Equinix, Inc. earnings recap

Q3 FY2026, reported October 28, 2026 · Beat 5 of last 8 quarters

Equinix, Inc. reported Q3 FY2026 revenue of $2.57B, a beat of 0.3% against consensus, and EPS of $4.93, a beat of 20.0%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Equinix, Inc. company page →See the earnings preview →Equinix, Inc. is in the Operators layer →
What this means for the buildout

Record bookings, 12% new-deal pricing and the pull-forward of more than 13,000 Q4 cabinets point to enterprise — not just hyperscale — demand for interconnected AI infrastructure, and Equinix now expects to exceed its own full-year retail capacity plan by nearly 40%, a signal that retail colocation supply chains are moving faster than planned. The Inference Exchange with NVIDIA and tenfold liquid-cooling bookings growth suggest AI inference workloads are migrating into third-party interconnection hubs rather than remaining entirely in owned campuses. A raised outlook with unchanged $5 billion-$6 billion of capex keeps Equinix a durable buyer of power, cooling and networking equipment into 2027.

Results vs consensus
EstimateActualvs est
Revenue$2.56B$2.57B+0.3%beat
EPS$4.11$4.93+20.0%beat
What was said

Equinix reported Q3 total revenue growth of 12% year-over-year on a normalized and constant-currency basis, with MRR up 11% and adjusted EBITDA margin of 51.4%, up 180 bps. AFFO per share rose 12% normalized excluding atNorth and 18% including the atNorth transaction with CPP Investments that closed this quarter, which will be accounted for under the equity method rather than consolidated. Annualized gross bookings reached a record $533 million, up 35%, churn was 1.7%, net cabinet billing rose 5,700 and 6,900 net interconnections were added. Capex was approximately $1.6 billion with about 90% directed to capacity expansion, six new projects opened across six metros including Dubai, Frankfurt, Miami, Paris and Sydney, and the 193 stabilized assets were 83% utilized at a 27% cash-on-cash return. Neocloud customers were described as representing less than 2% of MRR, and liquid cooling bookings were up more than tenfold year-over-year.

Key metrics
Annualized gross bookings
$533M
Up 35% YoY, a record; total sales activity including presales grew 38%, the third straight quarter above 30%
Monthly recurring revenue growth
11%
Normalized and constant currency; fourth consecutive quarter of double-digit MRR growth
New deal pricing
+12% YoY
Management expects pricing strength to be durable as in-place contracts renew and are marked to market
Adjusted EBITDA margin
51.4%
Up 180 bps YoY on revenue strength, cost discipline and operating leverage; FY guidance raised to ~51%
Q4 cabinet deliveries
13,000+
Highest delivery quarter on record; full-year retail capacity plan now expected to be exceeded by nearly 40%, with more than 20% of Q4 capacity presold
Management outlook

Management once again raised full-year 2026 guidance: total revenue up $100 million to roughly 12% growth, MRR growth of 10%-11%, adjusted EBITDA up $70 million to a margin of approximately 51%, AFFO up $90 million including a $31 million atNorth contribution, and AFFO per share up $0.92 to 11%-12% growth. For Q4 they guided to MRR growth of 10%-11% and total revenue growth of 12%-13%, with the EBITDA margin stepping down sequentially on seasonal spend while still up about 140 bps year-over-year. Capacity is being pulled forward — the company now expects to exceed its full-year retail capacity plan by nearly 40%, with more than 13,000 cabinets delivering in Q4 (over 20% presold) and 15% of retail capacity coming online in 2027 already sold. They point to 3 gigawatts of developable capacity, roughly 80% in top 25 metros with land, power and permitting largely secured, plus atNorth's 800 megawatts over five years and another 1 gigawatt of future expansion, while keeping 2026 capex at $5 billion-$6 billion excluding real estate acquisitions and xScale. On pricing, CEO Adaire Fox-Martin said Equinix is at the "very early stage of durable pricing strength," with new-deal pricing up 12% and mark-to-market renewals still ahead of it. The balance sheet — 4.1x net leverage, $9.1 billion of liquidity, a 3.2% blended in-place borrowing rate — is framed as the enabler to double the portfolio with only a modest leverage increase while holding investment-grade ratings, and management reiterated confidence in its long-term outlook, noting the plan already assumed higher rates.

From the call

“So we believe that we're at the very early stage of durable pricing strength going forward.”

on Pricing power

“We expect more than 13,000 cabinets in Q4, our highest quarter of delivery on record and more than 20% of that Q4 capacity has been presold.”

on Capacity delivery

“Supported by the robust demand environment and strong execution, we are raising our 2026 guidance. It reflects our recent outperformance and improved outlook for the remainder of the year.”

on Guidance raise

What analysts asked

Can you give more color on the pricing opportunity, including the potential shift of cross-connect pricing toward a consumption-based model, and what stabilized recurring revenue growth could ultimately look like given the pricing levers?

Adaire Fox-Martin said pricing starts with delivered value, but the market is exceptionally strong for colocation because industry capex is focused elsewhere, leaving insufficient capacity — which she believes puts Equinix at the early stage of durable pricing strength. New deals are the leading indicator at 12% growth YoY, providing a lens to mark the large installed base to market, and shorter contract durations than wholesale let Equinix reprice sooner; density and interconnection are incremental levers. Interconnection, 19% of revenue, is being re-examined for packaging and pricing through new products (Fabric One, Inference Exchange), with stabilized interconnection growing 10% versus 7% for stabilized colocation as an indicator. Olivier Leonetti declined to detail how the mid-20% cash-on-cash yield changes, saying the team is focused on maximizing asset value and will update when numbers need to change.

What is driving down quarterly MRR churn, and what churn assumption underpins the long-term 10%-13% revenue growth guide? Also, what makes up the 25,000 transactions cited this quarter versus historical deal counts?

Fox-Martin attributed 1.7% churn to renewal execution — engaging customers early on available-to-renew, negotiated pricing and upsell — plus a constrained-capacity market where customers have fewer alternatives. She said Equinix continues to assume 2%-2.5% churn for the remainder of the year and will refresh that with the February guide, while flagging possible intentional selective churn of low-density, low-interconnection customers in favor of higher-value ones as part of mark-to-market renewals. The 25,000 transactions are primarily portal-based, self-served extensions such as additional cross-connects, which extend go-to-market reach and manage cost of sale.

What explains the Q4 EBITDA margin guide of 49%-50% versus 51.4% this quarter, and how material are neoclouds to revenue and bookings — and is Equinix changing its approach given their perceived riskier credit profile?

Fox-Martin said neoclouds are an evolving part of the ecosystem, shifting from training work for large SaaS and hyperscaler clients toward inference and a broader enterprise base, and Equinix partners via curated network nodes (31 added, now 150), inference nodes in dense metros, Fabric connectivity and some sovereignty deployments. She noted over 100 providers and differing business models, said Equinix applies strict credit protections, and that the cohort in total represents less than 2% of MRR. Leonetti said the Q4 margin decline is traditional seasonality of spend, with year-over-year Q4 EBITDA margin still up 140 bps.

Potential supply chain impact
NVDANVIDIA provides compute for the newly launched Equinix Inference Exchange and the liquid-cooled innovation centers; tenfold liquid-cooling bookings growth could support incremental NVIDIA-based deployments inside Equinix sites.
CSCOEquinix's documented AI collaboration with Cisco and NVIDIA on enterprise AI blueprints may see incremental pull from the Inference Exchange launch and the Fabric One beta, though neither was specifically referenced on this call.
OKLOPower availability and utility structures — including the Central Georgia EMC substation funding agreement — were central to the capacity discussion; Equinix's non-binding LOI with Oklo could become more relevant if grid constraints persist.
DLREquinix's characterization of an early-stage durable pricing environment in a capacity-constrained colocation market, with new-deal pricing up 12%, could be a read-across signal for peer data center pricing.
APLDEquinix frames neoclouds largely as partners (under 2% of MRR) while competing with AI-focused data center operators; its 150 curated network nodes may influence how such providers reach enterprise customers.
IRENAs a colocation and AI cloud provider, IREN may be affected by incumbents' pricing discipline and by Equinix's stated willingness to selectively churn low-density customers in favor of higher-density, interconnection-rich workloads.