Exelon Corporation earnings recap
Q3 FY2026, reported October 30, 2026 · Beat 6 of last 7 quarters
Exelon Corporation reported Q3 FY2026 revenue of $7.32B, a beat of 8.3% against consensus, and EPS of $0.87, a beat of 10.4%.
The Buildout is a website built by one person using AI agents, and could have factual errors.
Exelon's quarter is a demand-side read on the buildout: a 23-gigawatt large-load cluster study, of which 11 gigawatts is high-probability and only about 10% energizes by 2028, suggests that interconnection and study timelines — not just capital availability — may gate data-center-driven load growth in PJM. With PJM's reliability backstop still working through FERC and an approximately 11.5 gigawatt capacity shortfall projected by 2030, Exelon is routing incremental spend into transmission ($12B–$17B) and regulated storage ($3B–$7B) that can be permitted and recovered at the state level, which could pull through grid, transformer and battery supply chains ahead of any regional market reform.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $6.76B | $7.32B | +8.3% | beat |
| EPS | $0.79 | $0.87 | +10.4% | beat |
Exelon reported third-quarter 2026 adjusted operating earnings of $0.87 per share versus $0.86 a year earlier, driven by $0.06 from approved distribution and transmission rates net of depreciation, $0.01 of AFUDC, $0.01 of weather and $0.03 of lower costs, offset by $0.07 related to storm activity and $0.04 of interest and tax expense. Year to date the utilities responded to approximately 31 significant weather events, including 57 confirmed tornadoes and two derechos, and grid investment helped prevent an estimated 6.6 million customer outages, with 94% of customers restored in under 48 hours; the four operating companies ranked first, second, fifth and sixth for electric reliability among U.S. utility peers. On regulation, the Maryland commission issued a final order approving a $50.9 million Pepco electric revenue requirement increase based on a 9.4% ROE and 50.5% equity ratio with new rates effective August 10, and ComEd reached a settlement with all parties in its annual reconciliation at a $205 million delivery adjustment amount, with a final order expected by December 20. The large-load cluster study declined to 23 gigawatts from 25, with 11 gigawatts classified as high-probability; management attributed the reduction to the study process working, citing projects falling out for reasons including communities and the absence of an end customer rather than any change in customer behavior. The company also completed 100% of planned 2026 debt financing and priced all $850 million of its 2026 equity needs under its ATM program, expected to settle by December 15.
Management narrowed full-year 2026 adjusted operating earnings guidance to $2.85 to $2.91 per share and said it is targeting the midpoint or better, while reaffirming annualized growth near the top end of its 5% to 7% range from 2025 through 2029. That growth is anchored on the $41.7 billion capital plan with 7.9% rate base growth and 16% transmission growth, plus two disclosed pockets of upside beyond the plan: $12 billion to $17 billion of transmission opportunity over the next decade and 1.5 to 3.5 gigawatts (roughly $3 billion to $7 billion) of regulated storage. New CFO Rob Kleczynski characterized both pipelines as incremental and said Exelon will pursue them only where customer need is clear, economics are attractive and approvals and recovery mechanisms are in place; Carim Khouzami said transmission accretes over a roughly 3-to-5-to-7-year timeline depending on project type, while the New Jersey battery could be running in just under three years. On regulation, BGE's electric distribution case is tracking to a January 2027 order, Delmarva to third quarter 2027, ComEd's grid plan order is expected by December 15 and the New Jersey BPU order on the 500-megawatt battery is expected late in the first quarter of 2027. Financing is largely de-risked for the year — 100% of 2026 debt financing is complete and roughly 30% of the $3.4 billion of planned equity through 2029 has been priced, including all $850 million of 2026 needs — with credit metrics averaging about 14% through 2029. The tone on PJM was impatient: Calvin Butler said progress on regional supply solutions "remains too slow" and that Exelon will advance practical state-level solutions where policy supports them rather than wait for a single regional fix.
“Based on our performance through the third quarter, we are narrowing our full year operating earnings to $2.85 to $2.91 per share with the goal of delivering at the midpoint or better.”
on Guidance narrowing
“We're at a point where our customers simply can't afford continued delays. So we're not waiting for a single regional solution. We're advancing practical solutions that states and utilities can pursue today, where policy supports them and customers are appropriately protected.”
on PJM delays and state-level solutions
“On the battery front, it's much shorter duration in terms of when we announced to when we actually have it up and operational. The New Jersey battery, for example, we expect that we will be able to get that once we get approval up and running in just under three years. So that will be when it starts to go into rate base and be accretive to earnings.”
on Storage timeline to rate base
You've quantified upside — $12B to $17B for transmission and the storage pipeline. At what point does that opportunity accrete to the growth rate, given you're already at the top end of the range?
Carim Khouzami said the pipelines are meant to illustrate the upside. Transmission awards are expected over the next few years and accrete to earnings once operational, with a timeline of roughly 3 to 5 to 7 years depending on project type. Battery storage is much shorter duration from announcement to operation — the New Jersey 500 MW project could be up and running in just under three years after approval, at which point it enters rate base and becomes accretive.
Given the lack of progress at PJM and the important FERC proceedings, how are you thinking about the May PJM auction — are you advocating for a price cap, a price floor, or more extensive changes to protect your customers?
Colette Honorable said PJM filed a revised reliability backstop procurement proposal the prior evening addressing three areas: cost allocation so large-load costs follow large load, a reduction in the collateral requirement from 50% to 40%, and exit fees applying to load-serving entities rather than transmission owners. She said PJM projects roughly an 11.5 gigawatt shortfall by 2030, credited FERC with helping refine collective focus on getting infrastructure online, urged more urgency and more state empowerment on resource adequacy, and said Exelon continues to support use of the cap in the short and medium term until better processes bring costs down.
Is any of the 11 gigawatts of high-probability load reflected in the current plan, and what energization schedule underpins that?
Calvin Butler said a small amount is reflected in the current plan today, with more added once load is known to be high-probability and secured. Jeanne Jones said about 10% comes online by 2028 and roughly three-quarters of the 11 gigawatts will be online by 2034, which is why only a portion of capex is captured near-term; she added that only about $1 billion of the $12 billion to $17 billion transmission opportunity is ascribed to high-density load growth, which she characterized as conservative.