DTE Energy Company (DTE) | The Buildout — AI Infrastructure

Mkt cap · 52-wk · YTD · delayed
Updated Aug 12, 2026Q2 FY2026 reviewed
DTE Energy supplies regulated electricity and grid capacity to hyperscale data centers in Michigan.
2.4 GW hyperscaler load
Oracle 1.4 GW approved; Google 1 GW executed and filed with MPSC.
~$5B Google capex
Incremental generation/storage through 2032, not yet in base plan.
2 GW late-stage deals
Plus 3-4 GW additional data center pipeline over time.
Google approval pending
Contested MPSC case; order expected by Sept 10, 2026.
The Buildout Takeaway
DTE has moved from a conventional Michigan utility to a data-center-driven capital story, with two named hyperscaler contracts and a quantified rate-case stay-out proposal. The open question is whether the Michigan commission clears Google on schedule and whether the late-stage pipeline converts into a third signed deal.
46 analysts·21 Buy25 Hold0 Sell
Median target$160  Range $150–$172 · 9 estimates

2026 operating EPS $7.59-$7.73 · long-term EPS growth 6-8% through 2030 · annual equity $500M-$600M, 2026-2028
Important: The Buildout is a data analytics platform. Content is generated by algorithms and AI agents using public filings, earnings transcripts, and market data. This is not personalized investment advice.
Our View

The Verdict

DTE Energy operates regulated electric and gas utilities in Michigan plus non-utility energy businesses. In the AI infrastructure buildout, it supplies electricity, generation capacity, storage, demand response, and supporting grid infrastructure to hyperscale and co-location data centers, making it a direct utility-shaped link in the AI buildout.

Market Cap
Revenue (TTM)$16.2B
Revenue Growth+14.4%
EBITDA Margin (TTM)24.3%
Net Debt$27.8B
Earnings Beats5 of 7
P/E (TTM)
EV/EBITDA (TTM)

What We Like

  • Oracle data center is MPSC-approved and under construction: 1.4 GW, grid attachment expected by end of 2026 and load ramp over 2-3 years.
  • Google contract executed and filed: 1 GW, full ramp by end of 2028, with roughly $5 billion of incremental generation and storage investment through 2032.
  • Data center pipeline quantified at roughly 2 GW late-stage and 3-4 GW additional; management targets another signed deal before the end of 2026.
  • Affordability mechanism is quantified: roughly $300 million annual customer benefits from Oracle and roughly $1.7 billion over the Google contract life.
  • Reliability outcomes improved: 90% improvement in outage duration from 2023 to 2025 and best all-weather SAIDI in nearly 20 years.

What We’re Watching

  • Google MPSC order expected by September 10, 2026; the case is contested, though management expects no PFD.
  • Electric rate case requests 10.25% ROE, 51% equity, and nearly $800 million of IRM additions by 2030; final order expected February 2027.
  • Vantage 350 MW behind-the-meter agreement was expected over the next several weeks from April 30, 2026, but no update appeared through August 12, 2026.
  • RNG tax credits: 2026 assumption is $50-60 million; DOE/Treasury rules are still being finalized.
Bottom Line

The thesis has strengthened: DTE converted a second hyperscaler into a named, executed contract, quantified its capital upside, and proposed a mechanism to extend the rate-case cadence. But the upside remains regulatory-contingent: Google is not in formal guidance until MPSC approval, the electric rate case is still pending, and the late-stage pipeline has not yet produced a third signed deal. The open question is whether the regulatory and zoning pieces land in time for data-center load to push EPS growth above the 6-8% long-term target.

Next upThe next visible catalyst is the MPSC order on the Google contract, expected by September 10, 2026. It tests whether the roughly $5 billion Google capex layer enters the capital plan and whether the rate-case stay-out can extend.
Last Quarter — Q2 FY2026

Earnings Beat

DTE reported Q2 2026 revenue of $3,336 million and gross margin of 16.1%; EBITDA was $900 million at a 27.0% EBITDA margin. The company separately disclosed first-half 2026 utility investment of more than $2.6 billion, including over $900 million in electric reliability investment.

MetricQ2 FY2026Q1 FY2026Q2 FY2025YoY
Revenue$3.3B$5.1B$3.4B−2.4%
Gross margin16.1%34.6%29.4%-1330bps
EBITDA$900M$895M$911M−1.2%
EPS$1.36$1.19$1.10+23.1%
We’ve also executed an agreement with Google to serve a 1-gigawatt data center. This project represents incremental upside to our current long-term plan and the contract has been submitted to the MPSC for approval.— Joi Harris, President and CEO, 2026-04-30

Management tone: Management's tone shifted from 'working on' to 'executed,' 'filed,' and 'down to the short strokes.' It was confident, specific, and execution-oriented, disclosing named counterparties and quantified capital and affordability figures. It also declined to comment on specific commercial credit terms, citing confidentiality.

Management Guidance

Management reaffirmed 2026 operating EPS guidance of $7.59-$7.73 and said DTE is positioned for the high end. It reaffirmed long-term operating EPS growth of 6-8% through 2030 and annual equity issuance of $500 million-$600 million in 2026 through 2028, with similar levels through 2030. Google and additional data center upside are not in formal guidance and will be incorporated only after MPSC approval.

Business Trajectory

Trajectory

Revenue rose from $4,440 million in Q1 2025 to $5,141 million in Q1 2026, then fell to $3,336 million in Q2 2026, down 2.4% year over year. Gross margin moved from 34.6% in Q1 2026 to 16.1% in Q2 2026. Energy Trading is the largest revenue line and is low-margin and volatile.

Revenue & Margin Trajectory
RevenueGross margin$0$2.0B$4.0B$2.9B$2.9B$3.2B$2.9B$3.2B$3.3B$3.8B$3.2B$3.5B$3.8B$3.5B$2.9B$3.1B$3.1B$3.0B$2.6B$3.1B$3.3B$3.6B$3.0B$3.7B$4.6B$4.6B$4.9B$5.3B$4.5B$3.8B$2.7B$2.9B$3.4B$3.2B$2.9B$2.9B$3.4B$4.4B$3.4B$3.5B$4.2B$5.1B$3.3B28%16%Q3'16Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26Q2
RevenueGross margin$0$2.0B$4.0B$2.9B$2.9B$3.2B$2.9B$3.2B$3.3B$3.8B$3.2B$3.5B$3.8B$3.5B$2.9B$3.1B$3.1B$3.0B$2.6B$3.1B$3.3B$3.6B$3.0B$3.7B$4.6B$4.6B$4.9B$5.3B$4.5B$3.8B$2.7B$2.9B$3.4B$3.2B$2.9B$2.9B$3.4B$4.4B$3.4B$3.5B$4.2B$5.1B$3.3B28%16%Q3'16Q4Q1'17Q2Q3Q4Q1'18Q2Q3Q4Q1'19Q2Q3Q4Q1'20Q2Q3Q4Q1'21Q2Q3Q4Q1'22Q2Q3Q4Q1'23Q2Q3Q4Q1'24Q2Q3Q4Q1'25Q2Q3Q4Q1'26Q2
Gross margin as reported.
Share Price — 12 Months
$50$100$150$052-wk high $154Aug '25NovFeb '26MayAug '26
52-week range $129–$154.
Share Price — 12 Months
$50$100$150$052-wk high $154Aug '25NovFeb '26MayAug '26
52-week range $129–$154.
The Numbers

The Model

The model projects FY+1 revenue of $17,500 million and EBITDA of $4,602 million, a 26.3% EBITDA margin, rising to FY+2 revenue of $19,500 million and EBITDA of $5,265 million, a 27.0% margin. The near term is anchored by the $36.5 billion five-year capital plan and the start of Oracle and Google load ramp; FY+2 reflects more contracted data-center load layering onto rate base.

Revenue & EBITDA Projections
REVENUE$15.6B$17.5B$19.5BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$4.1B$4.6B$5.3B27.0%FY25FY+1 (E)FY+2 (E)
REVENUE$15.6B$17.5B$19.5BFY25FY+1 (E)FY+2 (E)EBITDA & MARGIN$4.1B$4.6B$5.3B27.0%FY25FY+1 (E)FY+2 (E)
Solid bars are reported actuals; outlined bars are model projections — not company guidance.
MetricFY2025Next FY (E)Following FY (E)
Revenue$15.6B$17.5B$19.5B
YoY Growth+12.0%+11.4%
EBITDA$4.1B$4.6B$5.3B
EBITDA Margin26.5%26.3%27.0%

Projections are the median of 5 independent model runs. The model’s revenue sits 17.9% above analyst consensus.

Management reaffirmed 2026 operating EPS guidance of $7.59-$7.73 and said DTE is positioned for the high end. It reaffirmed long-term operating EPS growth of 6-8% through 2030 and annual equity issuance of $500 million-$600 million in 2026 through 2028, with similar levels through 2030. Google and additional data center upside are not in formal guidance and will be incorporated only after MPSC approval.

What Could Go Right — and Wrong

What good looks like
  • MPSC approves Google by September 10, 2026, adding roughly $5 billion of incremental generation and storage investment through 2032.
  • Rate-case stay-out is adopted in the current case, extending DTE's regulatory runway beyond 2028.
  • Third data center contract is signed before the end of 2026, converting the roughly 2 GW late-stage pipeline into a visible third anchor.
  • Vantage 350 MW behind-the-meter agreement closes and the model replicates across other hyperscalers or co-locators.
  • Existing data center customers expand once on the system, lifting load toward the roughly 40% full-ramp concentration.
What could go wrong
  • MPSC rejects or materially delays the Google contract, removing the $5 billion capex layer.
  • Electric rate case final order is weak on ROE, equity layer, or IRM, undermining the stay-out.
  • Oracle uses its one-year delay option or the Google ramp slips beyond the end of 2028.
  • No third deal is signed by the end of 2026, raising doubts about the 2 GW late-stage pipeline.
  • RNG tax credit final rules disappoint, pressuring the high end of 2026 guidance.
What’s Next

Looking Ahead

The next 12 months revolve around regulatory and contract conversion. DTE expects an MPSC order on Google by September 10, 2026, followed by a capital plan update at EEI in fall 2026. Management is also targeting a third data center deal before the end of 2026, and a final electric rate case order is expected in February 2027.

Catalysts
  • Sept 10, 2026Google MPSC order — Approval would clear roughly $5B capex; rejection removes upside.
  • Fall 2026 (EEI)Capital plan update — Shows when the ~$5B Google capex lands by year.
  • Before end 2026Third data center deal — Tests the ~2 GW late-stage pipeline conversion.
  • 2026Trenton Channel + Belle River — 220 MW storage and 1,300 MW gas peaker completion targeted.
  • February 2027Electric rate case order — Final decision on 10.25% ROE, 51% equity, IRM additions.
Numbers

Financials

Annual Summary

MetricFY2024FY2025TTMYoY
Revenue$12.5B$15.6B$16.2B+25.4%
Gross Margin35.0%39.2%36.7%+427bps
EBITDA$3.8B$4.1B$33.0B+7.7%
EBITDA Margin30.9%26.5%24.3%436bps
Net Income$1.4B$1.5B$1.3B+4.1%
Free Cash Flow−$824M−$1.0B−$6.7B
Net Cash

Key Ratios (Trailing)

Valuation
  • P/E TTM
  • EV/EBITDA TTM
  • EV/Revenue TTM
  • Price/FCF TTM
Profitability
  • Gross Margin (TTM)36.7%
  • EBITDA Margin (TTM)24.3%
  • Net Margin (TTM)8.1%
  • ROIC4.0%
  • FCF Conversion-48.9%
  • SBC / Revenue0.0%
Reference

The Company

DTE Energy is a Michigan-based energy company whose principal operations are two regulated utilities. DTE Electric generates, purchases, distributes, and sells electricity to about 2.3 million customers in southeastern Michigan; DTE Gas serves about 1.4 million natural gas customers across Michigan. It also operates DTE Vantage, a non-utility renewable and custom energy solutions business, and an Energy Trading segment. In the AI buildout, DTE supplies electricity, capacity, storage, demand response, and grid infrastructure to hyperscale and co-location data centers.

DTE Electric and DTE Gas operate as regulated utilities in their Michigan service territories, and DTE Electric's interconnections are generally owned and operated by ITC Transmission, an unrelated company. The regulated model means revenue and margins depend on rate cases, cost recovery, and infrastructure-recovery mechanisms. DTE has a 14 MW battery storage site in Wayne County and about 2,500 MW of renewables online; it is building about 900 MW/year of renewables on average over the next five years.

Business Segments

DTE Electric
Approximately 2.3 million customers in southeastern Michigan
Generates, purchases, distributes, and sells electricity; carries the Oracle and Google data center load.
Growth driver: Data center load and regulated rate-base expansion.
DTE Gas
Approximately 1.4 million customers throughout Michigan
Full-cycle natural gas utility: purchase, storage, transportation, distribution, and sale.
Growth driver: Gas rate case and infrastructure-recovery mechanism growth.
DTE Vantage and Energy Trading
Non-utility renewables, custom energy solutions, and energy marketing/trading
Includes behind-the-meter data center opportunity and energy trading operations.
Growth driver: Behind-the-meter data center project and trading timing.

Competitive Landscape

DTE Electric and DTE Gas operate as regulated utilities in their Michigan service territories. For load physically located in its territory, DTE is hard to replace because customers must connect to the local distribution and transmission system that DTE Electric serves and that interconnects through ITC Transmission. DTE Vantage is more exposed to competition because it competes for behind-the-meter and custom energy solution projects.

Supply Chain

DTE sits between fuel and equipment suppliers and a large Michigan customer base, with hyperscale data centers as a fast-growing new load. Named data center customers are Oracle and Google; LG Energy Solution Vertech is the most concrete storage-supplier link.

Supplier
LG Energy Solution Vertech
6 GWh battery energy storage systems over two years
Supplier
Vector Pipeline L.P.
Firm gas pipeline transportation capacity, expiry 2040
Supplier
ANR Pipeline Company
Firm gas pipeline transportation capacity, expiry 2028
Contracted hyperscaler load in Michigan
DTE
Generates, buys, distributes, and sells electricity; buys, stores, transports, distributes, and sells natural gas.
Oracle
1.4 GW
Approved; construction underway; grid attachment expected by end 2026.
Google LLC
1 GW
Executed and filed; MPSC order expected by Sept 10, 2026.
Electric customers
2.3 million
Residential, commercial, and industrial customers in southeastern Michigan.
Natural gas customers
1.4 million
Residential, commercial, and industrial customers throughout Michigan.

Analysis updated Aug 12, 2026, reviewing Q2 FY2026. Prices delayed. Built with The Buildout’s published methodology. Not investment advice. No positions held. © The Buildout 2026.