WhiteFiber, Inc. Ordinary Shares earnings recap
Q3 FY2026, reported November 10, 2026 · Beat 1 of last 5 quarters
WhiteFiber, Inc. Ordinary Shares reported Q3 FY2026 revenue of $24M, a miss of 19.7% against consensus.
The Buildout is a website built by one person using AI agents, and could have factual errors.
WhiteFiber is a small-cap read on where the AI infrastructure bottleneck sits: 40 MW retrofitted and billing in under 11 months, a $300 million project facility, and roughly $750 million of cloud contracts signed in a single quarter point to power-and-shell scarcity rather than demand scarcity. The company's insistence on investment-grade project-level credit and the disclosure that prepayments cover about 40% of CapEx on signed, not-yet-live deployments may signal tighter underwriting discipline spreading through the neocloud layer. The 105 MW in advanced 2027 discussions, the ~45 MW NC-1 expansion and the Duke power timeline are the items that determine whether that contracted demand converts to revenue on schedule.
| Estimate | Actual | vs est | ||
|---|---|---|---|---|
| Revenue | $30M | $24M | -19.7% | miss |
| EPS | -$0.37 | -$2.44 | — | Not comparable |
EPS: The gap is too large to be a like-for-like comparison (the estimate and the result may be on different bases), so we do not call it a beat or a miss.
Third quarter revenue was $24.0 million, up 19% year-over-year, with colocation revenue more than tripling to $5.6 million on MTL3 and the initial contribution from NC-1, which produced $1.1 million of lease revenue after the first 20 MW hall went into service on September 23. Cloud revenue of $18.1 million included a $3.4 million termination fee; excluding it, cloud revenue declined approximately 18% year-over-year as one customer transitioned out ahead of new deployments. Adjusted EBITDA was approximately breakeven versus positive $2.3 million in the prior-year quarter, and gross profit excluding depreciation and amortization was $13.7 million at roughly a 57% margin versus 59% last quarter, while the $101.4 million net loss included an $80.8 million induced conversion expense tied to the August convertible note repurchase. NC-1 reached full 40 MW billing on November 9 after switchgear shipping and commissioning issues pushed the ramp later than the August target, with management saying it does not expect late delivery penalties, and the quarter also brought a $300 million secured credit facility for NC-1 plus roughly $750 million of new cloud contract value across 5 customers. Remaining performance obligations were $729 million at September 30, with roughly $421 million of future lease payments excluded after certain colocation agreements were reclassified as leases for accounting purposes.
Management framed 2027 as the conversion year: NC-2 and NC-3, acquired for $60 million in Yadkin County, are targeted for initial capacity in late 2027, the ~$25 million MTL2 build is targeted ready in early 2027 ahead of Q2 GPU services, and the Paris deployment is targeted for initial service in January with full deployment in February. On cloud, they expect Q4 revenue roughly in line with Q3's $18.1 million, then significant sequential growth in Q1 and Q2 2027 as contracted deployments enter service, targeting about $365 million of annualized cloud revenue by mid-2027 and more than $50 million of managed services ARR by the end of Q1 2027. Development costs are tracking just below $9 million per gross megawatt, within the original $7 million to $9 million budget range, and management said current customer proposals would more than offset cost increases, implying higher yields than NC-1. They set a new underwriting standard for future leases — investment-grade credit at the project level, either directly or through a full credit wrap, plus committed debt arranged alongside the customer agreement — and said they would hold that standard even if it affects delivery dates. Demand was described as substantially stronger than a year ago, with about 105 MW of gross capacity in advanced customer discussions for 2027 delivery (roughly 45 MW of NC-1 expansion and 60 MW across NC-2 and NC-3), including investment-grade counterparties and Fortune 100 interest for sub-50 MW deployments; management acknowledged the sharp decline in AI infrastructure shares, including its own, but said the opportunity ahead has strengthened.
“All 40 megawatts are now billing under the contract.”
on NC-1 reaches full billing
“Since our last earnings call, we've signed approximately $750 million in new contract value across 5 customers.”
on Cloud contract momentum
“We require investment-grade credit at the project level, either directly from the customer or through a full credit wrap.”
on Underwriting discipline
Given the supply chain issues at NC-1, what are the learnings and what steps are you taking to derisk the supply chain for NC-2 and NC-3, and how much is already on order?
President Billy Krassakopoulos said NC-1 was built on an aggressive timeline — roughly 10 months — and that for similar projects the schedule will be a little longer, long-lead equipment will be preordered further in advance, and project management will be strengthened internally and with contractors and subcontractors. The same retrofit playbook will be applied at NC-2 and NC-3, which sit about 55 miles from NC-1 and can use the same workforce and general contractor.
Across the 5 cloud contracts and $750 million of contracted revenue, who bears the risk across delivery constraints, particularly reliance on colocation partners beyond Montreal, and how is the GPU supply chain looking?
Michael Francisco, Vice President of WhiteFiber Cloud U.S., said the company does not sign customer agreements or MSAs until it has clear visibility into the data center ready-for-service timeline and commitments from the selected OEM for GPUs and other cluster components — which sometimes means pushing a customer's desired date but lets it hit the dates it commits to. He said WhiteFiber largely stopped speculative purchasing this year, procuring at the point it receives customer prepayment, with exceptions such as NVIDIA networking fabric where lead times are long enough that the company ordered ahead in confidence it would be sold.
Cloud contracts average about 4 years — how do you think about term length going forward and balance term against pricing differences?
Michael Francisco said the primary rule is that no contract is structured without full payback within the original term. Customers are now pushing for longer terms than a year or even earlier this year: GPU capacity is hard to find, and the assumption that a shorter deal could be renegotiated cheaper has not played out — he noted H100 costs are higher today than at launch, so a two-year contract signed then would reprice upward. Longer terms let WhiteFiber secure payback while blending rates across the life of the deal to give customers relief on average cost.