Nebius Group N.V. earnings recap
Q3 FY2026, reported November 12, 2026 · Beat 6 of last 7 quarters
Nebius Group N.V. reported Q3 FY2026 revenue of $981M, a beat of 8.1% against consensus, and EPS of $0.30, a beat of 141.5%.
The Buildout is a website built by one person using AI agents, and could have factual errors.
Nebius is providing one of the clearest data points yet that customer prepayments can fund AI data center construction: coverage moved above 100% of CapEx on Q3 wins, and management expects 75%-85% of a $40B-$45B 2027 CapEx program to be covered by prepayments and asset-backed financing. At the same time, the New Jersey delay and the shift of revenue into next year underscore that power delivery and third-party construction — not demand — remain the binding constraint on the buildout. The intended shift of most new capacity onto company-owned sites could be a read on how neoclouds are internalizing more of the power and shell supply chain to control timing.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $907M | $981M | +8.1% | beat |
| EPS | -$0.72 | $0.30 | +141.5% | beat |
Group revenue was $980.8M, up 571% year-over-year, with Nebius AI cloud revenue of $973.8M (up 643%) representing about 99% of the total; the quarter included approximately $325M of nonrecurring revenue from an initial asset-light partnership transaction. Group adjusted EBITDA was $465.8M at a 47.5% margin versus $236.2M and 40.6% in Q2, while the AI cloud segment margin rose to 53.2%. Prepayments became the standard structure, with more than 90% of Q3 contract value carrying a prepayment and the weighted average prepayment share of contract value up roughly 20 percentage points sequentially. Customers committed more than $12B of contract value since the start of Q3, including multibillion-dollar five-year agreements and first-time multiyear deals with Databricks, Datadog and Snowflake, plus a multiyear agreement with Palantir, though reported RPO rose only 3% because several agreements signed after quarter-end. Management disclosed that some colocation sites, including New Jersey, are behind schedule, with part of that capacity shifting into 2027, while company-owned sites remain on or ahead of plan.
Nebius trimmed 2026 revenue guidance to $3.0B-$3.2B from $3.0B-$3.4B, attributing the change entirely to timing as some third-party colocation capacity shifts into Q2 2027, while keeping the ~40% adjusted EBITDA margin target unchanged. CapEx guidance for 2026 was raised to roughly $27B from $20B-$25B, with contracted power still expected to reach 5GW by year-end, up from more than 4GW today. For 2027, management introduced revenue of $12B-$13B, or roughly 4x, alongside CapEx of $40B-$45B sized for more than 1GW of new capacity, a majority of which will come from company-owned sites with a stronger margin profile than colocation. Management expects 75%-85% of that 2027 CapEx to be funded by prepayments and asset-backed financing against investment-grade contracts, with customer prepayments of $17B-$20B in 2027 (a figure it explicitly called not a ceiling), and it expects to reach pretax breakeven in Q4 2027 on 5-year depreciation of servers and networking equipment. The company also said it will stop guiding to annualized run-rate revenue after February, when it expects ARR to exceed $7B, shifting the narrative to revenue and pretax earnings. The tone was confident and explicitly conservative on build-out timing, with management saying demand risk is not the constraint — delivery of power and capacity is.
“Three months ago, we reported our first $1 billion-plus contracts. In Q4, we're already signing multibillion-dollar agreements for our AI cloud.”
on Contract size momentum
“The most important change is that the prepayments on new contracts now cover more than 100% of the capital needed to bring this contracted capacity online. Just to remind you, last quarter, it was 50% to 60%.”
on Prepayment coverage
“For example, some of our colocation sites, including New Jersey, are behind schedule. Customers have been kept informed and none of that capacity is canceled. Some of it has shifted to 2027.”
on Capacity delays
Customers committed more than $12 billion of TCV since the start of Q3, but RPO only increased 3%. How much of that TCV remains unrecognized in RPO, and what are the primary factors limiting reported backlog growth?
Management said it had been running pricing programs to learn the right terms before releasing capacity, then raised prices in early September and added higher prepaid terms and longer durations. The result was more than $12B of commitments since the start of Q3, including multibillion-dollar five-year agreements and expansions by existing landmark customers at higher rates and more paid upfront; several agreements signed after quarter-end will appear in next quarter's reported commitments, and momentum has continued into Q4.
Can you provide more color on the underlying causes of the delivery delays at Vineland, and what other sites are impacted, as the shareholder letter cited several delays across your colocation sites?
Management attributed the Vineland delay to power: after pivoting to Bloom generation in summer, the temporary generation provider decided to wind down faster than expected, creating a gap while Bloom ramps. Bloom electrons are already on site and the company is expediting the ramp; it said it continued delivering tranches to Microsoft through Q3 and will keep doing so in November and December. Management noted delays are more likely at third-party-built colocation sites and said it plans to use more Bloom generation at other sites.
You plan to add more than 1 gigawatt of computing capacity annually while taking a cautious view on commissioning timing. What are the main constraints between contracted power and customer-ready compute, what milestones should investors track, and are you changing how you think about timing?
Management said power and power interconnection are the main industry constraint, and that the key 2027 change is that most capacity will come from company-owned sites — Alabama, Missouri, two projects in Finland and Pennsylvania — giving full control over pace versus colocation. On supply chain, it said GPU, CPU, networking and storage supply is confirmed for 2027 with R&D, integration and benchmarks already complete for Vera CPUs, Vera Rubin GPUs and Groq, and it does not expect component availability to be a bottleneck.