TeraWulf Inc. earnings recap

Q3 FY2026, reported November 6, 2026 · Beat 0 of last 7 quarters

TeraWulf Inc. reported Q3 FY2026 revenue of $76M, a beat of 22.0% against consensus, and EPS of $-0.03, a beat of 83.5%.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full TeraWulf Inc. company page →See the earnings preview →TeraWulf Inc. is in the Operators layer →
What this means for the buildout

TeraWulf's quarter is a data point for the view that the AI buildout constraint has moved from demand to financeable, deliverable power — its answer is long-duration leases to a frontier lab backed by an investment grade credit backstop, paired with a fixed-price EPC. The Google backstop structure and the $19 billion Justified lease could become a template for converting non-investment-grade AI tenants into bankable project debt, which would broaden the pool of capital available to data center construction. Management's insistence on 250 to 500 MW of annual contracting and on not absorbing financing or technology risk suggests pricing discipline may hold even as sector leverage and issuance rise.

Results vs consensus
EstimateActualvs est
Revenue$62M$76M+22.0%beat
EPS-$0.18-$0.03+83.5%beat
What was said

Revenue was $76.2 million versus $44.8 million in Q2, with HPC lease revenue up 97% sequentially to $63 million, or about 83% of the total, consisting of $46 million of rent, $11.3 million of tenant fit-out revenue and $5.4 million of power pass-through. CB-3's FluidStack lease commenced July 13, putting 102 critical MW into revenue service and satisfying the conditions for $600 million of Google credit support to become effective; at CB-4 tenant equipment is energized in the first two of four data halls with rent commencement expected shortly and the remaining halls scheduled for the balance of Q4. Non-GAAP adjusted EBITDA was negative $12.8 million versus negative $18.3 million in Q2, GAAP net income was $709.9 million driven by non-cash Google warrant fair value adjustments and the Abernathy JV gain, and the 17% reported margin compares with an adjusted HPC leasing segment profit margin of approximately 83%. After quarter end the company upsized its revolver to $400 million from $250 million with a $150 million accordion, eliminated the $150 million LC supplement, secured Google's credit backstop on the Justified lease, and signed the definitive Fluor EPC. Cash and restricted cash totaled approximately $2.4 billion as of September 30, including roughly $1.1 billion at the parent, and approximately $2.9 billion of WULF Compute capital expenditures were complete with about $1 billion remaining.

Key metrics
Total Revenue
$76.2M
Up from $44.8M in Q2 FY2026
HPC Lease Revenue
$63.0M
+97% QoQ from $31.9M; ~83% of total revenue ($46M rent, $11.3M tenant fit-out, $5.4M power pass-through)
Justified Contracted Revenue
~$19B
20-year Anthropic lease at the Justified Data Center campus, now supported by a Google credit backstop
Lake Mariner Build Cost
~$8.9M per critical IT MW
Inside original $8M-$10M guidance; ~$2.9B of project capex complete, ~$1B remaining
Annualized Run-Rate Lease Revenue Target
~$700M
Expected on exit of Q1 FY2027, when ~half of contracted critical IT capacity is operating
Management outlook

Management framed the next two quarters as the conversion window: CB-4 comes online this quarter adding up to 168 critical MW, CB-5 follows in Q1, and on exiting Q1 they expect roughly half of contracted critical IT capacity operating and approximately $700 million of annualized run-rate leasing revenue. At Justified, the definitive Fluor EPC covers all three buildings with guaranteed maximum pricing to be established as engineering and procurement advance, and phased ready-for-service deliveries remain targeted from late 2027 through Q2 2028 at an unchanged $10 million to $12 million per critical IT MW. At Muskie, management says it holds a contracted path to an initial gigawatt of front-of-the-meter service and is working with Kentucky Power and AEP to potentially pull forward the second 500 MW into 2029, with a Kentucky PSC filing in the coming weeks for the 760 MW Big Sandy CCGT, approval expected by mid-2027 and generation in 2031. They reiterated the target of contracting an incremental 250 to 500 MW of critical IT capacity annually, and said it can be achieved with the portfolio already controlled. Reported margin was 17% against a long-term target of roughly 85%; management expects reported margins to converge as contracted capacity enters service and pre-revenue costs decline. CFO Patrick Fleury said existing liquidity plus expected Abernathy sale proceeds fund remaining Lake Mariner commitments, remaining Justified equity and interim Muskie letter-of-credit requirements without accessing the equity capital markets.

From the call

“A piece of land next to a transmission line is not a data center. And a queue position is not power.”

on Deliverable power

“We are not going to sign a lease that forces us to issue equity at a valuation we do not believe reflects the value of the company.”

on Capital discipline at Muskie

“We expect reported margins to move toward our long term target as additional contracted capacity enter service, pre revenue costs decline, and the mature HPC lease revenue becomes a larger portion of the overall mix.”

on Margin trajectory

What analysts asked

What gives you confidence in the $10 million to $12 million per megawatt capex estimate for Hawesville given industry cost overruns, how far along is the Fluor design, how much cost is fixed today, and who bears overruns?

Nazar Khan said Justified engineering and drawings are 90% complete and expected at 100% by December 1, long-lead equipment is over 80% procured and will reach 100% by year-end, and roughly 80% of the scope under the Fluor agreement — construction and long-lead equipment — will be buttoned down by early December. On overruns, he pointed to the guaranteed maximum price structure, under which subcontractors bear cost responsibility for their scope and Fluor bears the combination, giving an added layer of protection as the project rolls forward.

If the cost of capital rises after you sign a lease, what mechanisms exist in the contracts to protect your spread, both at Hawesville and on a go-forward basis?

Patrick Fleury said lease terms are confidential but that, similar to WULF Compute, Google has agreed to backstop Anthropic's lease obligations upon commencement through either a mandatory lease assumption or a debt-reducing termination payment. Unlike WULF Compute, TeraWulf is granting Google no incremental upfront equity, the cost of the credit support is borne by the tenant, and the backstop falls away once Anthropic achieves certain investment grade ratings.

On pulling forward the second 500 MW at Muskie, is any upfront investment required from TeraWulf, and is it generation or infrastructure upgrades?

Nazar Khan said the first 500 MW is under an existing ESA with Kentucky Power delivering in 2028, and the next 500 MW requires new generation — Kentucky Power's 760 MW Big Sandy CCGT — with a Kentucky PSC filing in the coming weeks, approval expected by mid-2027 and power in 2031. He said the structure draws a clear line between utility spend and what TeraWulf pays, including an incremental $100 million residential credit paid over 10 years and interest during construction from 2027 to 2031 factored into rates, supporting a full gigawatt prior to the end of 2029.

Potential supply chain impact
FLRThe definitive EPC for all three Justified buildings expands Fluor from early engineering and preconstruction into full engineering, procurement, construction, testing and commissioning with open-book cost reporting and GMP — a potential signal of larger fixed-price data center awards ahead, though scope and margin are not disclosed.
GOOGLGoogle's credit support now backstops the $19 billion Anthropic lease at Justified, on top of its existing Lake Mariner role with FluidStack; the structure — including the backstop stepping away once Anthropic reaches investment grade — may indicate how hyperscalers extend balance sheet support across the AI tenant ecosystem.
IRENTeraWulf's management argued its full turnkey colocation model earns a return on the full $10 million to $12 million per megawatt versus capital-light approaches; competitive positioning on build scope and cost of capital could pressure peers pursuing alternate structures.
CIFRThe call highlighted rising credit spreads and roughly 25 comparable bonds in the market; competitors converting mining sites to HPC leases may face a higher cost of capital absent an investment grade backstop, a potential relative advantage for TeraWulf.
CLSKWith roughly 25 bonds now outstanding in the sector and spreads wider, peer HPC conversions could face more expensive project financing than TeraWulf's backstopped structure, though the comparison depends on each company's contracted tenant credit.