Cipher Mining Inc. earnings recap
Q3 FY2026, reported November 2, 2026 · Beat 2 of last 5 quarters
Cipher Mining Inc. reported Q3 FY2026 revenue of $27M, a miss of 32.1% against consensus, and EPS of $-0.22, a beat of 12.0%.
The Buildout is a website built by one person using AI agents, and could have factual errors.
Cipher is converting a bitcoin-mining footprint into contracted HPC colocation, with 700 gross MW across three campuses now representing $16.6 billion of contracted revenue and first rent collected — evidence that the power-scarce, lease-backed model can reach revenue. The company's push into laterals supporting up to 2.5 GW of on-site generation, with first power potentially in late 2027 and ~1 GW of active lease discussions, underscores that grid interconnection queues, not chip supply, are increasingly the gating factor for AI capacity. At the same time, the Barber Lake cost reset to $13 million per IT MW and management's expectation of continued labor inflation in 2027 highlight margin pressure across the physical buildout.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $39M | $27M | -32.1% | miss |
| EPS | -$0.25 | -$0.22 | +12.0% | beat |
Cipher reported Q3 revenue of $27 million, up from $25 million in Q2, including its first HPC lease revenue after delivering 18 MW of critical IT capacity at Black Pearl in August, ahead of schedule and at the tenant's request. The company amended and expanded the Barber Lake lease, doubling the base term to 20 years and lifting site contracted revenue to roughly $9.1 billion — adding $5.2 billion of incremental rent — while agreeing to absorb about $359 million of tenant-directed change orders and share construction cost overruns 50/50 through rentalization. Cost to Cipher per critical IT megawatt at Barber Lake rose to $13 million from an original $9-11 million underwriting range, but management said the additional rent restored average yield on cost to approximately 15%, versus approximately 13% absent the amendment. GAAP net income was $32 million versus a $268 million loss in Q2 on a $127 million non-cash warrant gain, and adjusted EBITDA improved to a $10 million loss. Subsequent to quarter end, Cipher issued $850 million of 0% convertible notes due 2032 at a $15.31 conversion price with a capped call on ~$90 million, and equitized approximately $166 million of its 1.75% 2030 notes.
Management did not issue formal revenue or EBITDA guidance, but framed the forward path around delivery schedules and lease discipline. Barber Lake data halls are scheduled to come online from Q4 2026 through Q1 2027 under the amended phased framework, Black Pearl's remaining Phase 1 halls are in MEP fit-out with Phase 2 electrical work underway, and Stingray shell construction is expected to be complete in Q4 2026, with construction ramping over the coming quarters, additional site grading underway that could support future expansion phases, and additional capacity across all three sites expected to come online in phases over the coming months. Colchis, the 1 GW front-of-the-meter site, has a conditional base load classification with final classification expected in December; Tyler Page called it "a crown jewel" and said interest from prospective tenants "has been exceptional." The company is developing lateral natural gas pipelines capable of supporting up to 2.5 GW of generation with first power potentially as early as late 2027, and is in "early but active commercial discussions" for roughly 1 GW of on-site-generation-powered leases. On costs, management expects labor and build-cost inflation to persist into 2027 and said it will hold new leases until design sets are 30% to 60% complete and will evaluate tenant construction-reimbursement structures to protect yield-on-cost spreads. Capital position: pro forma for the October $850 million 0% convertible offering and Barber Lake funding, ~$724 million of unrestricted cash, with all three contracted projects funded through completion.
“I want to encourage all of our investors to take the view that we are building expressways for AI to come to market and we are charging a long term toll.”
on Long-term contracted model
“This was not simply additional capital required to complete the project. It was an incremental investment made in exchange for materially more valuable contract.”
on Barber Lake capital allocation
“We have held off on executing them until we have agreed 30% to 60% design sets, that vastly narrows the scope of the variability of those costs.”
on New lease underwriting discipline
Could you update us on Barber Lake and broader industry build-cost inflation — how should we think about future capex per megawatt, and can you raise rental rates in line with cost inflation to maintain development yields?
Tyler Page said the environment is inflationary for labor and that 2027 will likely continue that trend, but tenants recognize costs are rising and have so far shown willingness to increase rent in line with higher financing costs. He added that structures are evolving, with tenants increasingly willing to entertain capex reimbursement agreements ahead of lease signing to preserve schedule and secure long-lead equipment. Gregory Mumford noted that of roughly 20-25 high-yield issuances financing data center construction, three of the four tightest-trading bonds by spread are Cipher's, which he said supports continued efficient access to project capital if the company stays focused on high-quality tenants.
Can you talk more about the lateral natural gas pipelines you're developing, and how you address the need for equipment to convert that gas into power?
Tyler Page said time-to-power is what drives tenant interest in on-site generation, and that tenants prefer sites where they can do their own generation while retaining a path to grid connection. On equipment, he said there are not enough turbines and reciprocating engines in the world, and the envisioned structure is for a well-known, creditworthy IPP to work directly with the tenant to arrange and operate the equipment under a power purchase agreement, leaving Cipher to finance and build the data center. He said Cipher is already in advanced discussions on about a gigawatt of such deals with multiple interested tenants at multiple sites.
On the additional Barber Lake costs — when does that cost actually get locked in, given GC labor is typically contracted at signing, and what drove the increase?
Tyler Page said the initial leases were signed quickly with design sets that were not far advanced, which produced more change orders than expected and cascading cost and schedule effects; future leases will be held until 30% to 60% design sets are agreed, with earlier risk transference to GCs and subcontractors. Gregory Mumford separated tenant-directed change orders — of which the tenant reimburses ~$50 million while Cipher invests ~$359 million — from general scope evolution and labor inflation, which is shared 50/50 and recovered through rentalization at a contracted return. He said without the amendment the all-in cost would have been ~$12.3 million per critical IT megawatt; with it, cost is ~$13 million per IT MW but yield on cost is restored to roughly 15%. Tyler Page also noted the company had that morning delivered the RFS notice for the first 51 MW of critical IT at Barber Lake.