Keel Infrastructure Corp. earnings recap

Q3 FY2026, reported November 5, 2026 · Beat 1 of last 6 quarters

Keel Infrastructure Corp. reported Q3 FY2026 EPS of $-0.10, a miss of 13.2% against consensus.

The Buildout is a website built by one person using AI agents, and could have factual errors.

Go to the full Keel Infrastructure Corp. company page →See the earnings preview →Keel Infrastructure Corp. is in the Operators layer →
What this means for the buildout

Keel's quarter is a supply-side data point for the AI buildout: 478 MW of near-term power sat unleased while Pennsylvania rewrote its permitting framework, even as the four largest capacity buyers guided to more than $800 billion of 2026 capex and roughly $1.8 trillion of contracted backlog they say they cannot yet serve. Management argues that each delayed project — an estimated $200 billion of U.S. data center projects blocked or delayed in the first half alone — removes 2027-28 power from the market and raises the value of what remains, a thesis that favors developers who actually energize. The offsetting signal is timing: with Pennsylvania revenues now pointed at early 2028, the scarcity premium accrues to delivery, not to announced megawatts.

Results vs consensus
EstimateActualvs est
Revenue$19M$28M—Not comparable
EPS-$0.09-$0.10-13.2%miss

Revenue: The gap is too large to be a like-for-like comparison (the estimate and the result may be on different bases), so we do not call it a beat or a miss.

What was said

Keel reported Q3 2026 revenue of $28 million versus $68 million a year earlier, reflecting the second-quarter decommissioning of U.S. Bitcoin mining and a lower average Bitcoin price; operating loss narrowed to $8 million from $18 million, while loss from continuing operations was $62 million, or $0.10 per share, driven primarily by a $55 million noncash unrealized loss on capped calls tied to the 2025 convertible notes. Adjusted EBITDA was negative $27 million versus positive $19 million in the prior-year period, and cash SG&A has averaged $24 million per quarter through the first nine months of 2026. Keel sold 2,520 Bitcoin during the quarter for $192 million of proceeds and ended September with nominal holdings; only Canadian mining remains active at roughly 5-6 exahash, producing a couple of Bitcoin a day, and management said it will not invest further in it. Operationally, Moses Lake received every required approval and broke ground, Sharon is down to its final state environmental permit (already issued in draft), and Panther Creek has three remaining permits, one in draft and two in standard technical review. Management also disclosed a potential Allentown, Pennsylvania site — a fully constructed power shell with 75 MW of 2027 PPL power — under diligence but excluded from the ~2 GW expansion portfolio.

Key metrics
Liquidity (as of Nov 4, 2026)
$780M
Unrestricted cash, plus $53M of restricted cash collateralizing letters of credit posted for expansion capacity
Q3 Revenue
$28.0M
Down from $68M in Q3 2025 on the Q2 decommissioning of U.S. Bitcoin mining and lower average Bitcoin price
Adjusted EBITDA
-$27M
Versus +$19M a year ago; operating loss narrowed to $8M from $18M, while loss from continuing operations was $62M ($0.10/share) on a $55M noncash capped-call mark
Secured near-term power
478 MW
Moses Lake, Sharon (110 MW) and Panther Creek (350 MW, expandable toward 500 MW+); beyond that, the expansion portfolio is about 2 GW excluding Allentown (Scrubgrass up to 1.3 GW, Quebec 96 MW), with a potential 75 MW Allentown site — a fully constructed power shell with 2027 PPL power — being explored separately
Pre-lease capital commitments
$380M
Total through end of 2028; roughly half tied to finishing Moses Lake, most of the rest to substation and fiber work at Sharon and Panther Creek
Management outlook

Management withdrew its May target of signing three leases by year-end, attributing the slip to Pennsylvania's August 18 executive order — which took data centers out of the state's fast-track permitting program — and said permitting and commercial timelines moved back by months; it declined to give any lease timing guidance for any site going forward. The expansion load study update at Panther Creek and Scrubgrass, previously expected as early as December or January, is now expected in Q1 2027. Power delivery schedules under the ESAs are unchanged: the Sharon and Panther Creek substations are expected to energize in 2027, with revenues beginning in early 2028 and each site ramping capacity through 2028, while Moses Lake remains on track to be the first site energized in 2027. The executive order prompted a re-engineered backup power solution centered on battery storage, which management said was always in the plan and budget and does not meaningfully change project economics or timing for tenants; management also noted that the permits currently before the DEP are not subject to the order's new requirements, though the order removed data centers from the state's fast-track permitting program. CFO Jonathan Mir said Keel does not see a need for external debt or equity financing ahead of signing a lease, funding Stages 1 and 2 of a three-stage gate process from the balance sheet and Stage 3 with project financing at lease signing; Moses Lake is expected to be financed through private credit and its proceeds recycled into the equity required for Sharon and Panther Creek, where management is targeting investment-grade tenants or counterparties backed by an investment-grade wrap.

From the call

“In May, we set a goal to sign 3 leases by year-end. The new regulatory framework in Pennsylvania has moved our permitting and commercial time lines back by months, and we no longer expect to sign 3 leases this year.”

on Lease target withdrawn

“a lease is not a trophy for a press release. It's a 15-year commitment, and we will not sign the wrong lease at the wrong price just to hit a date.”

on Commercial discipline

“We currently do not see the need for any external debt or equity financing in advance of signing a lease.”

on Financing plan

What analysts asked

How are lease structures and terms evolving in tenant discussions over the last 90 to 180 days?

Gagnon said terms vary considerably by site and that competitive tension is building at all three as they advance toward commissioning dates. Tenant sensitivities now center on permits, community and financing; management believes it has given counterparties confidence on the first two, while financing is being worked through with each party. He said terms are getting more competitive and more tense in negotiations as supply in the market appears to shrink, and that the mix of counterparties differs by site — the largest compute buyers focus on Panther Creek and Sharon, while neoclouds and emerging companies look at Moses Lake or Sharon depending on scale and time-to-energy.

What is the expected timing on the remaining permits at Sharon and Panther Creek, and are those milestones effectively closing conditions for contracts with prospective tenants?

Gagnon said Sharon is down to its last environmental permit, already in draft form, which he described as meaning regulators have completed extensive review and intend to approve it, subject to a remaining review window and possible revision. Panther Creek has three remaining — one in draft and two in technical review — all submitted and processing with no red flags raised, though he said it is hard to guide on timing given the DEP backlog, which is a changing condition in real time. He emphasized that Keel was far enough advanced before the executive order that the impact is minimal because most permits were already in process.

How is the team navigating the supply chain for long lead time equipment given data center demand and restricted supply?

Gagnon said Keel has secured all long lead time equipment needed for the power connection — substation transformers and powered-land build-out — across all three sites, with Moses Lake equipment contracted and largely in hand. For data center equipment at Sharon and Panther Creek, Keel deliberately commits to manufacturing slots rather than specific equipment purchases, which minimizes deposits and preserves flexibility to match the end tenant's configuration. He framed time-to-RFS as three buckets — permitting, leasing and long lead equipment — and said leasing is the critical path at Panther Creek, which is what the slot strategy protects.

Potential supply chain impact
APLDPeer-group competitor in power-first HPC development; Keel's citation of roughly $200 billion of blocked or delayed U.S. projects in H1 could tighten near-term capacity and may support pricing for peers holding contracted 2027-28 power.
BTDRPeer-group competitor converting mining footprints to HPC; Keel's exit from U.S. mining and sale of 2,520 Bitcoin for $192 million may illustrate how miners are funding conversion, a possible read-across on capital allocation.
CIFRPeer-group competitor; Keel's Pennsylvania permitting drag from the August executive order shows state-level regulatory and community risk intensifying, which could affect how other developers sequence site selection and permitting.
CLSKPeer-group competitor in Bitcoin mining; Keel's negative $27 million adjusted EBITDA after winding down U.S. mining may signal margin pressure pure-play miners face at prevailing Bitcoin prices.
CORZPeer-group competitor pursuing HPC colocation; Keel's insistence on investment-grade tenants or investment-grade wraps for project financing could indicate how lenders are pricing counterparty credit in the sector.
DOCNPeer-group competitor in cloud services; Keel identified neoclouds and GPU clouds as prospective tenants at Moses Lake and Sharon, so cloud capacity demand could eventually show up as lease demand for peers.
GLXYPeer-group competitor; Keel's plan to lock financing terms at lease signing to avoid basis risk in a more selective debt market may be a relevant template for peers funding HPC buildouts.
HIVEPeer-group competitor with a Bitcoin-to-HPC transition; Keel's 96 MW Quebec site awaiting final ministerial approval may indicate the pace of provincial approvals that similar Canadian conversions could face.
HUTPeer-group competitor; Keel argued that Canadian data-sovereignty legislation supports a compute premium versus U.S. pricing, a potential tailwind for peers with Canadian capacity.
IRENPeer-group competitor with mining and HPC ambitions; Keel said electricity price barely comes up with tenants relative to time-to-power, which could suggest delivery dates rather than power cost are the deciding factor across the sector.