Oklo Inc. earnings recap
Q3 FY2026, reported November 6, 2026 · Beat 2 of last 7 quarters
Oklo Inc. reported Q3 FY2026 EPS of -$0.22, a beat of 18.4% against consensus.
The Buildout is a website built by one person using AI agents, and could have factual errors.
Oklo is spending against physical milestones rather than announcements: structural steel going up at Aurora-Idaho, a PDSA approval that unlocks safety-related construction and procurement, and a 27-module pressure-boundary capacity reservation for 2030-2035. The simultaneous build-out of fabrication (A3F), recycling and isotope processing signals that advanced nuclear's binding constraint is shifting from reactor design to fuel-cycle and heavy-component supply — the categories Oklo is now contracting years ahead of need. Its 900 MW PJM queue and 1.2 GW Ohio campus keep it in the pool of new dispatchable supply being positioned for data-center and industrial load.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $1.0M | $1.9M | — | Not comparable |
| EPS | -$0.27 | -$0.22 | +18.4% | beat |
Revenue: The gap is too large to be a like-for-like comparison (the estimate and the result may be on different bases), so we do not call it a beat or a miss.
These figures come from the same table as our earnings calendar. The write-up below may quote the company's own adjusted or reported figures, which can differ.
Oklo reported a year-to-date net loss of $123.3M through the third quarter, including a $195.2M operating loss offset by $72.4M of interest and dividend income, with $110.9M of cash used in operations and $280.9M of capital spend. The balance sheet held $3.1B of cash, equivalents and marketable securities at September 30 after $2.3B raised through ATM offerings during the first three quarters. At Aurora-Idaho, reactor-area excavation is complete, safety-related rebar and vertical structural steel are being installed, component RFPs have been released with vendors selected, and DOE approved the project's preliminary documented safety analysis, which management compared to an NRC construction permit. Groves-1 was completed for approximately $65M plus roughly $10M of commercially sourced Framatome fuel, and Groves-2 was selected for DOE's Nuclear Energy Launch Pad to pursue an integrated isotope production and processing pilot. PJM withdrew one Virginia interconnection application and FERC dismissed Oklo's complaint, which management said has no read-across to Ohio; separately, DOE selected Oklo for approximately $6.8M to advance recycled metal fuel work with Idaho National Laboratory.
Oklo is still pre-commercial and gave no revenue guidance, but reaffirmed its 2026 cash-use ranges of $120M-$150M used in operations and $400M-$500M of capital spend, funded off a $3.1B liquidity balance. Management laid out concrete near-term milestones: first full fuel assembly at A3F in 2027, recycling pilot commissioning in 2027, construction start on Groves-2 under DOE authorization and a first contracted isotope delivery, with the Aurora-Idaho documented safety analysis not expected until roughly 2028 and full commissioning bracketed at 2028-2029 in the 10-Q — a buffer the CEO attributed to lessons from Groves on plant integration, electrical noise and neutron-monitoring calibration. Capacity is being reserved ahead of need, most visibly the U.S. Forged Rings agreement covering the equivalent of 27 Aurora modules over 2030-2035, with management flagging fuel, vessels, pumps, instrumentation and control, turbines and heat exchangers as the long-lead categories still being worked. The Ohio/Meta campus of up to 1.2 GW and the 900 MW of PJM applications are expected to work through interconnection over roughly the next 24 months. On fuel, management framed third-party fabrication, recycling, conversion/deconversion partnerships and technical services as a potential revenue line, with early services revenue possible within about two years and the real ramp arriving once facilities are scaled. The tone was confident — the CEO described the company as never better positioned and pointed to roughly $75M all-in for Groves as evidence the historical nuclear cost paradigm can be disrupted.
“We completed substantial construction in 229 days and reached first criticality less than a year after groundbreaking. That is an extraordinary pace for a complex industrial facility.”
on Groves-1 execution record
“Reserving capacity now gives us a stronger foundation for coordinating future orders and deployment schedules.”
on U.S. Forged Rings capacity reservation
“If you think about what we have at fuel fabrication, to answer your question in a number of ways, it's really a capability that is, frankly, our goal is to be the leading fuel fabricator for advanced fuel forms.”
on Third-party fuel fabrication ambition
Could you drill into the fuel business and the potential for third-party revenue — timing, what fuel types, and whether it is fed by recycling or external procurement?
CFO said it could take several forms: recycling capacity aimed at non-Oklo customers, fabrication work for others at A3F, investments and partnerships around conversion/deconversion, and possibly technical services even before Oklo is fabricating for third parties. Jake added the goal is to be the leading fabricator for advanced fuel forms — metallic HALEU, oxide fuels for advanced reactors, and support for nitride and zirconium hydride forms — across roughly the 5% to just-under-20% enrichment band, with the facility able to rent floor space to others, partner, or manufacture directly. On timing, he said some early services revenue could come over the next two years, but the real ramp happens after facilities scale into operation and other companies' reactors deploy.
Is the agreement with Meta binding to build the reactor? If not, when do you get there, and what milestones need to occur?
Jake said it is not binding to build the reactor, which he called natural for a project where Meta is acting as a development partner rather than a purely transactional customer; it progresses through site development, long-lead procurement such as fuel, interconnection and then full execution. The CFO added there are binding elements — Meta provided capital that gives it capacity reservation — and that the first big milestone tied to that capital is securing fuel, which Oklo is working on now, with further milestones as the project progresses.
The 10-Q says Aurora-INL comes online 2028 to 2029 — should we read that as a modest pushout to 2029, and if so, why?
Jake said the range reflects buffer for equipment recalibration, retesting and plant integration, drawing directly on Groves-1 experience — citing electrical noise management and the sensitivity of neutron monitoring instrumentation as examples of work that is hard to complete until the plant is fully assembled. He said the team has pulled some schedule to the left but wants margin, and noted the extra time also supports the irradiation, isotope and training roles the plant will serve. He did not commit to a narrower window.