NuScale Power Corporation earnings recap

Q3 FY2026, reported November 5, 2026 · Beat 3 of last 7 quarters

NuScale Power Corporation reported Q3 FY2026 EPS of $-0.11, a beat of 9.8% against consensus.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full NuScale Power Corporation company page →See the earnings preview →NuScale Power Corporation is in the Power Generation layer →
What this means for the buildout

NuScale remains effectively pre-revenue with no signed module order, so this quarter does not yet register in AI data center power procurement; management explicitly said it is not reliant on data centers and is marketing process heat, district heat and utility offtake alongside hyperscalers. The signal is instead on the supply side: funding first article metal with Doosan, completing fuel design at Framatome and locking safety I&C at Paragon moves an NRC-approved light-water design closer to a buildable, repeatable product. If a TVA-linked PPA materializes, the long-lead work already in progress could shorten the interval between contract and hardware — the constraint that has kept SMRs out of near-term data center capacity plans.

Results vs consensus
EstimateActualvs est
Revenue$3.7M$281K—Not comparable
EPS-$0.12-$0.11+9.8%beat

Revenue: The gap is too large to be a like-for-like comparison (the estimate and the result may be on different bases), so we do not call it a beat or a miss.

These figures come from the same table as our earnings calendar. The write-up below may quote the company's own adjusted or reported figures, which can differ.

What was said

NuScale reported $0.3 million of revenue for the quarter ended September 30, 2026, versus $8.2 million a year earlier, which the CFO attributed to the absence of RoPower front-end engineering and design Phase 2 work that had completed in late 2025. Operating expenses were $65 million versus $549 million in the prior-year period, and liquidity stood at approximately $1.9 billion versus roughly $916 million a year ago. The company signed an agreement with long-time partner Doosan Enerbility to manufacture first article production of the NuScale power module, and said first article spend will accrue as work-in-progress inventory on the balance sheet before flowing through cost of goods sold on an OEM sale. Supply chain items cited included Framatome completing fuel design ahead of customer commitments, Paragon's award for safety instrumentation and control development with NuScale jointly owning the IP, and a first-of-a-kind fabrication milestone with MillenniTEK on the passive emergency core cooling system; NuScale also said it deployed nuclear-specific AI tools across engineering and knowledge management. A new E2 center was signed, taking the network to 13 worldwide, and management said it continues dialogue with RoPower and Nuclearelectrica following the change of government in Romania.

Key metrics
Revenue
$0.3M
Down from $8.2M in Q3 last year; prior period included front-end engineering and design Phase 2 work in support of the RoPower project with no comparable scope this quarter
Liquidity
~$1.9B
Cash, cash equivalents and investments, versus ~$916M at the end of Q3 last year; management calls it adequate to fund first article fabrication, engineering and licensing
Operating expenses
$65M
Versus $549M in the same period last year; CFO said OpEx should remain 'fairly constant' near current levels until a project is engaged
Qualified supplier base
60+
Specialized suppliers covering every major module scope; management says it is driving dual or tertiary sourcing on the majority of packages so no single supplier becomes a constraint
Legacy COLA work reusable
50%–60%
Portion of the carbon-free power project's construction and operating license application work management estimates is transferable to another customer, which should compress schedule and cost
Management outlook

Management gave no revenue or margin guidance and no timeline for a Tennessee Valley Authority power purchase agreement, framing the quarter instead as a shift 'from development to physical production.' The Doosan Enerbility first article agreement commits NuScale to fund initial module component fabrication, with component costs expected to be recovered through the owner's contractual payment schedule under a future OEM agreement. CFO Ramsey Hamady said OpEx should remain 'fairly constant' near the current ~$65M quarterly level, with growth arriving only once a project such as TVA is engaged, and that spending would then be split between OpEx and cost of goods sold. He added that once an OEM agreement is in hand the company will have 'further clarity on margins' and expects to be able to give guidance 'soon,' with the objective of helping the Street assess profitability. Management said it has no other significant publicly communicated investments beyond Doosan, that ~$1.9B of liquidity is built for the long term, and that Romania remains in a holding pattern pending direction from the new government while talks continue with utilities, hyperscalers and industrial offtakers.

From the call

“We are no longer simply designing and planning, we are manufacturing.”

on First article production with Doosan

“while our expectation is the PPA is the next step, which eventually leads to the sale of modules, the PPA in itself -- I don't know that I have to clarify this, the PPA in itself is not the sale of modules.”

on PPA versus module order sequencing

“We know there's a bipartisan push on [ NIMBY ] and everything else, but we're not reliant on data centers.”

on Demand mix beyond hyperscalers

What analysts asked

Given the procurement of long lead items implies confidence in a conclusion, can you give a timeline for a potential commercial agreement on TVA and the other opportunities you alluded to?

John Hopkins said the process continues and management is 'optimally optimistic,' but the company is focused on what it can control: building execution capacity, moving into first article to take the design into physical hardware, and surfacing issues before series production. He reiterated NuScale is 'ready to move' but gave no date, noting it has been a lengthy process.

Once the PPA is signed, what are the remaining steps to securing a binding module order, and does the PPA itself trigger a module order?

Hopkins said yes in the sense that NuScale is pre-positioning so it can move quickly into COLA and long lead items once the PPA is initiated. Ramsey Hamady clarified sequencing: the PPA is between ENTRA1 and TVA and is not itself the sale of modules; pre-engineering, predelivery services and COLA work are expected to follow, with the module sale coming under an OEM agreement between NuScale and ENTRA1.

With OpEx expected to remain flat, does the reaccelerating activity with Doosan run through another line, and what other controllable milestones should investors watch ahead of ENTRA1 and TVA?

Hamady said NuScale held OpEx within a plus-or-minus 5% band for eight straight quarters, and that current costs reflect a deliberate choice to retain engineering talent as RoPower work wound down. Doosan spend will accrue on the balance sheet as work-in-progress inventory and only expense through cost of goods sold once modules are sold under an OEM contract, which he described as controlled and deliberate against the $1.9 billion cash position.

Potential supply chain impact
CWNuScale's documented supplier list includes Curtiss-Wright, and management said it is driving dual or tertiary sourcing across most packages while funding first article fabrication — incremental component demand could follow if series production begins, though NuScale explicitly avoids single-supplier dependence.
FLRThe year-over-year revenue decline to $0.3M was attributed to completion of Fluor's RoPower FEED Phase 2 scope in late 2025, so Fluor-linked engineering revenue may stay absent until new project work is authorized; NuScale also said NuScale would support a separately contracted EPC once one is selected.
FLRFluor serves as a primary contractor in the documented relationship set; management described an EPC-led delivery structure where NuScale supports design under a separate contract, so EPC selection timing may influence when NuScale services revenue resumes.
HONHoneywell is listed as a control systems supplier; NuScale's comments that many critical components will already be designed, scaled and tested when an OEM agreement is executed could imply modest pull-through for instrumentation vendors, contingent on a module order.
MIRMirion appears among NuScale's documented suppliers; radiation monitoring scope would likely be tied to actual plant construction rather than first article fabrication, so timing may lag any module order.