Core Scientific, Inc. earnings recap

Q3 FY2026, reported November 5, 2026 · Beat 2 of last 7 quarters

Core Scientific, Inc. reported Q3 FY2026 revenue of $233M, a beat of 18.6% against consensus.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Core Scientific, Inc. company page →See the earnings preview →Core Scientific, Inc. is in the Operators layer →
What this means for the buildout

Core Scientific is now a live proof point that contracted AI colocation capacity converts into revenue quickly: 485 MW billing and a 57% Adjusted EBITDA margin on $215 million of colocation revenue in a single quarter, with another ~100 MW in commissioning. The AMD program — 530 MW contracted plus ~1.9 GW under reservation, with deadlines concentrated in 2027 — combined with a ~$1.8 billion run-rate revenue target on ~1.1 GW, extends visible high-density data center demand into 2028. Management's message that capital, not demand, is the binding constraint on new development suggests the buildout's pace will increasingly be set by project finance conditions rather than by customer appetite.

Results vs consensus
EstimateActualvs est
Revenue$197M$233M+18.6%beat
EPS-$0.046$0.47—Not comparable

EPS: The gap is too large to be a like-for-like comparison (the estimate and the result may be on different bases), so we do not call it a beat or a miss.

These figures come from the same table as our earnings calendar. The write-up below may quote the company's own adjusted or reported figures, which can differ.

What was said

Core Scientific delivered another 90 MW into billing in the third quarter, bringing total billable capacity to CoreWeave to 485 MW of the 590 MW contracted across five campuses, with the remaining ~100 MW in commissioning at Dalton Phase 2. GAAP colocation revenue rose nearly 60% sequentially to $215 million and Adjusted EBITDA more than tripled to $134 million, expanding margin to 57% from 25%. The Bitcoin mining wind-down continued, with nearly 50% fewer miners online at quarter-end than at year-end 2025, and management expects to complete the exit during the fourth quarter. Liquidity stood at approximately $1.7 billion — ~$800 million cash, ~$840 million restricted cash and debt service reserves, and $100 million revolver availability — down roughly $1 billion sequentially on $540 million of CapEx, primarily AMD sites, and ~$440 million for the Polaris acquisition. On the regulatory front, management said its sites received conditional classifications consistent with expectations under ERCOT's Batch Zero process, Pecos and Hunt secured stormwater permits, and Hunt was included in the November Quarterly Stability Assessment.

Key metrics
GAAP Colocation Revenue
$215M
Up nearly 60% sequentially; another 90 MW brought into billing during the quarter
Adjusted EBITDA
$134M
More than tripled from $41M in Q2 2026
Adjusted EBITDA Margin
57%
Up from 25% in the prior quarter
CoreWeave Billing Capacity
485 MW
Of 590 MW contracted across five campuses; up from 120 MW at the beginning of the year, with ~100 MW in commissioning
Contracted Portfolio Run-Rate
$1.8B revenue / $1.6B NOI
Expected average annual run-rate once ~1.1 GW contracted across CoreWeave and AMD is fully delivered and billing
Management outlook

Management guided to a double-digit sequential increase in fourth quarter revenue as additional megawatts begin billing and prior deliveries contribute a full quarter, and expects the remaining ~100 MW of CoreWeave capacity at Dalton Phase 2 to be delivered by early next year. The AMD program remains on track to begin delivery at Pecos in the first half of 2027, with roughly half of the initial 530 MW online next year and the balance through 2028; AMD also holds exclusive reservation rights on approximately 1.9 GW more across Muskogee, Hunt and Pecos, with the overwhelming majority of commitment deadlines falling in 2027. Financing is the stated gating item: project bonds remain the expected approach for the remaining AMD build-out, management is evaluating other debt options, and it explicitly does not expect to issue additional equity or equity-linked securities to fund phase one, with roughly $650 million of Tranche 1 warrant proceeds expected around January 2027. The company expects to exit Bitcoin mining by year-end and enter 2027 as a pure-play high-density colocation provider, with cash SG&A in the low $30 million range per quarter as a baseline. Beyond contracted capacity, management is evaluating approximately 2 GW of potential new sites for 2029+ energization and described a widening set of acquisition opportunities, while saying it will stay selective and prioritize delivery of existing commitments.

From the call

“GAAP colocation revenue increased nearly 60% sequentially, while Adjusted EBITDA reached over $130 million, up from $41 million in the second quarter.”

on Quarterly financial inflection

“We have approximately 1.1 GW contracted across CoreWeave and AMD. Once fully delivered and billing, we expect that portfolio alone to generate $1.8 billion in average annual run rate revenue and $1.6 billion in NOI.”

on Contracted portfolio economics

“I think the overarching theme right now in the market is capital is the throttle on all new development.”

on Capital as competitive differentiator

What analysts asked

Following the election, is there risk to the PUC in December or any delays to the final Base Load review, and what are the expectations there?

Adam Sullivan said the differentiator is site status: Pecos already had a building in place, chillers set and was previously an energized Bitcoin mining site, making it a low-risk proposition for early 2027; Hunt was approved for power in 2024 and the November ERCOT study is the final stage, typically occurring one to two quarters before energization. He called both Texas sites under development very low risk.

What are you seeing in the project financing market for the AMD builds — changes in covenants, loan-to-cost levels, or is it paused until next year?

CFO Jim Nygaard said the project bond market is absolutely open and diligence has become more comprehensive, but there has been no change in terms or covenants. He highlighted AMD's credit profile as a key selection criterion, noted there is little AMD paper outstanding for what they are about to do, and said the market has strong appetite. Adam added there are five separate leases across five locations, giving flexibility on how to package and sequence, supported by balance sheet liquidity.

Have you filed the necessary permits for behind-the-meter generation, and what is the plan for the January warrant exercise cash?

Adam Sullivan said the company has not yet filed air permits, which will be done in conjunction with the IPP it ultimately selects, and that it has a narrowed list of IPPs and generation units being chosen alongside AMD. Jim Nygaard said the cash-only warrant proceeds are expected to be prioritized toward proactive builds and deployed as equity in reserved sites as AMD exercises over time.

Potential supply chain impact
CRWVCoreWeave remains the sole colocation customer and now accounts for 485 MW of the 590 MW contracted, with management emphasizing that CoreWeave has already funded the overwhelming majority of the build-out and that the facilities rank among its most economically attractive. Continued CoreWeave financing scrutiny could pressure sentiment even as the physical capacity and lease economics appear largely locked in.
DUKDuke Energy is the documented utility relationship tied to the Marble, North Carolina campus, which was fully turned over to operations earlier this year and is now part of the billing base. Incremental load growth at that site may depend on Duke's interconnection and rate treatment for high-density data center customers.
APLDApplied Digital is a documented competitor in converting digital mining facilities to HPC. CORZ's commentary that more powered land and even contracted projects are coming to market as peers run short of capital could be a relative signal of advantage for better-capitalized developers, though it may also indicate tighter financing broadly.
CIFRCipher Mining is a documented competitor that has signed HPC leases. Management's point that bidder counts on powered land are shrinking while valuations hold could shape how aggressively CORZ and peers pursue acquisitions in 2027.
IRENIREN is a documented competitor with HPC leases. CORZ's decision to price behind-the-meter solutions around BESS-backed generation may become a competitive design benchmark as AI tenants trade uptime for cost of deployment.
CLSKCleanSpark is listed among CORZ's North American competitors. CORZ's exit from Bitcoin mining by year-end removes it from the self-mining competitive set, potentially shifting hashrate and power-contract dynamics for remaining miners.