Comfort Systems USA, Inc. earnings recap

Q3 FY2026, reported October 22, 2026 · Beat 7 of last 7 quarters

Comfort Systems USA, Inc. reported Q3 FY2026 revenue of $3.77B, a beat of 10.7% against consensus, and EPS of $13.91, a beat of 8.2%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Comfort Systems USA, Inc. company page →See the earnings preview →Comfort Systems USA, Inc. is in the Construction layer →
What this means for the buildout

Comfort Systems is a direct read on physical data center delivery: technology was 59% of revenue, backlog reached a record $17.8 billion with a duration now stretching 18 to 24 months, and modular capacity is being expanded toward 6 million square feet — a combination that suggests hyperscale and colocation construction schedules remain funded and accelerating rather than digesting. Management's comment that customers are committing earlier and for larger scopes because capacity like theirs is scarce points to continued tightness in mechanical and electrical labor, which supports trade-contractor pricing. The reluctance to extend programmatic modular commitments to new frontier lab and colo buyers over payment terms is a reminder that counterparty credit, not demand, may be the binding constraint on the buildout.

Results vs consensus
EstimateActualvs est
Revenue$3.40B$3.77B+10.7%beat
EPS$12.85$13.91+8.2%beat
What was said

Revenue rose 54% to $3.8 billion, with Electrical segment revenue up 85% and Mechanical up 43%, and gross margin held at 24.8% as Mechanical improved to 25.1% while Electrical fell to 24.3% against a prior-year quarter that included roughly 1.8 points of discrete gains. Operating income rose 65% to $625 million, or 16.6% of revenue, EBITDA rose 61% to $668 million, and SG&A fell to 8.3% of revenue from 9.4%. Backlog reached a record $17.8 billion, up $8.4 billion year over year and $3.8 billion sequentially, with third-quarter bookings especially strong in the technology sector across both traditional construction and modular. Technology was 59% of revenue versus 42% a year earlier, industrial customers were 76% of revenue, institutional 16% and commercial 8%, while modular was 17% of revenue and service revenue grew 13% at record profitability. The company closed two acquisitions on August 1 — Lewis Electrical and Neopod — expected to contribute over $100 million of annual revenue, and reported $86 million of third-quarter free cash flow after deferring $166 million of income tax payments into the fourth quarter.

Key metrics
Backlog
$17.8B
Record; up $8.4B (90%) year over year and $3.8B (27%) sequentially — eighth consecutive sequential increase
Quarterly revenue
$3.8B
Up 54% YoY; Electrical segment +85%, Mechanical segment +43%
Diluted EPS
$13.91
Up $5.66 from $8.25 in Q3 2025
Gross margin
24.8%
Mechanical rose to 25.1% from 24.3%; Electrical slipped to 24.3% from 26.2%, which included ~1.8 pts of discrete prior-year gains
Modular capacity
6M sq ft
Targeted by end of 2027, up from over 4M sq ft expected by end of 2026
Management outlook

Management said same-store revenue rose 47% through nine months and expects full-year 2026 same-store revenue growth in the mid-40% range, and for the first time on this call quantified 2027, estimating full-year 2027 same-store revenue growth in the mid-20% range, with 2027 gross margins "likely to continue in the strong ranges" achieved on average over recent quarters. Trent McKenna reiterated the modular buildout, with more than 4 million square feet of space by the end of 2026 and approximately 6 million square feet of capacity by the end of 2027, all tied to existing programmatic customers while frontier lab and colocation work remains non-programmatic pilot volume. Brian Lane said backlog duration has stretched to roughly 18 to 24 months versus about nine months a decade ago, and management expects continuing growth and strong results for the remainder of 2026 and into 2027. Full-year CapEx is expected at 4% to 5% of revenue, including over $100 million spent this quarter on prefabrication facilities, with elevated spending likely to continue in the first half of 2027. The company raised its quarterly dividend by $0.10 to $1.00 per share, bought back stock in the quarter, and Bill George described a "very, very good acquisition pipeline" while stressing patience on price.

From the call

“Bookings were strong, and our backlog at the end of the quarter grew to a new high of $17.8 billion.”

on Record backlog

“We remain on track to have over 4 million square feet of space in our modular businesses by the end of 26 and with ongoing orders and investments to meet that demand, we expect to have approximately 6 million square feet of capacity by the end of 27.”

on Modular capacity expansion

“So another way of asking it, the other side of that question is, why would we divert from a sure thing to sort of a mystery?”

on Selectivity on new modular customers

What analysts asked

Can you give more color on the sequential margin decline and how we should think about margins in the next few quarters?

Trent McKenna attributed it to a higher proportion of equipment and materials in the cost mix — equipment adds revenue but labor carries the margin, so the percentage comes down even as dollars rise. Bill George added roughly $12 million more in purchase-accounting adjustments tied to acquired WIP than in Q2, plus one large electrical company whose margins were above average but no longer in the thirties, and noted the company does not pull out high margins early in jobs; he expects a return to average margins in the first half of next year.

Is the incremental modular capacity to 6 million square feet tied to existing hyperscalers or to frontier labs and colocation providers, and can you expand on those engagements?

McKenna said the announced buildout is entirely for the existing programmatic customer base; work for a frontier lab and colo providers is real but not yet programmatic. George added that the company has not yet reached terms it is willing to accept, with ability to pay front and center, noting programmatic customers typically make five-year volume commitments that justify large CapEx, and that modular remains 17% of revenue because the rest of the business is also growing.

With political rhetoric around data center moratoriums and state-level regulation, have you seen any change in project schedules or pipeline push-outs?

George said he knows of no project where these considerations have changed its trajectory, though at a macro level it may push more work into friendlier jurisdictions. Lane said the company has not been delayed by any moratorium on the work it has today, and McKenna noted modular is even less exposed because product ships to wherever the customer site is.

Potential supply chain impact
ETNElectrical segment revenue grew 85% and management cited a higher share of equipment and materials in its cost mix; that could imply greater electrical equipment pull-through, though the mix dampened FIX's own margins.
CARRMechanical gross margin improved to 25.1% with equipment and materials a larger part of cost on early-stage jobs, which may signal rising chiller and rooftop unit shipments, though timing is lumpy.
JCIA larger equipment and materials component in the cost mix during a 43% mechanical revenue increase could be a modest positive read for HVAC equipment suppliers, though management framed it as job-stage driven.
CATManagement noted many data centers are generating their own power anyway; that could support genset demand, though the comment was qualitative and not tied to specific volumes.
CMIThe same on-site power generation remark may carry a read-through to backup generation suppliers, though FIX did not quantify related revenue or equipment spend.
ABBRapid electrical segment growth plus over $100 million of prefabrication CapEx could imply continued demand for electrical components, though FIX does not disclose supplier-level volumes.
EMEFIX described capacity as scarce and customers locking up labor 18 to 24 months out, which may indicate similar tightness across mechanical and electrical peers, though share shifts are not observable from this call.
LGNRecord bookings concentrated in technology work could suggest a strong overall environment for national mechanical/electrical contractors, though FIX's selectivity on terms may differ from peers.
ECGComments that some modular entrants are accepting payment terms FIX considers unfavorable may signal differing risk appetites among competitors, though the call did not name specific firms.