Keel Infrastructure Corp. earnings recap
Q3 FY2026, reported November 5, 2026 · Beat 1 of last 6 quarters
Keel Infrastructure Corp. reported Q3 FY2026 EPS of $-0.10, a miss of 13.2% against consensus.
The Buildout is a website built by one person using AI agents, and could have factual errors.
Keel's quarter is a supply-side data point for the AI buildout: 478 MW of near-term power sat unleased while Pennsylvania rewrote its permitting framework, even as the four largest capacity buyers guided to more than $800 billion of 2026 capex and roughly $1.8 trillion of contracted backlog they say they cannot yet serve. Management argues that each delayed project — an estimated $200 billion of U.S. data center projects blocked or delayed in the first half alone — removes 2027-28 power from the market and raises the value of what remains, a thesis that favors developers who actually energize. The offsetting signal is timing: with Pennsylvania revenues now pointed at early 2028, the scarcity premium accrues to delivery, not to announced megawatts.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $19M | $28M | — | Not comparable |
| EPS | -$0.09 | -$0.10 | -13.2% | miss |
Revenue: The gap is too large to be a like-for-like comparison (the estimate and the result may be on different bases), so we do not call it a beat or a miss.
Keel reported Q3 2026 revenue of $28 million versus $68 million a year earlier, reflecting the second-quarter decommissioning of U.S. Bitcoin mining and a lower average Bitcoin price; operating loss narrowed to $8 million from $18 million, while loss from continuing operations was $62 million, or $0.10 per share, driven primarily by a $55 million noncash unrealized loss on capped calls tied to the 2025 convertible notes. Adjusted EBITDA was negative $27 million versus positive $19 million in the prior-year period, and cash SG&A has averaged $24 million per quarter through the first nine months of 2026. Keel sold 2,520 Bitcoin during the quarter for $192 million of proceeds and ended September with nominal holdings; only Canadian mining remains active at roughly 5-6 exahash, producing a couple of Bitcoin a day, and management said it will not invest further in it. Operationally, Moses Lake received every required approval and broke ground, Sharon is down to its final state environmental permit (already issued in draft), and Panther Creek has three remaining permits, one in draft and two in standard technical review. Management also disclosed a potential Allentown, Pennsylvania site — a fully constructed power shell with 75 MW of 2027 PPL power — under diligence but excluded from the ~2 GW expansion portfolio.
Management withdrew its May target of signing three leases by year-end, attributing the slip to Pennsylvania's August 18 executive order — which took data centers out of the state's fast-track permitting program — and said permitting and commercial timelines moved back by months; it declined to give any lease timing guidance for any site going forward. The expansion load study update at Panther Creek and Scrubgrass, previously expected as early as December or January, is now expected in Q1 2027. Power delivery schedules under the ESAs are unchanged: the Sharon and Panther Creek substations are expected to energize in 2027, with revenues beginning in early 2028 and each site ramping capacity through 2028, while Moses Lake remains on track to be the first site energized in 2027. The executive order prompted a re-engineered backup power solution centered on battery storage, which management said was always in the plan and budget and does not meaningfully change project economics or timing for tenants; management also noted that the permits currently before the DEP are not subject to the order's new requirements, though the order removed data centers from the state's fast-track permitting program. CFO Jonathan Mir said Keel does not see a need for external debt or equity financing ahead of signing a lease, funding Stages 1 and 2 of a three-stage gate process from the balance sheet and Stage 3 with project financing at lease signing; Moses Lake is expected to be financed through private credit and its proceeds recycled into the equity required for Sharon and Panther Creek, where management is targeting investment-grade tenants or counterparties backed by an investment-grade wrap.
“In May, we set a goal to sign 3 leases by year-end. The new regulatory framework in Pennsylvania has moved our permitting and commercial time lines back by months, and we no longer expect to sign 3 leases this year.”
on Lease target withdrawn
“a lease is not a trophy for a press release. It's a 15-year commitment, and we will not sign the wrong lease at the wrong price just to hit a date.”
on Commercial discipline
“We currently do not see the need for any external debt or equity financing in advance of signing a lease.”
on Financing plan
How are lease structures and terms evolving in tenant discussions over the last 90 to 180 days?
Gagnon said terms vary considerably by site and that competitive tension is building at all three as they advance toward commissioning dates. Tenant sensitivities now center on permits, community and financing; management believes it has given counterparties confidence on the first two, while financing is being worked through with each party. He said terms are getting more competitive and more tense in negotiations as supply in the market appears to shrink, and that the mix of counterparties differs by site — the largest compute buyers focus on Panther Creek and Sharon, while neoclouds and emerging companies look at Moses Lake or Sharon depending on scale and time-to-energy.
What is the expected timing on the remaining permits at Sharon and Panther Creek, and are those milestones effectively closing conditions for contracts with prospective tenants?
Gagnon said Sharon is down to its last environmental permit, already in draft form, which he described as meaning regulators have completed extensive review and intend to approve it, subject to a remaining review window and possible revision. Panther Creek has three remaining — one in draft and two in technical review — all submitted and processing with no red flags raised, though he said it is hard to guide on timing given the DEP backlog, which is a changing condition in real time. He emphasized that Keel was far enough advanced before the executive order that the impact is minimal because most permits were already in process.
How is the team navigating the supply chain for long lead time equipment given data center demand and restricted supply?
Gagnon said Keel has secured all long lead time equipment needed for the power connection — substation transformers and powered-land build-out — across all three sites, with Moses Lake equipment contracted and largely in hand. For data center equipment at Sharon and Panther Creek, Keel deliberately commits to manufacturing slots rather than specific equipment purchases, which minimizes deposits and preserves flexibility to match the end tenant's configuration. He framed time-to-RFS as three buckets — permitting, leasing and long lead equipment — and said leasing is the critical path at Panther Creek, which is what the slot strategy protects.