IREN Limited earnings recap

Q1 FY2027, reported November 5, 2026 · Beat 3 of last 7 quarters

IREN Limited reported Q1 FY2027 revenue of $228M, a miss of 0.1% against consensus, and EPS of $-0.62, a beat of 14.4%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full IREN Limited company page →See the earnings preview →IREN Limited is in the Operators layer →
What this means for the buildout

IREN's quarter is a live test of whether contracted AI capacity can be converted into revenue on schedule: AI Cloud revenue nearly tripled and adjusted EBITDA margin doubled, but the more than $4 billion ARR ramp slipped on a customer-requested network redesign and supplier timing — a reminder that the last mile of commissioning, not demand, is the gating item. The cut to planned CapEx and the explicit pacing of deployments against capital-market conditions suggests the buildout is entering a phase where financing availability, not customer appetite, sets the cadence for at least some developers. Pricing evidence — $22 million per megawatt on five-year terms with ~90% customer prepayment of GPU CapEx, above $40 million on short duration, and H100s re-contracted at double — indicates compute scarcity is still intensifying even as capital markets tighten.

Results vs consensus
EstimateActualvs est
Revenue$228M$228M-0.1%miss
EPS-$0.72-$0.62+14.4%beat
What was said

IREN reported AI Cloud revenue of $200 million, up about 182% quarter-over-quarter, and total revenue of $228 million, up 66%, while Bitcoin mining revenue fell to $28 million as mining hardware is decommissioned ahead of GPU installs. Adjusted EBITDA was $66 million at roughly a 29% margin, up from 14%, and operating ARR reached $1 billion, with gross margin before D&A of 80% overall and 86% in AI Cloud. Operating capacity rose 127% to 0.1 gigawatts, Horizon 1 was handed over to Microsoft with NVIDIA Exemplar Cloud status roughly 14 months from civils, and Horizons 2 through 4 were described as built or nearing completion, with the ramp of the 0.3 gigawatts now targeting January. The quarter carried a $263 million net loss, including $224 million of operating expense with $63 million of stock-based compensation, and total assets of $20.6 billion including $6 billion of unencumbered data center assets and $5.8 billion of cash, with $10.2 billion of largely low-coupon convertible debt maturing in 2032 and beyond.

Key metrics
AI Cloud revenue
$200M
Up ~182% QoQ, nearly tripling; total revenue rose 66% QoQ to $228M as Bitcoin mining revenue fell to $28M
Operating ARR
$1.0B
Doubled QoQ; the more than $4B contracted and fully funded target has moved from year-end to January, with risk of slipping to end-February
Revenue backlog
>$20B
Multiyear contracts including a leading frontier AI lab; two-thirds with investment-grade counterparties (Microsoft, NVIDIA)
Adjusted EBITDA
$66M
~29% margin versus 14% in the prior quarter; AI Cloud gross margin before D&A held at 86%
Planned CapEx, remainder of FY27
~$15B
Down from the prior estimate after ~$5B spent in the quarter; ~$6B still to be funded against $12B–$15B of identified sources
Management outlook

Management declined to give a specific ARR target beyond the more than $4 billion already contracted, saying the level and timing will depend on contracts signed and when capacity is accepted; the ramp is now targeted for January, with a credible path to end-February if suppliers are late. For the December quarter, Anthony Lewis said IREN expects to recognize roughly one quarter of the $1.0 billion operating ARR as revenue, with no material contribution from incremental Horizon or Mackenzie capacity (most arriving late December or early calendar 2027), and cash operating expense rising $50 million to $60 million sequentially. Planned CapEx for the rest of the fiscal year was cut to approximately $15 billion, with $6 billion left to fund against $12 billion to $15 billion of identified data center, GPU and prepayment sources, and the Childress air-cooled deployments now spread across calendar 2027 rather than front-loaded. Dan Roberts framed the slower pace as deliberate — flexing construction to financial market conditions rather than a demand problem — while pointing to 0.8 gigawatts targeted by end-2027, $10 billion of data center assets and $25 billion of combined data center and GPU assets by June. The demand read was emphatic: contracts signed since quarter-end at $22 million per megawatt on a five-year term with ~90% customer prepayment of GPU CapEx, a short-duration deal above $40 million per megawatt, and older H100s re-contracted at double the original price, with management targeting total GPU financing including prepayments of about 90% of GPU CapEx.

From the call

“If suppliers deliver, we're targeting January. If they're late, as suppliers have been across the industry this year, it may run to the end of February.”

on ARR ramp timing

“Capital markets have become more selective in the last few weeks. And the questions have undoubtedly moved from how big the contract is to whether it can be delivered, financed and run at a profit.”

on Financing environment

“We haven't mentioned on this call, but the supply of VRs next year is exceptionally scarce, and we're seeing a lot of interest, and that's something that's really exciting to us in terms of the prospective economics on it.”

on Vera Rubin supply

What analysts asked

Can you give additional color on the Microsoft capacity delivery dynamics — how much of the supplier delay relates to the change orders versus being unrelated, and any clarity on what the market has been hearing?

Roberts said Horizon 1 was handed to Microsoft in August, after which the customer requested a reconfiguration and upgrade of network infrastructure to enable the 200 megawatts to serve the latest frontier models — a request IREN accepted. He described the resulting delay as small, targeting January with a chance it moves to end-February depending on supplier performance, and noted Horizon 2 is built with power on at the rack across all three halls, GPUs racked, fiber in and Dell commissioning now, Horizon 3 fully energized and Horizon 4 GPUs arriving in coming weeks. The incremental CapEx for the network upgrade is immaterial against the broader cluster, and the learnings are being compounded into other sites under construction.

CapEx for fiscal '27 has come down from the prior quarter and the quarter before that — what's driving the flexibility, and why is it ticking down for this year?

Roberts said the reduction is deliberate: the demand, customers and sites are there, but capital needs to be respected in the current environment and IREN will not grow at all costs — it will throttle the growth curve based on availability and cost of funding. He contrasted the model with 20-year colocation liabilities and very large GPU commitments, arguing the cash-funded land, power and data centers let IREN ride financial market volatility and be poised to flex up when markets recorrect, noting the business-level demand signals were from deals signed that week.

Can you talk about the cost of purchasing new GPUs and how that's trending, whether GPUs are available as long as you can bring data center infrastructure online, and whether the cost to purchase will catch up to where you're leasing them today?

Kent Draper cited continued industry supply constraints, notably SSDs and RAM and other components, and said IREN would expect GPU pricing to keep increasing on the back of end-customer demand, with customer price increases flowing through immediately to hourly contract pricing so payback periods hold or even shrink. Roberts added that IREN deliberately has not acquired 100% of next year's GPUs because it sees right-way risk: if markets stay weak and construction remains challenging, GPU prices could fall, and if markets recover the company can afford a slight premium or a two-to-three-month wait, since time-to-power is the binding constraint.

Potential supply chain impact
DELLIREN said Dell is commissioning at Horizon 2 and flagged supplier timing as the swing factor between a January and end-February ARR ramp, which could make Dell delivery schedules a read-through on frontier-lab cluster handovers.
CRWVIREN repeatedly contrasted its owned land, power and data center model with asset-light neoclouds carrying lease liabilities; tightening capital markets could sharpen that differentiation, though it may not reflect on peers' contracted backlog.
DLRIREN's pitch that it does not lease third-party colocation and keeps more of the economics may pressure the value proposition for colocation middlemen on frontier AI leases, though hyperscale colocation demand is driven by a separate customer set.
AMZNIREN's disclosed recent pricing of $22 million per megawatt on five-year terms and above $40 million on short duration could serve as a reference point for competing AI cloud capacity, potentially signaling where hyperscaler-adjacent pricing is trending.
CLSKIREN is decommissioning Bitcoin mining hardware with the transition substantially complete by the end of this quarter, which could modestly shift relative hash share among miners, though IREN's mining revenue already fell to $28 million.