Cipher Mining Inc. (CIFR) | The Buildout — AI Infrastructure

Mkt cap · 52-wk · YTD · delayed
Updated Aug 12, 2026Q1 FY2026 reviewed
Cipher Digital develops and operates industrial-scale data centers delivering contracted, power-dense compute capacity to hyperscalers.
907 MW op. & contracted
Three HPC leases plus 207 MW Odessa mining; $11.4B contracted revenue.
$793M NOI
Average annualized contracted NOI, Oct 2026-Sep 2036.
5.3 GW pipeline
11 sites; 4.4 GW expected future developments.
Revenue -29% QoQ
Q2 $25M vs $35M Q1; first HPC rent began Aug 2026.
The Buildout Takeaway
The mining-to-HPC pivot has passed its first real test: Black Pearl delivered two months ahead and rent has commenced, while Barber Lake rent follows in October. The open question is whether the ERCOT batch-process delay stalls the 2028+ uncontracted pipeline.
13 analysts·13 Buy0 Hold0 Sell
Median target$32  Range $22–$44 · 10 estimates

~$11.4B contracted revenue across 10-15 year base lease terms · ~$793M average annualized NOI (Oct 2026-Sep 2036) · ~5.3 GW portfolio across 11 sites
Important: The Buildout is a data analytics platform. Content is generated by algorithms and AI agents using public filings, earnings transcripts, and market data. This is not personalized investment advice.
Our View

The Verdict

Cipher Digital is a vertically integrated developer and operator of industrial-scale data centers. It originates land, power, and interconnection, then designs, builds, and operates turnkey campuses for hyperscalers and HPC tenants under long-term leases. That makes it a supplier of the power-dense physical capacity AI compute requires.

Market Cap
Revenue (TTM)$210M
Revenue Growth+37.9%
EBITDA Margin (TTM)-87.7%
Net Debt$944M
Earnings Beats2 of 7
P/E (TTM)
EV/EBITDA (TTM)

What We Like

  • Three signed HPC campus leases anchor approximately $11.4B of contracted revenue across 10-15 year base lease terms (Q1 2026 call).
  • Contracted NOI guided to about $793M average annualized from October 2026 through September 2036 (Q2 2026 call).
  • Black Pearl first capacity delivered in August 2026, two months ahead of schedule, with rent commenced.
  • Three project-level bond financings priced tighter sequentially: Barber Lake 7.125%, Black Pearl 6.125%, Stingray 6.000%.
  • Portfolio about 5.3 GW across 11 sites; 477 MW potentially available in 2027 outside the ERCOT batch process.

What We’re Watching

  • ERCOT Batch Zero timing slipped from June 2026 after the Texas Governor's letter; no firm new date was given.
  • Stingray timeline wording shifted from Q4 2026 energization to first-half 2027 delivery, not explicitly reconciled.
  • Revenue continues to fall: $59.7M Q4 2025 to $35M Q1 2026 to $25M Q2 2026 while HPC rent ramps.
  • Tenant concentration is high: three HPC tenants anchor the contracted book; one is undisclosed.
Bottom Line

The contracted near-term thesis is strengthening: the first HPC rent began early, and the third project bond priced at the lowest coupon yet. The farther-out thesis is unresolved: the 2028+ pipeline depends on an ERCOT decision that just slipped. The key open question is whether management can convert its 477 MW of near-term uncontracted capacity into signed leases before the mining bridge fully winds down.

Next upBarber Lake Phase 1 delivery is expected in September 2026, with rent in October 2026; that is the next test of whether the second contracted NOI stream converts on schedule. Beyond that, the ERCOT Batch Zero decision, now undated after the Governor's letter, gates the 2028+ pipeline.
Last Quarter — Q1 FY2026

Earnings

Q2 2026 revenue was $25 million, down from $35 million in Q1, reflecting the planned decommissioning of bitcoin mining at Black Pearl. Net loss widened to $268 million, driven largely by a $150.5 million noncash warrant remeasurement loss. Unrestricted cash rose $204 million to $832 million.

MetricQ1 FY2026Q4 FY2025Q1 FY2025YoY
Revenue$35M$60M$49M−29.0%
Gross margin-105.9%1.2%40.4%-14630bps
EBITDA−$29M−$177M$6M−608.8%
EPS$-0.28$-1.92$-0.11+160.8%
I'm proud to announce the early delivery of data center capacity at Black Pearl, 2 months ahead of schedule. At the request of our tenant, we executed an amendment to the lease that accelerated the development time line of initial capacity. I'm pleased to report that we delivered that capacity and rent has commenced at the site.— Tyler Page, CEO, August 4, 2026

Management tone: Management's tone shifted from Q4 2025 transition framing, to Q1 2026 execution framing ("2026 is the year of execution"), to Q2 2026 flywheel framing ("each step forward in the progress of our flywheel is now reinforcing the next"). On the Q2 call management was candid about the ERCOT delay and unusually unhedged about demand.

Management Guidance

Management does not give traditional revenue or EPS guidance. Its formal forward figures are contracted capacity, revenue, and NOI: approximately $11.4B of contracted revenue across 10-15 year base lease terms; approximately $793M average annualized NOI from October 2026 through September 2036; and a portfolio of roughly 5.3 GW across 11 sites. The company also said it expects no additional equity based on the current forecast, with the CFO's caveat that pipeline or lease materialization could create a future need.

Business Trajectory

Trajectory

Reported revenue is declining by design: $59.7M in Q4 2025, $35M in Q1 2026, and $25M in Q2 2026, as bitcoin mining at Black Pearl was decommissioned. The forward picture shifts to contracted HPC NOI: Black Pearl rent commenced in August 2026 and Barber Lake rent is expected in October 2026, while contracted HPC NOI guidance rose from about $669M at Q4 2025 to about $793M at Q2 2026. Gross, operating, and EBITDA margins are compressing through the transition, and Q1 2026 adjusted EBITDA was negative at -$48.2M.

Revenue & Margin Trajectory
RevenueGross margin$0$25$50$0M$0M$0M$0M$0M$0M$0M$0M$0M$0M$3M$22M$31M$30M$43M$48M$37M$24M$42M$49M$44M$72M$60M$35M0%-106%Q2'20Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26
RevenueGross margin$0$25$50$0M$0M$0M$0M$0M$0M$0M$0M$0M$0M$3M$22M$31M$30M$43M$48M$37M$24M$42M$49M$44M$72M$60M$35M0%-106%Q2'20Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26
Gross margin as reported.
Share Price — 12 Months
$10$20$052-wk high $26Aug '25NovFeb '26MayAug '26
52-week range $5–$26.
Share Price — 12 Months
$10$20$052-wk high $26Aug '25NovFeb '26MayAug '26
52-week range $5–$26.
The Numbers

The Model

The model projects FY+1 revenue of $249M and EBITDA of $43M (17.4% margin), rising to FY+2 revenue of $770M and EBITDA of $601M (78.0% margin). The near-term projection is anchored by early HPC rent at Black Pearl and Barber Lake; FY+2 reflects the step-up as the contracted HPC NOI stream ramps.

Revenue & EBITDA Projections
REVENUE$224M$249M$770MFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN−$149M$43M$601M78.0%FY25FY+1 (E)FY+2 (E)
REVENUE$224M$249M$770MFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN−$149M$43M$601M78.0%FY25FY+1 (E)FY+2 (E)
Solid bars are reported actuals; outlined bars are model projections — not company guidance.
MetricFY2025Next FY (E)Following FY (E)
Revenue$224M$249M$770M
YoY Growth+11.2%+209.2%
EBITDA−$149M$43M$601M
EBITDA Margin-66.7%17.4%78.0%

Projections are the median of 5 independent model runs.

Management does not give traditional revenue or EPS guidance. Its formal forward figures are contracted capacity, revenue, and NOI: approximately $11.4B of contracted revenue across 10-15 year base lease terms; approximately $793M average annualized NOI from October 2026 through September 2036; and a portfolio of roughly 5.3 GW across 11 sites. The company also said it expects no additional equity based on the current forecast, with the CFO's caveat that pipeline or lease materialization could create a future need.

What Could Go Right — and Wrong

What good looks like
  • Black Pearl and Barber Lake deliver on schedule and convert leases into the contracted ~$793M average annualized NOI stream.
  • The 477 MW outside the ERCOT batch process (Odessa, Reveille, Ulysses) is leased at improving terms.
  • Colchis, Mikeska, and McLennan are expected in ERCOT Batch Zero and would move the 2028-2029 pipeline forward.
  • Odessa PPA renegotiation converts the 207 MW legacy mining site to HPC by late calendar 2027.
  • Behind-the-meter generation or compute ownership becomes a committed project and expands the model beyond colocation.
What could go wrong
  • Stingray or Barber Lake timing slips further, delaying rent commencement and contracted NOI conversion.
  • The ERCOT batch-process audit reorders or delays the 2028+ pipeline beyond management's expected 2028-2029 window.
  • Labor and equipment inflation raises build budgets and cost per megawatt beyond contracted caps.
  • A tenant concentration event at one of the three HPC tenants reduces the contracted NOI base.
  • Financing markets tighten enough to force an equity raise the company currently says it does not need.
What’s Next

Looking Ahead

Over the next 12 months, the story shifts from signing leases to delivering and converting them into rent. Barber Lake Phase 1 is due for September 2026 delivery with October rent; Black Pearl's remaining Phase 1 and Phase 2 capacity continues delivery; Stingray is expected in first-half 2027. The biggest external gate is the now-undated ERCOT Batch Zero decision, which gates the 2028+ pipeline.

Catalysts
  • Q3 2026Stingray foundation and steel start — Tests third leased campus staying on schedule; earthwork and underground electrical underway.
  • September 2026Barber Lake Phase 1 delivery — Tests second contracted HPC delivery; tenant has already begun beneficial use.
  • October 2026Barber Lake rent commencement — Tests conversion of the second lease into contracted NOI.
  • First half 2027Stingray delivery — Tests full first wave of the contracted portfolio; financing complete.
  • Q3 2027Reveille energization target — Tests first uncontracted near-term site if leased; advanced lease discussions.
  • Q4 2027Ulysses energization target — Tests PJM-approved site reaching energization; advanced lease discussions.
Numbers

Financials

Annual Summary

MetricFY2024FY2025TTMYoY
Revenue$151M$224M$210M+48.1%
Gross Margin13.2%28.3%3.3%+1,508bps
EBITDA$60M−$149M−$182M-348.4%
EBITDA Margin39.7%-66.7%-87.7%10,640bps
Net Income−$45M−$822M−$898M-1739.6%
Free Cash Flow−$391M−$615M−$1.5B
Net Cash

Key Ratios (Trailing)

Valuation
  • P/E TTM
  • EV/EBITDA TTM
  • EV/Revenue TTM
  • Price/FCF TTM
Profitability
  • Gross Margin (TTM)3.3%
  • EBITDA Margin (TTM)-87.7%
  • Net Margin (TTM)-427.8%
  • ROIC-17.2%
  • SBC / Revenue33.7%
Reference

The Company

Cipher Digital develops and operates industrial-scale data centers built for power-dense computing. It has intentionally evolved from a pure-play bitcoin miner into a vertically integrated data center development and operations platform; the core product is contracted, turnkey hyperscale capacity under 10-15 year leases. That capacity sits at the physical layer of the AI compute buildout.

Cipher controls the full value chain, including land and power origination, interconnection, site development, data center design and construction, and ongoing operations, rather than outsourcing development. It reports two segments, HPC Data Centers and Bitcoin Mining, but the mining segment is now a bridge at the 207 MW Odessa site, being wound down or converted while the company builds out roughly 5.3 GW across 11 sites.

Business Segments

HPC Data Centers
Ramping in H2 2026; no HPC lease revenue through Q1 2026
Develops and operates industrial-scale data centers for hyperscaler and HPC tenants under long-term leases.
Growth driver: Contract conversion at Black Pearl, Barber Lake, Stingray.
Bitcoin Mining
207 MW Odessa site; all reported revenue through Q2 2026
Legacy mining business at Odessa being deliberately wound down; about 346 bitcoin mined in Q2 2026.
Growth driver: No additional mining capex; HPC conversion explored at Odessa.

Competitive Landscape

Cipher's own 10-K names CoreWeave, Digital Realty, Equinix, Vantage Data Centers, and Aligned Data Centers as HPC services competitors, and Hut 8, IREN, TeraWulf, Core Scientific, and Applied Digital as bitcoin-mining competitors that expanded into HPC. The company's positioning rests on scarce power and interconnection rights, in-house procurement, and delivered execution.

  • CoreWeave
    Named in Cipher's 10-K as an HPC services competitor.
  • Digital Realty
    Named in Cipher's 10-K as an HPC services competitor.
  • Named in Cipher's 10-K as a bitcoin-mining competitor that expanded into HPC.
  • IREN Limited
    Named in Cipher's 10-K as a bitcoin-mining competitor that expanded into HPC.
  • Named in Cipher's 10-K as a bitcoin-mining competitor that expanded into HPC.
Named in Cipher's 10-K.

Supply Chain

Cipher sits between utilities, grid operators, and equipment providers on one side and hyperscale tenants on the other, converting power and interconnection rights into leased data center capacity. Its named EPC partner is Quanta Services; Odessa's power supplier is Luminant/Vistra.

Supplier
Named EPC partner for Black Pearl and Barber Lake.
Supplier
Luminant ET Services Company LLC
Power supplier to Odessa under fixed-price PPA through July 2027.
Supplier
Oncor Electric Delivery Company LLC
Transmission/distribution utility dependence named in 10-K.
Supplier
Transmission/distribution utility dependence named in 10-K.
Contracted power and delivered execution
CIFR
Vertically integrated developer: land, power, interconnection, design, construction, operations.
Amazon Web Services, Inc.
300 MW gross, 15-year lease
Black Pearl tenant; first capacity delivered Aug 2026, rent commenced.
Fluidstack USA II Inc.
300 MW gross lease
Barber Lake HPC tenant; Google backstops obligations.
Undisclosed investment-grade hyperscaler
100 MW, 15-year initial term
Stingray tenant; identity not disclosed.

Analysis updated Aug 12, 2026, reviewing Q1 FY2026. Prices delayed. Built with The Buildout’s published methodology. Not investment advice. No positions held. © The Buildout 2026.

More on CIFR: Earnings recap