Centuri Holdings, Inc. earnings recap

Q3 FY2026, reported November 5, 2026 · Beat 4 of last 7 quarters

Centuri Holdings, Inc. reported Q3 FY2026 revenue of $1.19B, a beat of 14.7% against consensus, and EPS of $0.42, a beat of 85.9%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Centuri Holdings, Inc. company page →See the earnings preview →Centuri Holdings, Inc. is in the Construction layer →
What this means for the buildout

Centuri's results read through to the utility-side of the AI infrastructure buildout rather than to data centers directly: the $19 billion pipeline is roughly $12 billion electric (about $10 billion distribution and transmission) and $7 billion gas, and the company said $4.8 billion of bids, including $2 billion of MSA renewals, reflect updated pricing for fuel and fleet cost escalation. Data center work remains deliberately capped — roughly $370 million booked in aggregate with about $200 million of backlog expected to burn off next year — so the buildout signal here is grid hardening, reliability and transmission capacity for investor-owned utilities rather than hyperscale construction. The 1.3x-plus book-to-bill and mid-teens 2027 revenue growth outlook suggest utility capex programs are converting into contracted service work with improving margin.

Results vs consensus
EstimateActualvs est
Revenue$1.04B$1.19B+14.7%beat
EPS$0.23$0.42+85.9%beat
What was said

Centuri reported record quarterly revenue of $1.2 billion, up 40% year over year, and record gross profit of $113 million at a 9.5% margin, as workforce investments made in the first half translated into higher productivity. U.S. Gas gross margin improved to 8.2% from 4.2% in the second quarter, Canada posted a 19.6% gross margin on $98 million of revenue, Union Electric revenue rose 65% to $354 million with the JJ White acquisition, and non-union electric revenue grew 18% to $175 million at an 8.7% margin. Third quarter bookings were approximately $730 million, bringing year-to-date bookings to roughly $2.9 billion, and the company booked about $275 million in early Q4 split evenly between bid work and MSAs. Backlog stood at approximately $6.2 billion with an opportunity pipeline of approximately $19 billion, and the company said its 2026 book-to-bill ratio would be at least 1.3x versus its earlier 1.2x target. Free cash flow was negative $30 million in the quarter on working capital, and net debt to adjusted EBITDA was 2.6x versus 3.8x a year ago.

Key metrics
Revenue
$1.19B
Record quarterly revenue, up 40% year over year on a $342 million increase
Gross Profit / Margin
$113M / 9.5%
Record quarterly gross profit; margin up from 7.2% in Q2 and 10.4% incremental gross margin year over year
Adjusted Net Income
$42M ($0.42/sh)
More than double the $17M ($0.19/sh) reported a year ago; adjusted EBITDA $108M, +44%
Outstanding Bids
$4.8B
More than doubled from $2.5B at the end of Q2; includes ~$2B of MSA renewals expected to close by year end
Opportunity Pipeline
$19B
Up 46% year over year; backlog $6.2B, up 5% year over year, with over $3.7B of 2027 revenue coverage
Management outlook

Full-year 2026 guidance was updated to revenue of $3.8B-$3.9B, adjusted gross profit of $305M-$315M, adjusted EBITDA of $290M-$300M, adjusted net income of $80M-$90M and net capex of $60M-$70M, with the fourth quarter assuming no storm work contribution. For 2027, management guided to mid-teens revenue growth that puts revenue above $4.4B, accompanied by an overall gross profit margin target of 8.5%-9% and incremental gross profit margins of 12%-15%. Christian Brown said the company is tracking toward roughly $4B of backlog coverage for next year and expects 2029 targets to be refreshed alongside next year's full guidance, adding he expects those 2029 targets to be higher, not lower. Full-year free cash flow guidance was lowered to $25M-$50M from the prior estimate on higher working capital from revenue growth consistently exceeding forecast, which the CFO characterized as a timing issue that translates into higher 2027 cash flow. Leverage is expected in the low 2x range by year end, down from 2.6x this quarter, with the CFO targeting below 2x over time and prioritizing delevering and organic growth over buybacks or dividends. Management framed fourth quarter conservatism around uncertainty over customer budget exhaustion and surplus budget allocation, and noted early-October storm work would be additive to the guide.

From the call

“By this time next year, we expect the vast majority of our backlog to reflect the updated market pricing.”

on Pricing and margin expansion

“Looking ahead, we now have over $3.7 billion of revenue coverage for 2027, which combined with our pipeline gives us visibility to mid teens percentage revenue growth for 2027.”

on 2027 visibility

“Though we have booked approximately $370 million of data center work in aggregate. With approximately $200 million remaining in backlog. Whilst meaningful, we continue to believe that data center work will not exceed 10% of our overall annual revenue.”

on Data center exposure

What analysts asked

The quarter's incremental margin was 10.4% — can you break that out excluding diesel fuel cost pass-throughs, and how should we think about 2027?

Kelly Youngblood said the net fuel impact came in at almost exactly the ~$5 million guided on the prior call, that Centuri has been successful pushing fuel and fleet leasing cost into customer pricing, and that another $2 billion of contracts being renegotiated before year end will incorporate those higher costs. He said the company will stop quantifying the absolute dollar value of fuel, and that implied 2027 guidance puts incremental margins within the 12%-15% range. Christian Brown added that backlog coverage is trending toward $4 billion by year end, supporting the $4.4B-$4.5B revenue commentary.

Implied fourth quarter EBITDA guidance suggests a lower margin than previously, even though Q3 beat plan — what are the moving pieces?

Youngblood said Q3 beat consensus and internal budget while Q4 looks light versus consensus, but the full second half beat across revenue, gross profit and EBITDA dollars versus both consensus and internal budget. He attributed the EBITDA margin shortfall largely to the shift toward more fleet leasing rather than capex, which removes the depreciation benefit and represents about a 90 basis point impact to full-year 2026 EBITDA margins versus 2025. He noted 2027 guidance takes revenue above $4.4 billion, ahead of the 2029 expectations laid out earlier in the year.

Can the next phase of growth avoid another labor ramp headwind — how fast can you grow without reaccelerating headcount?

Christian Brown said adding another 1,800 people in a half year is unlikely, noting roughly 300 were added in the last quarter versus 1,800 in the first half of the year. He said growth should become more linear across the 12 months as the business reduces seasonality, and that future mobilization will be more normalized given the tools now in place across the group and the size and scale of the organization.

Potential supply chain impact
AEPCenturi's $12 billion electric pipeline, of which about $10 billion is distribution and transmission, and its pricing-refreshed MSA renewals could reflect continued multiyear T&D capex visibility at large investor-owned electric utilities such as AEP.
ENBU.S. Gas revenue rose 40% to $576 million with gas margins at 8.2%, and $7 billion of the $19 billion pipeline sits on the gas side — a potential signal of sustained distribution replacement and integrity spending by gas utility customers including Enbridge.
ETRManagement said most data center opportunities in the pipeline are in the Atlantic and Midwest areas of the U.S., with only one in Texas; utility customers with southern and Gulf footprints such as Entergy may see less of that specific bidding activity.
EXCWith data center bids concentrated in the Atlantic and Midwest, Centuri's cautious, funded-and-permitted-only approach could mean a slower cadence of awarded work for utility customers in those regions such as Exelon.
NICenturi cited roughly 45% of gas distribution mains and service lines being over 35 years old or of unknown origin, and expects to be profitable in gas in Q1 2027 — a possible read on accelerating replacement programs at gas distribution customers like NiSource.
PWRCenturi's outstanding bids more than doubled to $4.8 billion and 2026 book-to-bill is now tracking at least 1.3x, which may indicate intensifying competition for utility T&D and bid work among large infrastructure services providers such as Quanta.
MTZCenturi is deliberately growing bid work (22% to a targeted ~35% mix) to drive margin, a shift that could increase competitive overlap with MasTec on larger electric transmission and industrial projects.
MYRGSeveral electric transmission awards in the $10-$20 million project size range were booked this quarter; that project-size band may be an area of direct competitive overlap with MYR Group.
PRIMUnion Electric revenue rose 65% to $354 million including JJ White, and management flagged cross-selling opportunities — potentially a competitive signal for Primoris in union and industrial electrical work.
ECGCenturi said customers are focused on affordability and that scale enables cross-selling across gas, electric, union and non-union — a dynamic that could pressure smaller or less-integrated competitors such as Everus on multi-scope utility awards.