than commodity spreads, and management describes a standing plan of filing three to five rate cases annually. Combined retail customer growth was 1.4% year over year as of Q1 2026, within a targeted 1%–2%. The quarterly dividend was raised to $0.145 per share, or $0.56 annualized, on August 13, 2026.

Business Segments

Electric
Retail electric service in 185 communities
Operated through subsidiary Montana-Dakota, serving residential, commercial, industrial and municipal customers in 185 communities and adjacent rural areas.
Growth driver: Data-center load plus new rates
Natural gas distribution
343 communities across eight states; largest segment by revenue
Retail natural gas sales and transportation through Montana-Dakota, Cascade and Intermountain; $462.3 million of external operating revenues in Q1 2026.
Growth driver: Customer growth, new rates and volumes
Pipeline
Over 3,800 miles; ~94% of segment revenue in 2025
WBI Energy Transmission is a FERC-regulated interstate system; a non-regulated cathodic-protection business made up the other 6% of segment revenue.
Growth driver: Bakken East, pending FID

Competitive Landscape

The 10-K names what MDU's electric segment competes against: rural electric cooperatives, on-site generators, co-generators and municipally owned systems. The evidence set adds a structural alternative — behind-the-meter generation, where a data center builds its own plant rather than buying delivered power. WMB delivered 200 MW at its Socrates project in under 18 months, and Applied Digital, MDU's named data-center customer, owns roughly 10% of Base Electron, a roughly 1.2 GW front-of-the-meter gas generation developer in the Dakotas. The intel file reads that ownership as potentially complementing or competing with MDU-supplied power, and labels the read as inferred. MDU's own defense is the customer bill credit, which is designed to keep it the preferred counterparty for regulators and communities.

  • Rural electric cooperatives
    Named in the 10-K's electric-segment competition language.
  • On-site generators and co-generators
    Named in the 10-K's electric-segment competition language.
  • Municipally owned systems
    Named in the 10-K's electric-segment competition language.
  • Appears in the supply-chain wiring layer only; not discussed in company filings.
  • Appears in the supply-chain wiring layer only; not discussed in company filings.
The first three rows come from the 10-K's electric-segment competition disclosure; Black Hills Corporation and Xcel Energy appear only in the supply-chain wiring layer, which is lower-confidence and carries no supporting quotes.

Supply Chain

MDU buys coal and purchased power, holds minority stakes in generation, and delivers electricity and natural gas to retail customers across eight states plus FERC-regulated pipeline service. Its data-center customers sit downstream of it. No neighbor transcript in the source set names MDU.

Supplier
Coyote Creek
Coal supply to Coyote Station; contract expires December 2040.
Supplier
Navajo Transitional Energy Company, LLC
Coal supply to Big Stone Station; meets all fuel requirements through 2026.
Supplier
Wyodak Resources Development Corp.
Coal supply to Wygen III at contracted pricing through June 1, 2060.
Supplier
Black Hills Power, Inc.
Power purchase of up to 49,000 kW of capacity annually through December 31, 2028.
→
Regulated delivery franchise
MDU
Three segments — electric utility, natural gas distribution, and a FERC-regulated interstate pipeline.
→
Applied Digital
430 MW
Polaris Forge 3 AI factory near Center, ND; 180 MW Ellendale data center already served.
State of North Dakota
$50M/yr for 10 years
Firm natural gas capacity commitment on the proposed Bakken East pipeline.
Montana-Dakota (affiliate)
19%
Share of WBI Energy Transmission's 2025 subscribed firm transportation contract demand.
One unnamed third-party customer
~17%
Share of WBI's 2025 revenue; identity not disclosed.

Analysis updated Sep 22, 2026, reviewing Q2 FY2026. Prices delayed. Built with The Buildout’s published methodology. Not investment advice. No positions held. © The Buildout 2026.

More on MDU: Earnings recap